• Tidak ada hasil yang ditemukan

Basic features of a Marine HV Power Supply and Distribution System

Dalam dokumen Buku Marine High Voltage Technology (Halaman 145-161)

High Voltage Generation and Distribution

4.8 Basic features of a Marine HV Power Supply and Distribution System

High Voltage Generation and Distribution

Figure 4.25 Isolation of the NER

Chapter 4

Figure 4.26 Typical Marine HV Power Supply and Distribution System

Large power consumers such as thrusters, propulsion motors, air-conditioning compressors and HV transformers are fed directly from the HV switchboard. An economical HV system must be simple to operate, reasonably priced and one that requires a minimum of maintenance over the life of the ship. On a HV powered ship with electric propulsion, each generator may be rated at 10 MVA or more and produces 6.6 kV, 60 Hz three-phase AC voltages.

The principal consumers are the two synchronous AC propulsion electric motors (PEMs) that individually demand 12 MW e e a a c d . Eac P

Electrical Motor (PEM) has two stator windings supplied separately from the main HV switchboard via transformers and frequency converters.

In an emergency, a PEM may therefore be operated as a half-motor with a reduced power output. A few large induction motors are supplied at 6.6 kV from the main switchboard or cargo switch board auto transformer starter, with the vacuum contactor acting as a direct-on- line (DOL) starting switch or soft starters and a variable speed drive.

High Voltage Generation and Distribution

4.8.1 High Voltage System for a Liquefied Natural Gas Carrier

One or two diesel generators and two turbo generators are generally installed; they can supply both main switchboards independently, but under normal conditions the two switchboards will be linked. However, modern vessels can operate with more than this number (of generators).

4.8.1.1 Salient Features

1. The generator is usually rated more than 3 MVA at 6.6 kV, 3-phase, 60 Hz and could be driven either by a diesel engine or a steam turbine. It is a totally enclosed, self-excited or separately excited, brushless machine.

2. The breakers are normally operated by the power management system, but also can be operated manually (at the switch board). The electric power system is thus designed with discrimination on the distribution system, so that the generator breaker is the last to open if any abnormalities occur.

3. The voltage is kept constant by controlling the excitation current to the exciter. Output power from the stator is fed into a current / voltage compound transformer and the output ec ed a d ed e e c e a d . T e agnetic field in the e c e a d ce AC e e c ed , c ec ed b e a d de a d passed to the DC main rotor windings. The initial voltage build-up is achieved by residual magnetism in the rotor. Constant voltage control is achieved by the automatic voltage

e a , c a a ab e c e e e c e d a a

de ee e AC a a e c a .

4. The generator is cooled by passing air over an integral fresh water cooler, using a closed- circuit air supply. The cooling spaces are fitted with internal baffles to prevent water from reaching the stator windings in the event of any cooler leakage. Water leakage and temperature sensors are fitted in each air cooler.

5. Space heaters which are energised when the generator circuit breakers are open, protect the generator against internal condensation during shut down periods. An embedded

Chapter 4

8. The starting of large motors is prevented until there is sufficient power available; the diesel generator will be started to meet the shortfall in case the turbo generator cannot sustain the load. Two generators will be required to operate in parallel when:

a. Discharging cargo.

b. Loading cargo.

c. Manoeuvring with the bow thruster in use.

The diesel generator will thus start and connect to the bus bar under the following conditions:

R Ge e a c c b ea e ab a ( .e., a dead bus due to a blackout situation).

The bus parameters are abnormal (i.e., high or low voltage and low frequency).

The generator will start, be synchronized and get connected to the bus bar to run in parallel with proportional load sharing in case the circuit breaker of a running turbo generator that was paralleled, trips abnormally (and the bus is still alive). In case of an over load condition, the preferential trip system will shed non-essential loads; however, rather than preferential tripping, it is preferred to have a standby diesel generator that will start, synchronize, connect to the bus bar and run in parallel with proportional load sharing.

4.8.2 High Voltage Supply Generation and Distribution in Gas Tankers

A HV Power supply system in gas tankers generally has 3,300 volt generators that are run by prime mover run by a steam turbine, with the steam generated by utilising boil-off gases in the boiler.

TG 1 supplies HV switchboard 1 and TG 2 supplies HV switchboard 2. Both the HV switchboards are connected by the bus tie breakers TB1 and TB2 which are normally connected so that it is possible to supply all the load from both the switchboards either by T/G 1 or T/G 2 or both the T/Gs running in parallel. Bus tie breakers TB 1 and TB 2 trips automatically in case of a fault such as a short circuit in any of the HV switchboards or can be manually tripped in case of an isolation requirement of the HV bus bar for maintenance.

High Voltage Generation and Distribution

TG 1 2500 kVA 3300 V HV Sw Bd 1 TG 2

2500 kVA 3300 V HV Sw Bd 2

3.3 kV Cargo Sw. Bd 2

3.3 kV Cargo Sw. Bd 1

440 V Cargo Sw. Bd 2 440 V Cargo Sw. Bd 1

440 V Sw. Bd 2 440 V Sw. Bd 1

220 V Section

220 V Section 220 V

Section Emergency Sw. Bd

No. 1

3.3 kV / 440 V Tr

No. 2

3.3 kV / 440 V Transformer

TG1 TG2

TB2 TB1

TC2 TC1

CC2 CC1

CB2 CB1 CL1

CL2

No. 2

3.3 kV / 440 V CSBD Transformer

No. 1

3.3 kV / 440 V CSBD Transformer

LL2 LB2 LL1 LB1

No.1 DG

440 V 1380 kVA No.2 DG

440 V 1380 kVA

No. 2 440 V to 220 V LV Transformer

No. 2 440 V to 220 V LV Transformer Shore Power

Connection Box

440 V to 220 V Em. Transformer Em. DG

440 V 1360 kVA Interlocks

EG1 EG2

GL2 GB2 GE2 GE1 GB1 GL1

Figure 4.27 Power Supply Distribution on a Gas tanker

HV motors such as the bow thruster and ballast pumps are directly fed from HV switchboard.

The cargo switchboard 1 is supplied from the HV switchboard 1 by the TC1 and CC1 feeder breakers. Similarly, cargo switchboard 2 is supplied from the HV switchboard 2 by the TC2 and CC2 feeder breakers. All HV motors for cargo pumps and other cargo equipme

like compressor are fed from both HV cargo switch boards.

The HV power distribution systems are so arranged that in case of fault in any of the main HV switchboard, Cargo switch board 1 and 2 can be connected by the bus tie breaker CB1 and CB 2.

Two transformers rated at 3300 V / 440 V from both cargo switch board feed 440 Volt the

Chapter 4

A similar arrangement is made for 440 V 1 and 2 auxiliary switchboards which are normally fed from two 3300V / 440 V transformers feeding independently the 440 V auxiliary switchboards 1 and 2. Redundancy for 440 V supply availability is done by GB1 and GB2 bus tie breakers in case of faults in any of the main HV switch boards.

A Further development of the HV supply distribution system is a 6600 V system which is most common in commercial vessels. Standby D/G 1 and 2 also feed the HV switchboard.

High Voltage Generation and Distribution

Chapter 4

However, there were some concerns about the availability of power supply in case of faults under certain conditions; for example, assuming that DG is under maintenance, DG 1 is on standby mode and TG 1 is running and feeding supply to all loads; if there is a short circuit fault condition in HVSB 1, TG 1 circuit breaker T1 will trip.

Even though standby DG 1 starts, the circuit breaker cannot be closed because of a short circuit condition in HVSB 1. So, running the TG and Standby DG cannot be from same the switch board. If DG 2 cannot be started, then TG 2 should be the running generator; DG 1 can be on standby so that there will not be any problem for the availability of power in case of a fault. To solve this problem and to have 100% availability of power supply, the distribution system is further modified as shown in Figure 4.29.

One generator from both the HV switchboards has the option of connecting to either switchboard; for example, DG 2 can be connected to 1 HV MSB 1 by the DGB 2A circuit breaker or can be connected to HV MSB 2 by the DGB 2B circuit breaker and similarly is the case for DG 3.

So now DG 1 can be the running generator and DG 2 can be the standby generator, which will supply HV MSB 2 in case of a short circuit fault in HV MSB 1.

High Voltage Generation and Distribution

Figure 4.29 An Alternate 6600 V Power Supply Distribution System

DG 4 DG 3 DG 2 DG 1

No.2 HV MSB No.1 HV MSB

EG Shore (SC)

EGB SHB

MESB1 MESB2

DS

CESB ESB

No. 1 LVMSB

No. 2 LVCSB No. 1 LVCSB

No. 2 LVMSB

No. 2 HVCSB No. 1 HVCSB

DGB4 DGB3 DGB2B DGB3A DGB2A DGB1

HMBTB2 HMBTB1

HMCSB2 HMCSB1

HMTRB2 HMTRB2

HCBTB2 HCBTB1

HCCSB2

HCTRB2

HCCSB1

HCTRB1

LCTRB2 LCTRB1

LCTB1 LCTB2

LCESB

LMTRB2 LMTRB1

LMESB1 LMESB2

LMBTB2 LMBTB1

Chapter 4

HV MSB

DGB2A and DGB2B are mutually interlocked only ONE of them can be closed

DGB3A and DGB3B are mutually interlocked only ONE of them can be closed

HMBTB1 and HMBTB2 are normally closed.

HMTRB1/ HMTRB2 will be open when LMTRB1/ LMTRB2 is open

If there is a Bus short circuit fault #1 or #2 HVCSB, then following breakers will be tripped condition.

Short circuit fault in # 1 HVMSB: DGB1, DGB2A, DGB3A, HMBTB1, HMBTB2 Short circuit fault in # 2 HVMSB:

DGB3, DGB 4, DGB2B, HMBTB1, HMBTB2

HV CSB

HCBTB1 and HCBTB2 are normally open HCCSB1, HCCSB2, HCBTB1 and HCBTB2

are mutually interlocked only three of them can be closed

HCTRB1/ HCTRB2 will be open when LCTRB1/ LCTRB2 is open

If there is a Bus short circuit fault #1 or #2 HVCSB, then following breakers will be tripped condition.

Short circuit fault in # 1 HVCSB: HMCSB1, HCCSB1, HCBTB1 and HCTRB1

Short circuit fault in # 2 HVCSB: HMCSB2, HCCSB2, HCBTB2 and HCTRB2

LV MSB

1) LMBTB1and LMBTB2 are normally open 2) LMTRB1, LMTRB2, LMBTB1 and LMBTB 2

are mutually interlocked only three of them can be closed

3) LMTRB1/LMTTRB2 can be closed only when HMTRB1 / HMTRB2 is closed

LV CSB

1) LCTB1 and LCTB 2 are normally open

2) LCTRB1, LCTRB2, LCTB1 and LCTB 2 are mutually interlocked only three of them can be closed

3) LCTRB1/LCTTRB2 can be closed only when HCTRB1 / HCTRB2 is closed

ESB

1) MESB1, MESB2, ECB andSHB are mutually interlocked only one of them can be closed.

Interlocked is released when EG or SC feedback to LVMSB.

2) MESB1, MESB2and CESB are mutually interlocked so that only one of them can be closed.

3) When feedback mode, LMTB1 and LMTRB2 cannot be closed.

Table 4.1 Interlocks in the HV supply Distribution as Shown in Figure 4.29

High Voltage Generation and Distribution

4.8.3 Radial / Tree-type Electrical Power Distribution System

A radial electrical power distribution system has one major drawback that in case of any feeder failure, the associated consumers would not get any power as there is no alternative path to feed the transformer. In case of a bus failure in either HV switchboard, the power supply is interrupted. In other words, the consumer in a radial electrical distribution system would be in deprived of the power supply until the feeder or transformer is rectified.

With reference to Figure 4.30, considering that there is a fault in the HVSB 1 bus bar, DG 1 and DG 2 b ea e a d e b e b ea e be ed b e ec e a . Hence there will not be any power supply to the 6600 / 440 V reefer transformers (that feed the reefer containers). It will be a matter of concern to maintain the temperature of the reefers;

there are also limitations in feeding these containers by connecting portable cables from other spare supply sockets of the transformers that are fed from HVSB 2.

Engine Room 1.5 MW Bow Thruster

Engine Room 6.6 kV / 440 V

6.6 kV / 440 V 400 kW

Main LO Pump

Passageway

Passageway

Passageway Passageway

Passageway

DG2 DG3 DG4

M

um Voltage SwitchboardBus tie

Forward

M

440 V 60 Hz Main Switchboard

Bus tie

4 MVA

2 MVA

Distribution Boards for Reefer Container Sockets Engine Room

DG1 4 MVA

2 MVA

SC

Distribution Boards for Reefer Container Sockets

Chapter 4

4.8.4 Ring Net Topology

The drawback of a conventional tree / radial electrical power distribution system can be overcome by introducing a ring net electrical power distribution system. Here, one ring net network of distributors is fed by more than one feeder. In this case, if there is a fault in one feeder or it is under maintenance, the ring net distributor is still energized by other feeders that are connected to it. In this way, the supply to the consumers is not affected even when any feeder is out of service.

In addition to that, the ring net system is also provided with different sections that are isolated at suitable points. If any fault occurs in any section of the ring, that section can be easily isolated by opening the associated section isolators on both sides of the faulty zone. In this way, supply to the consumers connected to the healthy zone of the ring, can be easily maintained even when one section of the ring is shutdown.

Passageway M

RTR 2/3

Ring 2

RTR 2/2

RTR 2/1 DS 2/2

DS 2/3 Ring 1

R2

R1 R3

HVSB2HVSB1

RTR 2/4

DG4

DG3

DG2

DG1

M

Lighting Hold Fan

Deck Machinery Fwd Lighting Passageway

Hold Fan

Deck Machinery Fwd

Passageway

Passageway

Passageway Passageway

Passageway Passageway

Main Switchboard

Shi Load Shi Load

NC Medium Voltage Switchboard NC

Circuit Breaker Load Connector

Distribution Board for Feeder Sockets M

Main L.O. Pump

Main L.O. Pump Earth Point

Earth Point

Earth Point Earth Point

Bow Thruster

NC

NC

NC

NO

NO

NC

NC

NC

NO

NO

NO

NO

NC NC NC

NC

NC

NO

NO

Figure 4.31 A Ring Net Power Supply Distribution

High Voltage Generation and Distribution

It can be seen in Figure 4.31 for the ring net power supply distribution, there are two ring net power distribution circuits; Ring 1 supplied by R1 form HVSB 1 busbar and supplied by R3 form HVSB2 Busbar. Similarly Ring 2 supplied by R3 form HVSB 1 busbar and also supplied by R4 form HVSB2 Busbar. The reefer transformer rooms are fed in series by the disconnectors (NC). DS are normally always closed other than any time there is fault in the ring. This can be used for isolation of a faulty reefer transformer room in that ring.

Considering Ring 1 is supplied by the R1 circuit breaker, now if there is short circuit fault in HVSB 1 bus bar, DG1, DG2 and the bus tie breaker will trip; R1 circuit breaker will also trip due to under voltage. Now Ring 1 can be supplied by R2 circuit breaker from the live HVSB 2 bus bar.

Another advantage of a ring main system is that if any fault occurs in any section of the ring, this section can easily be isolated by opening the associated section isolators on both sides of the faulty zone.

Let us consider a fault condition in one of the transformers in Ring 2 reefer transformer room RTR 2/2. R4 circuit breaker which was feeding that ring 2 will be tripped by the protection relay. In order to isolate the fault in Ring 2, first R3 and R4 circuit breakers isolation procedures will be carried out and disconnectors DS2/2 in the RTR 2/1 and DS2/3 in the RTR 2/3 reefer transformer room can be switched off so that the faulted transformer in transformer room RTR 2/2 is isolated.

Under this condition as ring 2 is open circuited, power supply to reefer transformer room RTR 2/3 and RTR 2/4 can be supplied by switching on R4 circuit breaker and reefer transformer room RTR 2/1 can be supplied by switching on circuit breaker R3 as a conventional / radial system. Whenever a fault in the reefer transformer is solved or the faulty transformer is isolated, Ring 2 can be once again reverted back by connecting disconnectors DS2/2 in the RTR 2/1 and DS2/3 in RTR 2/3 reefer transformer rooms.

4.8.4.1 Interlocking of a Circuit Breaker for the 6600 / 440 V Transformer With reference to Figure 4.32, the following interlocks function:

Chapter 4

3. MBT can be closed with manual synchronisation when both sides of MBT are alive.

4. LR1 (LR2) can be closed when HR1 (HR2) is closed.

5. LR1 (LR2) can be opened automatically when HR1 (HR2) is opened.

6. HR1 (HR2) can be opened automatically when LR1 (LR2) is opened.

Shore Gen

D2 D1 D3

D4

MBT

B Bus A Bus

HR2 HR1 AMP

TR2 TR1

LR2 LBT LR1

EBS EB1

Spare EB2

EG SC

AMP Port

AMP Stbd

Port Socket

Stbd Socket

AMP Container

Only one line can be connected AMP

Changeover Panel ESB

440 Sw Bd 6.6 kV Sw Bd

Shore Side AMP Container

Breaker

DG4 DG3 DG2 DG1

EG

Figure 4.32 Interlocking of a Circuit Breaker for a 6600 / 440 V Transformer The 6.6 kV switchboard is fitted with a short circuit fault detection system. In such a case, the following breakers cannot be electrically closed:

1. Short circuit fault on Bus A: D1, D2 and MBT 2. Short circuit fault on Bus B: D3, D4 and MBT

3. SHB cannot be closed when the DG feeds the 440 V switchboard.

High Voltage Generation and Distribution

Figure 4.33 A Ring Net Distribution System in Cruise Ships / Offshore Vessels

Ring main Breaker

Ring main Breaker

Ring main Breaker

Ring main Breaker

Chapter 4

Figure 4.34

Chapter 5

Dalam dokumen Buku Marine High Voltage Technology (Halaman 145-161)