APPROVAL MATRIAL
PT. CATUR MANUNGGAL PAKERTI
Indonesia Authorized Sales
Head Office :
Ruko Pondok Cabe Mutiara Blok B-16, Jl. Raya Pondok Cabe, Tangerang Selatan
Tel. 021 – 22742550 Mail.
[email protected] Email.
Contact Person. +62821 4438 4766
Branch Office :
Ruko Sentra Tropodo Blok B No. 5, Sidoarjo, Surabaya.
Tel. 031-99686654 Mail.
1 (satu) Unit BED ELEVATOR B1600-60-CO-4/4-MR
RSU BHAYANGKARA JOMBANG - TAHUN 2024
1
PT. CATUR MANUNGGAL PAKERTI
Indonesia Authorized Sales
BED / HOSPITAL ELEVATOR OVERVIEW
MACHINE ROOM TYPE
Fuji Japan Elevator Machine Room Bed Elevator is medical elevator series, taking full account of the uniqueness of the hospital environment, using the world’s cutting-edge mpdular computer control technology, formed a highly integrated VVVF serial communication control system, so that the elevator brake smooth, smooth operation, patient times feel comfortable.
The design of multiple safety features effectively reduces the probability of accidents and allows and inaccessible patients access.
2
PT. CATUR MANUNGGAL PAKERTI
Indonesia Authorized Sales
CAR DESIGN
Buyer CMP Other Other
Front Wall : Stainless Steel Side Wall : Stainless Steel Rear Wall : Miror Etching with Logo
Cabin Design Etching Mirror Option
F-BC01
F-K41 F-K14
F-K12 F-K13
F-K40 F-K04
F-K04
3
PT. CATUR MANUNGGAL PAKERTI
Indonesia Authorized Sales
CEILING DESIGN OPTION
Buyer CMP Other Other
4
PT. CATUR MANUNGGAL PAKERTI
Indonesia Authorized Sales
FLOORING & HANDRAIL DESIGN OPTION
Buyer BGN CMP Other
5
PT. CATUR MANUNGGAL PAKERTI
Indonesia Authorized Sales
CAR OPERATING PANEL (COP) | HALL OPERATING PANEL (HOP)
Buyer BGN CMP Other
Standard Version Deluxe Version
Numbering Floor Lt 1 : ………
Lt 2 : ………
Lt 3 : ……..
Lt 4 : …….
6
PT. CATUR MANUNGGAL PAKERTI
Indonesia Authorized Sales
ELEVATOR SCOUP OF WORK – RS. MMC
N
O WORK DESCRIPTIONS By. CMP By. Others
A
. LIFT INSTALLATION WORK
1 Plumb Line +
2 Shaft/Hoistway installation:
a. Rail Brakets, Rail, Jamb, Hall Doors +
b. Car, Cwt, Governor, Buffer assembling +
c. Circuit wiring, Hall indicator, Indicator +
3 Machine Room Installations:
a. Traction Machine +
b. Governor +
c. Receiving Distribution Panel +
d. Floor Control Panel +
4 Installation Outside of Shaft/Hoistway:
a. Traffic System +
b. Interphone System (Exc. Cable Line) +
5 Test Running +
B
. CIVIL WORKS
1 Pit and Shaft Cleaning (water and garbage) +
2 Supply and install:
a. Sparing and block out in M/C Room for
Car, Cwt, Governer ropes, Fan +
b. Sparing and block out for box indicator +
and Hall button +
c. Traction Machine Foundation +
3 Facility for Hoisting Lift Equipment +
4 Equipment ware house at Ground Floor +
5 Power Source for Installation working +
7
PT. CATUR MANUNGGAL PAKERTI
Indonesia Authorized Sales
6 Power Source for Running Test Commissioning +
7 Grouting & Finishing for indicator, button and Jamb +
8 Sill Support +
NO WORK DESCRIPTIONS By. CMP By. Others
C. OTHERS
1
Supply and install Power Panel (SDP) at Machine
Room +
2 Supply, Install and Connection Power Cable from MDB (Main Distribution Board) to SDP at Machine
Room
+
3 Conection Cable From SDP to Lift Control Panel
+
4 Bamboo or Scaffolding inside Shaft/Hoistway +
5 Removing Scaffolding after installation finish +
6 Air Conditioning in Machine Room +
7 Lighting in Machine Room +
8 Supervisory Panel Not Available Not Available
9 Cable for Supervisory Panel Not Available Not Available
10 Separator Beam +
11 Hoisting Hook +
12 Inspection Plug (Receptacle) +
13 Pit Ladder +
14 Cinder Conrete +
15 Water Profing Finish +
16 Lamp Of Hoistway +
Buyer CMP Other Other
8
PT. CATUR MANUNGGAL PAKERTI
Indonesia Authorized Sales