38. 38.
2.
Tarakan No. Cabang/
Branch
Jangka Waktu Pekerjaan/Duration of work
No. Berita Acara Progres Pekerjaan/
Minutes of Work Progress Number
Nilai Pekerjaan/
Work Value (Rp)
% Progres Pekerjaan/
Construction Progress
Nilai Progres Pekerjaan/
Construction Progress Value
(Rp)
Realisasi
Pembayaran/
Realization Payments (Rp) No. Kontrak/ Contract Number
84.651
63.270
Dinson Industries Corp, Kontrak Akta No.23 tanggal 9 Ferbruari 2017 Notaris
Ahmad Tauzan Siata SH.M.KN/
Contracts Act No. 23 dated February 9, 2017, Notary Ahmad Tauzan Siata SH.M.KN
Jangka waktu 272 hari/Duration of 272 calendar days
Ambon &
Jayapura.
Pengadaan 2 Unit RTG untuk Cabang Ambon dan 3 Unit Untuk Jayapura (3 Unit untuk Ambon dan 2 Unit untuk Jayapura) USD 6.290.000 /Procurement of 2 RTG Units for Ambon Branch and 3 Units For Jayapura (Addendum 3 Units for Ambon and 2 Units for Jayapura) USD 6.290.000
84.651
100
80,32 106.218 87.926
PT Adhi Karya (Persero), Kontrak Akta No.1 tgl 14 Oktober 2016 Notaris Ahmad Tauzan Siata SH.M.Kn/Contracts Act No.
1 dated October 14, 2016, Notary Ahmad Tauzan Siata SH.M.Kn
Jangka waktu 540 hari/Duration of 540 calendar days (multi years, 2016 - 2017) Addendum No.5/HK.301//8/PI.IV/2017 16
Agustus 2017 / Addendum No.
5/HK.301//8/PI.IV/2017 August 16, 2017 Laporan progres fisik per 31 Desember 2017/Physical progress report of December 31, 2017
Addendum 7/HK.301/12/DFP-2017 : 8
November 2017/ Addendum
7/HK.301/12/DFP-2017: November 8, 2017
Berita Acara Serah Terima 247/PMO- P/BA-ST/RTG-AMB-JYP/XII/2017 / Minutes of Handover 247/PMO-P/BA- ST/RTG-AMB-JYP/XII/2017.
3 Pembangunan Container Yard seluas
2,14 Ha Pelabuhan Tarakan/Construction of Container Yard 2,14 Ha of Tarakan Port.
132.243
39. 39.
Ternate
Kendari
INFORMATION REALIZATION OF USE OF FUNDS PMN (continued)
No. Cabang/
Branch
Investasi/ Investments
Nilai Pekerjaan/
Work Value (Rp)
% Progres Pekerjaan/
Construction Progress
Nilai Progres Pekerjaan/
Construction Progress Value
(Rp)
Realisasi
Pembayaran/
Realization Payments (Rp) No. Kontrak/ Contract Number
Jangka Waktu Pekerjaan/Duration of work
No. Berita Acara Progres Pekerjaan/
Minutes of Work Progress Number INFORMASI REALISASI PENGGUNAAN DANA PMN (lanjutan)
PT Adhi Karya (Persero), Akta No.22 tanggal 15 Agustus 2017 Notaris Ahmad Tauzan Siata SH. M.Kn/PT Adhi Karya (Persero), Deed No.22 dated August 15, 2017 Notary Ahmad Tauzan Siata SH.
M.Kn
Jangka waktu 540 hari kalender/Duration of 540 calendar days(multi years, 2017 - 2019)
PT Nindya Karya (Persero), Akta No.22 tanggal 14 Oktober 2016 Notaris Ahmad Tauzan Siata SH. M.Kn/Contracts Act No. 22 dated October 14, 2016, Notary Ahmad Tauzan Siata SH.M.KN
Jangka waktu 730 hari kalender/Duration of 730 calendar days(multi years, 2016 - 2018)
Laporan progres fisik per 31 Desember 2017/Physical progress report of December 31, 2017
Pembangunan Container Yard (CY) dan Reklamasi Terminal Petikemas Kendari
New Port di Pelabuhan
Kendari/Construction of Container Yard (CY) and Reclamation of Kendari New Port Dealer Terminal at Kendari Port.
147.697
6,89 10.176 - PT Hutama Karya (Persero), Kontrak No.
50 tanggal 30 Juni 2016 Notaris Ahmad Tauzan Siata SH. M.Kn/Contracts Act No. 50 dated June 30, 2016, Notary Ahmad Tauzan Siata SH.M.KN
Jangka waktu 365 hari /Duration of 365 calendar days (multi years, 2016 - 2017) Addendum No. 4/HK.301/1/PI.IV-2017 6 November 2017/Addendum no. 4 / HK.301 / 1 / PI.IV-2017 November 6, 2017
Laporan progres fisik per 31 Desember 2017/Physical progress report of December 31, 2017
5. Pembangunan Dermaga 300 X 35 M2
dan Trestle 2 X 10 X 200 M2 di Pelabuhan Kendari/Construction of Port 300 x 35 M2 and Tretle 2 x 10 x 200 M2 in Kendari Port.
323.884
81,67 264.516 209.845
4. Replacement Dermaga seluas 3.500 M2
di Pelabuhan Ternate/Construction of Jetty 3.500 M2 in Ternate Port.
98.098
100 98.098 81.693
Jayapura
Sorong
Merauke No. Cabang/
Branch
Nilai Pekerjaan/
Work Value (Rp) No. Kontrak/ Contract Number
Jangka Waktu Pekerjaan/Duration of work
No. Berita Acara Progres Pekerjaan/
Minutes of Work Progress Number
PT Hutama Karya ( Persero), Akta No. 18 tanggal 17 Oktober 2016, Notaris Ahmad Tauzan Siata, SH., M.Kn./Contracts Act No. 18 dated October 17, 2016, Notary Ahmad Tauzan Siata SH.M.KN
Jangka waktu 660 hari
kalender/Duration of 680 calendar days (multi years, 2016 - 2017)
Laporan progres fisik per 31 Desember 2017/Physical progress report of December 31, 2017
7. Pembangunan Dermaga Petikemas dan
Reklamasi Pelabuhan
Sorong/Construction of Jetty of Container Yard and Reclamation in Sorong Port.
296.615
58,74 174.232 114.314
PT Wijaya Karya (Persero), Akta No. 60 tanggal 31 Oktober 2016 Notaris Ahmad Tauzan Siata SH. M.Kn./Contracts Act No. 60 dated October 31, 2016, Notary Ahmad Tauzan Siata SH.M.KN
Jangka waktu 540 hari kalender/Duration of 540 calendar days (multi years, 2016 - 2017)
Addendum No. 01- : 5 Juni
2017/Addendum No. 01- : 5 June 2017 Laporan progres fisik per 31 Desember 2017/Physical progress report of December 31, 2017
8. Pembangunan Dermaga 75 X 30 M2 dan
Pondasi Fixed Crane di Pelabuhan Merauke/Construction of Jetty 75 x 30 M2 and Foundation Fixed Crane in Sorong Port.
64.552 Laporan progres fisik per 31 Desember 2017/Physical progress report of December 31, 2017
6. Pembangunan Dermaga Penumpang
1.500 M2 dan Replacement Dermaga
150 X 30 M2 di Pelabuhan
Jayapura/Construction of Jetty 1.500 M2 and Replacement 150 x 30 M2 in Jayapura Port.
156.819
70,17 110.040 88.532
PT Nindya Karya ( Persero). Akta No.26 tanggal 14 Oktober 2016 Notaris Ahmad Tauzan Siata SH. M.Kn/Contracts Act No. 26 dated October 14, 2016, Notary Ahmad Tauzan Siata SH.M.KN
95,41 61.589 49.211
% Progres Pekerjaan/
Construction Progress
Nilai Progres Pekerjaan/
Construction Progress Value
(Rp)
Realisasi
Pembayaran/
Realization Payments (Rp)
39. 39.
Merauke (lanjutan/
continued)
Manokwari
INFORMASI REALISASI PENGGUNAAN DANA PMN (lanjutan)
No. Kontrak/ Contract Number Jangka Waktu Pekerjaan/Duration of
work
INFORMATION REALIZATION OF USE OF FUNDS PMN (continued)
No. Cabang/
Branch
Investasi/ Investments
Nilai Pekerjaan/
Work Value (Rp)
Nilai Progres Pekerjaan/
Construction Progress Value
(Rp)
Realisasi
Pembayaran/
Realization Payments (Rp) 8. Jangka waktu 275 hari kalender/Duration
of 275 calendar days (multi years, 2016 - 2017)
Addendum 15 / HK.301 / 9 / PI.IV-2017:
20 Oktober 2017/ Addendum HK.301 / 9 / PI.IV-2017: October 20, 2017
Laporan progres fisik per 31 Desember 2017/Physical progress report of December 31, 2017
% Progres Pekerjaan/
Construction Progress
11.960
6.203
PT Mercor Indonesia ( Persero), Akta No.
10/HK.301/6/PI.IV-2017 5 Juni 2017, Notaris Imas Fatimah, S.H/Contract Act Deed No. 10 / HK.301 / 6 / PI.IV-2017 June 5, 2017, Notary Imas Fatimah, S.H Jangka waktu 175 hari kalender/Duration of 175 calendar days
Addendum 9/HK.301/11/PI.IV 2017 13
November 2017 / Addendum
9/HK.301/11/PI.IV 2017: November 13, 2017
Berita Acara Serah Terima
182/BA.ST1/PMO-MRK/XII/2017 tanggal 27 Desember 2017/Minutes of the
Handover 182/BA.ST1/PMO-
MRK/XII/2017 dated on December 27, 2017.
9. Pembangunan Dermaga 75 X 30 M2 di
Pelabuhan Manokwari/
Construction of Jetty 75 x 30 M2 in Manokwari Port.
46.316
67,72 31.365 13.024 No. Berita Acara Progres Pekerjaan/
Minutes of Work Progress Number
Pengadaan 2 Unit Fix Crane di Pelabuhan Merauke/Procurement of 2 Units Fix Cranes at Merauke Port.
87,50 10.468 10.468
Pembangunan 1 Unit Pondasi Fix Crane 100 di Pelabuhan Merauke /Construction of 1 Unit of Fix Crane Foundation at Port of Merauke.
11.960 Wuxi Huadong Heavy Machinery Co.Ltd , Akta No. 27 tanggal 28 April 2017, Notaris Ahmad Tauzan Siata, SH., M.Kn./Contracts Act No. 27 dated April 28, 2017, Notary Ahmad Tauzan Siata SH.M.KN. USD 2.597.000
Jangka waktu 300 hari kalender/Duration of 300 calendar days (multi years, 2017 - 2018)
Laporan progres fisik per 31 Desember 2017/Physical progress report of December 31, 2017
Manokwari (lanjutan/
continued)
40. 40.
a. a.
9.
No. Cabang/
Branch
Nilai Pekerjaan/
Work Value (Rp)
% Progres Pekerjaan/
Construction Progress
Nilai Progres Pekerjaan/
Construction Progress Value
(Rp)
Realisasi
Pembayaran/
Realization Payments (Rp) No. Kontrak/ Contract Number
Jangka Waktu Pekerjaan/Duration of work
No. Berita Acara Progres Pekerjaan/
Minutes of Work Progress Number PT Brantas Abipraya ( Persero), Akta No.
25 tanggal 14 Oktober 2016 Notaris
Ahmad Tauzan Siata SH.
M.Kn./Contracts Act No. 25 dated October 14, 2016, Notary Ahmad Tauzan Siata SH.M.KN
Jangka waktu 305 hari kalender/Duration of 305 calendar days (multi years, 2016 - 2017)
Addendum No. 3/HK.301/8/PI.IV-2017 : 25 Agustus 2017/ Addendum HK.301 / 8 / PI.IV-2017: August 25, 2017
Laporan progres fisik per 31 Desember 2017/Physical progress report of December 31, 2017