• Tidak ada hasil yang ditemukan

Roadmap for Boiler Examination

4 ROADMAP FOR BOILER INSPECTIONS AND IN-SERVICE INSPECTION

4.1 Roadmap for Boiler Examination

Figure 4-1 provides a roadmap for (i) solving boiler tube failures – mechanism unknown, (ii) solving boiler tube failures – mechanism known, and (iii) anticipating and preventing future boiler tube failures. The Boiler and Heat Recovery Steam Generator Tube Failures Manual [4-1]

(the BTF/HTF manual) provides detailed guidance on the other steps in the roadmap.

As shown, three avenues are open to the investigator or BTF team depending upon the status of the BTF event:

• Path A: BTF with mechanism unknown. If a BTF has occurred for the first time or a number of repeat failures have occurred and the mechanism is not known, then the charts of typical appearance and location, Tables 4-2 and 4-4, along with Tables 5-1 through 5-35 should be consulted. Note that these tables are based on simple, generally macroscopic features of failure and should be used as a guide to a particular chapter for further analysis.

• Path B: BTF with “known” mechanism. If the BTF Team has knowledge from past failures that a particular mechanism is the likely cause, then Tables 5-1 through 5-35 can be used to go directly to the appropriate chapter in the BTF/HTF manual. Here, the team can follow step-by-step the steps to confirming the mechanism, establishing the root cause and formulating/executing the appropriate solutions.

• Path C: Anticipating and preventing future BTF. Historically, utilities and operators responded to tube damage only after failures had occurred. This reactive response is economically costly and, as the understanding of key mechanisms has improved, not necessary. The modern approach for world class units is to understand the conditions in the boiler, generally through monitoring activities, and to prevent tube failures from occurring [4-1].

Roadmap for Boiler Inspections and In-Service Inspection

Figure 4-1

Roadmap for Boiler Inspections with Three Starting Points for Use of Information Contained in This Report and Referenced to the Boiler and HRSG Tube Failures Manual [4-1].

Roadmap for Boiler Inspections and In-Service Inspection

As indicated in Figure 4-1, establishing an in-service examination program is a critical step for anticipating and avoiding boiler damage. The NDE priorities, as shown in Table 4-1, are to be considered in establishing that program. Details of the steps represented in Figure 4-1 are discussed in Section 4.2 below. Issues will include these steps:

• Setting the examination interval

• Delineating potential damage mechanisms

• Determining locations to be examined

• Identifying examination methods to be used

• Making pre-examination preparations

• Conducting the examination

• Resolving any indications found

• Setting the re-examination interval

Table 4-1

NDE Priorities for Boiler

Boiler Life Phase NDE Priorities Periodic in-service

examination Formulate an examination plan for the unit including:

Locations to be examined Examination period

Techniques to be employed Acceptability standards for damage

Perform periodic examinations as required.

Proactively use the information obtained from the examinations to:

1. Determine the status of the unit.

2. Check on the rate of damage accumulation compared to the design.

3. Provide feedback on setting the next examination.

4. Monitor the performance of repairs or other mitigation actions taken.

As shown in Figure 4-1, if no damage is found during the in-service examination, then a re- examination interval is established, and later examinations are conducted. If damage is found during an in-service examination, a process will need to start to determine the active mechanism, diagnose the root cause, determine the extent of the damage (does it extend to other areas, how deep or long are indications, has it spread to other parts of the boiler, etc.), and implement repairs and solutions to prevent reoccurrence of the problem. These steps are shown in the middle and

Roadmap for Boiler Inspections and In-Service Inspection

In either event, Tables 4-2 and 4-4, plus the one-page summaries of damage mechanisms (Tables 5-1 through 5-35) should be consulted. These tables are used to help screen damage, based on the location found, and to determine the mechanism causing the damage. From this knowledge, the balance of the indicated steps in Figure 4-1 can proceed. If the correct mechanism is not

identified and the root cause determined, then a commitment to on-going repair/replacement will occur because the wrong solutions will inevitably be chosen.

Table 4-2 provides a list of mechanisms that have been confirmed in the field, organized by boiler component. Footnotes to Table 4-2 provide some specific location information for selected damage types, and where available, a cross reference to a figure in the BTF/HTF manual is given that illustrates the appearance of the specific damage type and/or location.

As the boiler fleet ages, there will undoubtedly be additions to the columns of this table.

Therefore, if the detected damage cannot be confirmed as one listed in the table through subsequent investigation, the investigator needs to review other potential damage types in the BTF/HTF manual. When a list of potential damage types for the specific component has been compiled, the investigator can review Table 4-3 and/or the summaries of each mechanism (Tables 5-1 through 5-35) for additional information about how to proceed.

Table 4-2

Developing a List of Examination Locations – Likely Damage in Various Boiler Components

Component Field-Confirmed Mechanisms

Economizer tubing Acid dew point corrosion Corrosion fatigue

Flow-accelerated corrosion (FAC)1 Fly ash erosion

Low-temperature creep cracking Pitting

Thermal fatigue

Reheater tubing Chemical cleaning damage Dissimilar metal weld failures Fireside corrosion2

Fly ash erosion Graphitization3

Long-term overheating4

Low-temperature creep cracking Pitting

Short-term overheating Sootblower erosion Stress corrosion cracking Thermal-mechanical fatigue Vibration-induced fatigue

Roadmap for Boiler Inspections and In-Service Inspection Table 4-2 (continued)

Developing a List of Examination Locations – Likely Damage in Various Boiler Components

Component Field-Confirmed Mechanisms

Superheater tubing Caustic gouging

Chemical cleaning damage Dissimilar metal weld failures5 Fireside corrosion

Fly ash erosion Graphitization

Long-term overheating

Low- temperature creep cracking6 Pitting7

Short-term overheating Sootblower erosion Stress corrosion cracking8 Thermal-mechanical fatigue Vibration induced fatigue Waterwall tubing Acid phosphate corrosion9

Caustic gouging

Chemical cleaning damage Coal particle erosion Corrosion fatigue10

Explosive cleaning damage Falling slag

Fireside corrosion Fly ash erosion Hydrogen damage Short-term overheating Thermal fatigue

Thermal-mechanical fatigue11 Vibration-induced fatigue Notes:

1. Economizer inlet header stub tubes (see Figure 32-1 in the BTF/HTF manual).

2. Tubes with longer gas-touched lengths (see Chapters 45 and 46 in the BTF/HTF manual).

3. Low-temperature portions of the superheater and reheater (see Figure 59-2 in the BTF/HTF manual).

4. Lowest tube in horizontal platen or leading tube in a pendant section (see Figure 44-2 in the BTF/HTF manual).

5. Where ferritic materials are joined with austenitic stainless steel (see Figure 47-2 in the BTF/HTF manual).

6. Tube bends with high residual stress remaining from fabrication (see Figure 35-1 in the BTF/HTF manual).

7. Bottoms of pendant loops (see Figure 58-1 in the BTF/HTF manual).

8. Bends, welds, supports, and spacers (see Figure 49-5 in the BTF/HTF manual).

9. Locations where boiling first initiates (see Figure 23-2 in the BTF/HTF manual).

Roadmap for Boiler Inspections and In-Service Inspection

Table 4-3 gives a list of common NDE techniques and the acronyms used to reference these techniques. This table also provides direction to the section of the report which contains information on the specific NDE technique.

Table 4-4 can be used in conjunction with Table 4-2 to help screen for potential damage types. It provides the following:

• A summary of all major damage types

• Some additional information about where the damage generally occurs (column 2)

• Example-specific locations (column 3)

• The most generally applied examination techniques (column 4)

• A cross reference to the information about that damage type contained in Section 5

Table 4-3

Location of Additional Information on Examination Techniques Examination Technique Abbreviation or

Acronym See This Section of This Report for Information

AC potential drop ACPD 7.6

Computed radiography using phosphor plates CRT 8.2 Digital radiography using solid-state detectors DRT 8.2

Eddy current testing ET 7.5

Exploratory grinding

Liquid dye penetrant PT 7.4

Low-frequency electromagnetic technique LFET 8.3

Magnetic particle examination MT 7.3

Oxide thickness measurement by ultrasonics UT-oxide 10.1

Pulsed eddy current PEC 10.2

Radiographic examination RT 8.2

Remote visual or internal videoscopic

examination Internal visual 7.1

Replication 9.2

Tube sampling

Ultrasonic attenuation measurements UT-attenuation 8.1

Ultrasonic examination UT 8.1

Ultrasonic phased array examination UT-PA 8.1

Ultrasonic shear wave examination UT-shear 8.1

Ultrasonic thickness measurements UT-thickness 10.1 Ultrasonic time-of-flight diffraction UT-TOFD 8.1

Visual examination VT 7.1

Wet fluorescent magnetic particle examination WFMT 7.3

Roadmap for Boiler Inspections and In-Service Inspection Table 4-4

Summary of Damage Mechanisms, Examination Locations, and Examination Techniques Damage

Mechanism Where Damage Occurs – General Example Locations Examination

Techniques For More Information,

See:

Corrosion fatigue Water-touched components, especially the economizer

Steam-touched tubing containing condensate during operational transients

Welded connections, bends, and attachments with high thermally induced forces and bending moments

Locations with significant thickness transitions

Tube-to-header welds

Scallop bar attachments

U-bend-to-drain-line welds

Riser and downcomer tubes

Internal visual (video probe, borescope)

UT-thickness (internal rotary probe

Phased array UT

Digital RT or Computed RT

Quantify by tube sampling

Table 5-1

Thermal-

mechanical fatigue

All boiler sections, most likely at welded connections and

attachments, occasionally at bends

Locations with significant thickness transitions

Tube-to-header welds

Tube bends near header attachments

Lower slope region near ash hopper

Visual inspection

Particle testing

Eddy current

Quantify with: UT, ACPD, exploratory grinding, or RT

Table 5-9 Table 5-28

Creep fatigue Components in creep regime, notably SHs and RHs

Locations with welded

connections, bends, attachments, and header boreholes

Tube-to-header connections

SH header boreholes

VT

WFMT

PT

Quantify with: UT, ACPT, replication, exploratory grinding

Table 5-14 Table 5-20

Roadmap for Boiler Inspections and In-Service Inspection Table 4-4 (continued)

Summary of Damage Mechanisms, Examination Locations, and Examination Techniques Damage

Mechanism Where Damage Occurs – General Example Locations Examination

Techniques For More Information,

See:

Flow-induced vibration fatigue

All sections, most notably SHs and RHs

Welded connections, bends, and attachments

Vertical screen tubes and

horizontal rear pass tubes VT

PT

Magnetic particle

Quantify with: UT, ACPD, exploratory grinding

Table 5-9 Table 5-28

Flow-accelerated corrosion

High-pressure portions of the feedwater system

Water-touched components in the temperature range 536°F–572°F (280°C–300°C)

Economizer inlet header stub tubes nearest the feedwater inlet

Internal visual (video probe, borescope)

UT-thickness

Pulsed eddy current (for insulated piping)

Quantify with UT- thickness, tangential radiographic testing

Table 5-11

Acid phosphate corrosion; caustic gouging; hydrogen damage

Locations where water/fluid flow adjacent to the tube wall is disrupted

Locations where stable steam films are likely to form

Downstream of welds

Locations with internal deposits

Locations with high heat transfer or high steam quality

Horizontal tubes

Internal visual (video probe, borescope)

Quantify with: UT- thickness (internal rotary probe or from the outside surface), tube sampling

Table 5-3 Table 5-4 Table 5-5

Roadmap for Boiler Inspections and In-Service Inspection Table 4-4 (continued)

Summary of Damage Mechanisms, Examination Locations, and Examination Techniques Damage

Mechanism Where Damage Occurs – General Example Locations Examination

Techniques For More Information,

See:

Internal pitting Oxygen pitting prevalent in economizers, possible at any wet surface, especially non-drainable, horizontal surfaces

Pitting caused by improper chemical cleaning possible at any surface in contact with cleaning solvents

Locations where condensate forms and remains as liquid during shutdown periods

Bottoms of pendant loops

Low points in sagging horizontal tubing

Internal visual (video probe, borescope)

Quantify with: UT- thickness (internal rotary probe), tube sampling, guided waves on straight piping

Magnetostrictive sensor technique

Table 5-16 Table 5-30

Graphitization Occurs after prolonged exposure to temperatures above 842°F–

1292°F (450°C–700°C)

Low temperature portions of the SH and RH

Near weld heat-affected zones (HAZ)

Miniature fracture mechanics tests

Bend tests

Punch testing

Table 5-31

Thermal fatigue Where there is slag buildup, high heat fluxes, or flame impingement

Where cyclic thermal stress is sufficiently high

Fireside waterwall and membranes

Header-to-stub-tube attachment weld of the economizer inlet

VT

Liquid penetrant

Magnetic particle testing

Quantify with RT or AC potential drop

Table 5- 7 Table 5-8 Table 5-10

Acid dew point corrosion

Gas-touched surfaces where the metal temperatures are below the acid dew point

Tubes, casings, ducts, and

stacks VT

Quantify with UT- thickness

Table 5-19

Roadmap for Boiler Inspections and In-Service Inspection Table 4-4 (continued)

Summary of Damage Mechanisms, Examination Locations, and Examination Techniques Damage

Mechanism Where Damage Occurs – General Example Locations Examination

Techniques For More Information,

See:

Stress corrosion cracking

Locations with the highest potential for concentration of contaminants as well as high stresses

Condensate collection points (concentration of contaminants)

Bends, welds, attachments, supports (high stress locations)

VT

WFMT (for magnetic materials)

PT

ET

Quantify with exploratory grinding

Table 5-25

Short-term overheating

Locations where overheating is likely

Locations where partial or complete blockage of flow through tubes is likely

Downstream of bends where blockage by oxide, condensate, debris, etc. can occur

Above orifices in lower waterwalls where blockage results from feedwater corrosion products

Bottom bends in SH loops

VT for tube damage, bulging, flame patterns, etc.

Internal visual (video probe, borescope) for blockages

Quantify with tube sampling

Table 5-13 Table 5-24

Long-term

overheating/creep

Steam-cooled tubing where overheating is likely

Near material changes

Where there is a variation in gas- touched length among tubes of the same material

Final leg of tubing just before outlet header.

Lowest tube in a horizontal platen or leading tube in a pendant section.

UT–oxide, internal scale, and wall thickness survey

Quantify with remaining creep life assessment using internal scale and wall thickness survey

Table 5-20

Low-temperature creep cracking

High-stress locations with

residual stresses from fabrication Weld connections and header

boreholes Magnetic particle

Quantify with UT or ACPD

Table 5-14

Roadmap for Boiler Inspections and In-Service Inspection Table 4-4 (continued)

Summary of Damage Mechanisms, Examination Locations, and Examination Techniques Damage

Mechanism Where Damage Occurs – General Example Locations Examination

Techniques For More Information,

See:

Fly ash erosion Where nonuniform high gas flows

develop locally Back pass in the waterwall

Inlet sections of RH tubes

VT for the

appearance of rust shortly after washing

Ultrasonic testing (UT) to quantify damage determining the extent of wall thinning

Table 5-2

Fireside corrosion Waterwall tubes, generally at the crown of the tube facing the flame

SH/RH tubing

Where metal temperatures exceed 1112°F (600°C)

Leading sides tubes, pendant platens

Tubes out of alignment

Spacers and uncooled hangers

Tubes with longer gas-touched length

VT for signs of corrosion, wear, etc

UT to quantify wall thinning

Pulsed eddy current (PET)

Table 5-6 Table 5-21 Table 5-22

Sootblower erosion

Waterwall tubes

SH/RH tubes

Circular pattern around wall blowers

SH/RH tubing in the direct path of retractable blowers

Visual testing (VT) for rusted tube locations after boiler wash

Quantify with UT

Table 5-12 Table 5-26

Chemical cleaning damage

Inside surface of fluid-touched

tubes Waterwall tubing

SH/RH tubing

UT for wall thinning

RT to detect possible blockages

Table 5-15 Table 5-32 Coal particle

erosion

Fireside of waterwall tubes Replaceable wear liners near the end of the burner

Refractories covering waterwall

Visual inspection

UT to quantify

Table 5-17

Roadmap for Boiler Inspections and In-Service Inspection