MrP Processing and outputs

Dalam dokumen Industrial Engineering and Management (Halaman 109-116)

5.1 IntroductIon

5.2.2 MrP Processing and outputs

The MRP system determines the net requirements for raw materials, component parts and subassemblies based on the information gathered from the bill of materials, master schedule and inventory records file. It determines the gross material requirements, then subtracts out the inventory on hand and adds back in the safety stock in order to compute the net requirements.

The main outputs from MRP include three primary reports and three secondary reports. The primary reports consist of planned order schedules, order releases and changes to planned orders, which might include cancellations or revisions of the orders. The secondary reports generated by MRP include performance control reports (which are used to track problems like missed delivery dates and stock outs in order to evaluate system performance), planning reports (which can be used in forecasting future inventory requirements); and exception reports (which call managers’

attention to major problems).

The MRP process involves the following steps:

• Determine the gross requirements of a finished product.

• Determine the net requirements and when orders will be released for fabrication or subassembly.

• Net requirements = Total requirements – Available inventory.

• Net requirements = (Gross requirements + Allocations) – (On hand) − Scheduled receipts.

example 5.1: A firm manager receives an order of 500 staplers. The order is to be delivered at the end of 10th week from now. He had 200 staplers in the inventory at the time of the order receipts. The product components and its structure are shown in Figures 5.2 and 5.3, respectively.

The lead time to manufacture the components is shown in Figure 5.4. Using MRP, determine the schedules for the orders to be released for the manufacturing and assemblies of the components so that the 500 staplers can be delivered on time.

Top assembly

Arm Rubber pad

Spring steel and

Tooth

Carriage Helical

spring Magazine

cartridge Pin Base Strike pad

Rubber

pad Level-2 Level-1 Level-0

Base assembly Middle assembly

Stapler

Figure 5-3: Product structure (Bill of materials) of staplers Rubber pad

Arm Spring steel and tooth

Carriage Spring Magazine cartridge

Strike pad Pin

Base Rubber pad

Figure 5-2: Stapler with its components

solution:

The order release schedules and the amount of the components at various stages of the manufacturing are shown in Tables 5.1 to 5.14.

Table 5-1: MRP schedules for the stapler

Item: Stapler Lead time: 1 week

Week

1 2 3 4 5 6 7 8 9 10

Gross requirements 500

Scheduled receipts 0

Projected on-hand inventory 200

Net requirements 300

Planned order receipts 300

Planned order releases 300

Rubber pad Top assembly

1 week 1 week

1 week 1 week

2 weeks

2 weeks

Rubber pad Middle assembly

Pin 1 week

1 week 1 week

1 week 1 week

Strike pad

1 week

week

0 1 2 3 4 5 6 7 8 9 10

Base

Base assembly

1 week Stapler Helical spring

Magazine catridge Carriage

Arm 1 week spring steel and tooth

Figure 5-4: Lead times of the various components of the stapler

Table 5-2: MRP schedules for the top assembly of the stapler

Item: Top assembly Lead time: 1 week

Week

1 2 3 4 5 6 7 8 9 10

Gross requirements 300

Scheduled receipts 0

Projected on-hand inventory 0

Net requirements 300

Planned order receipts 300

Planned order releases 300

Table 5-3: MRP schedules for the rubber pad (top assembly) of the stapler

Item: Rubber pad Lead time: 1 week

Week

1 2 3 4 5 6 7 8 9 10

Gross requirements 300

Scheduled receipts 0

Projected on-hand inventory 0

Net requirements 300

Planned order receipts 300

Planned order releases 300

Table 5-4: MRP schedules for the spring steel and tooth (top assembly) of the stapler Item: Spring steel and tooth Lead time: 1 week

Week

1 2 3 4 5 6 7 8 9 10

Gross requirements 300

Scheduled receipts 0

Projected on-hand inventory 0

Net requirements 300

Planned order receipts 300

Planned order releases 300

Table 5-5: MRP schedules for the arm (top assembly) of the stapler

Item: Arm Lead time: 1 week

Week

1 2 3 4 5 6 7 8 9 10

Gross requirements 300

Scheduled receipts 0

Projected on-hand inventory 0

Net requirements 300

Planned order receipts 300

Planned order releases 300

Table 5-6: MRP schedules for the middle of the stapler

Item: Middle assembly Lead time: 2 weeks

Week

1 2 3 4 5 6 7 8 9 10

Gross requirements 300

Scheduled receipts 0

Projected on-hand inventory 0

Net requirements 300

Planned order receipts 300

Planned order releases 300

Table 5-7: MRP schedules for the carriage (middle assembly) of the stapler

Item: Carriage Lead time: 1 week

Week

1 2 3 4 5 6 7 8 9 10

Gross requirements 300

Scheduled receipts 0

Projected on-hand inventory 0

Net requirements 300

Planned order receipts 300

Planned order releases 300

Table 5-8: MRP schedules for the magazine cartridge (middle assembly) of the stapler

Item: Magazine catridge Lead time: 1 week

Week

1 2 3 4 5 6 7 8 9 10

Gross requirements 300

Scheduled receipts 0

Projected on-hand inventory 0

Net requirements 300

Planned order receipts 300

Planned order releases 300

Table 5-9: MRP schedules for the helical spring (middle assembly) of the stapler

Item: Helical spring Lead time: 2 weeks

Week

1 2 3 4 5 6 7 8 9 10

Gross requirements 300

Scheduled receipts 0

Projected on-hand inventory 0

Net requirements 300

Planned order receipts 300

Planned order releases 300

Table 5-10: MRP schedules for the pin (middle assembly) of the stapler

Item: Pin Lead time: 1 week

Week

1 2 3 4 5 6 7 8 9 10

Gross requirements 300

Scheduled receipts 0

Projected on-hand inventory 0

Net requirements 300

Planned order receipts 300

Planned order releases 300

Table 5-11: MRP schedules for the base assembly of the stapler

Item: Base assembly Lead time: 1 week

Week

1 2 3 4 5 6 7 8 9 10

Gross requirements 300

Scheduled receipts 0

Projected on-hand inventory 0

Net requirements 300

Planned order receipts 300

Planned order releases 300

Table 5-12: MRP schedules for the rubber pad (base assembly) of the stapler

Item: Rubber pad Lead time: 1 week

Week

1 2 3 4 5 6 7 8 9 10

Gross requirements 300

Scheduled receipts 0

Projected on-hand inventory 0

Net requirements 300

Planned order receipts 300

Planned order releases 300

Table 5-13: MRP schedules for the strike pad (base assembly) of the stapler

Item: Strike pad Lead time: 1 week

Week

1 2 3 4 5 6 7 8 9 10

Gross requirements 300

Scheduled receipts 0

Projected on-hand inventory 0

Net requirements 300

Planned order receipts 300

Planned order releases 300

Table 5-14: MRP schedules for the base of the stapler

Item: Base Lead time: 1 week

Week

1 2 3 4 5 6 7 8 9 10

Gross requirements 300

Scheduled receipts 0

Projected on-hand inventory 0

Net requirements 300

Planned order receipts 300

Planned order releases 300