1 PRAKTIKUM SOFTWARE BIM 112 days Mon 07/08/23 Tue 09/01/24

2 PEKERJAAN STRUKTUR 100 days Mon 07/08/23 Fri 22/12/23

3 PONDASI 32 days Mon 07/08/23 Tue 19/09/23

4 Spun Pile D (400) mm 14 days Mon 07/08/23 Thu 24/08/23

5 Pilecap PC 1 (2500) x (3000) x (870) mm 14 days Fri 25/08/23 Wed 13/09/23 4

6 Pilecap PC 2 (2500) x (2500) x (770) mm 14 days Fri 25/08/23 Wed 13/09/23 5SS

7 Pilecap PC 3 (2500) x (5000) x (670) mm 14 days Fri 25/08/23 Wed 13/09/23 6SS

8 Kolom K1 (770) x (770) mm(Pedestal) 4 days Thu 14/09/23 Tue 19/09/23 7

9 Kolom K2 (670) x (670) mm(Pedestal) 4 days Thu 14/09/23 Tue 19/09/23 8SS

10 Kolom K3 (570) x (570) mm(Pedestal) 3 days Thu 14/09/23 Mon 18/09/23 9SS

11 LANTAI 1 11 days Wed 20/09/23 Wed 04/10/23

12 Sloof S1 (470) x (720) mm(Lantai 1) 5 days Wed 20/09/23 Tue 26/09/23 8

13 Sloof S2 (420) x (570) mm(Lantai 1) 5 days Wed 20/09/23 Tue 26/09/23 12SS

14 Sloof S3 (320) x (520) mm(Lantai 1) 5 days Wed 20/09/23 Tue 26/09/23 13SS

15 Sloof S4 (270) x (470) mm(Lantai 1) 5 days Wed 20/09/23 Tue 26/09/23 14SS

16 Kolom K1 (770) x (770) mm(Lantai 1) 6 days Wed 27/09/23 Wed 04/10/23 15

17 Pekerjaan Pembesian(Lantai 1) 5 days Wed 20/09/23 Tue 26/09/23 12SS

18 Kolom K2 (670) x (670) mm(Lantai 1) 6 days Wed 27/09/23 Wed 04/10/23 16SS

19 Kolom K3 (570) x (570) mm(Lantai 1) 6 days Wed 27/09/23 Wed 04/10/23 18SS

20 Plat Lantai t=15 cm(Lantai 1) 5 days Wed 20/09/23 Tue 26/09/23 12SS

21 LANTAI 2 11 days Thu 05/10/23 Thu 19/10/23

22 Balok B1 (470) x (720) mm(Lantai 2) 5 days Thu 05/10/23 Wed 11/10/23 19

23 Pekerjaan Pembesian(Lantai 2) 5 days Thu 05/10/23 Wed 11/10/23 22SS

24 Balok B2 (420) x (570) mm(Lantai 2) 5 days Thu 05/10/23 Wed 11/10/23 23SS

25 Balok B3 (370) x (520) mm(Lantai 2) 5 days Thu 05/10/23 Wed 11/10/23 24SS

26 Balok B4 (270) x (470) mm(Lantai 2) 5 days Thu 05/10/23 Wed 11/10/23 25SS

27 Kolom K1 (770) x (770) mm(Lantai 2) 6 days Thu 12/10/23 Thu 19/10/23 26

28 Kolom K2 (670) x (670) mm(Lantai 2) 6 days Thu 12/10/23 Thu 19/10/23 27SS

29 Kolom K3 (570) x (570) mm(Lantai 2) 5 days Thu 12/10/23 Wed 18/10/23 28SS

30 Plat Lantai t=15 cm(Lantai 2) 5 days Thu 05/10/23 Wed 11/10/23 26SS

31 LANTAI 3 11 days Thu 19/10/23 Thu 02/11/23

32 Balok B1 (470) x (720) mm(Lantai 3) 5 days Thu 19/10/23 Wed 25/10/23 29

33 Balok B2 (420) x (570) mm(Lantai 3) 5 days Thu 19/10/23 Wed 25/10/23 32SS

34 Balok B3 (370) x (520) mm(Lantai 3) 5 days Thu 19/10/23 Wed 25/10/23 33SS

35 Balok B4 (270) x (470) mm(Lantai 3) 5 days Thu 19/10/23 Wed 25/10/23 34SS

36 Balok Kantiliver BK 1 (150) x (300) mm(Lantai 3) 5 days Thu 19/10/23 Wed 25/10/23 35SS

37 Balok Kantiliver BK 2 (100) x (375) mm(Lantai 3) 5 days Thu 19/10/23 Wed 25/10/23 36SS

38 Kolom K1 (770) x (770) mm(Lantai 3) 6 days Thu 26/10/23 Thu 02/11/23 37

39 Kolom K3 (570) x (570) mm(Lantai 3) 6 days Thu 26/10/23 Thu 02/11/23 38SS

PEKERJAAN STRUKTUR PONDASI

Spun Pile D (400) mm

Pilecap PC 1 (2500) x (3000) x (870) mm Pilecap PC 2 (2500) x (2500) x (770) mm Pilecap PC 3 (2500) x (5000) x (670) mm Kolom K1 (770) x (770) mm(Pedestal) Kolom K2 (670) x (670) mm(Pedestal) Kolom K3 (570) x (570) mm(Pedestal)

LANTAI 1

Sloof S1 (470) x (720) mm(Lantai 1) Sloof S2 (420) x (570) mm(Lantai 1) Sloof S3 (320) x (520) mm(Lantai 1) Sloof S4 (270) x (470) mm(Lantai 1)

Kolom K1 (770) x (770) mm(Lantai 1) Pekerjaan Pembesian(Lantai 1)

Kolom K2 (670) x (670) mm(Lantai 1) Kolom K3 (570) x (570) mm(Lantai 1) Plat Lantai t=15 cm(Lantai 1)

LANTAI 2

Balok B1 (470) x (720) mm(Lantai 2) Pekerjaan Pembesian(Lantai 2) Balok B2 (420) x (570) mm(Lantai 2) Balok B3 (370) x (520) mm(Lantai 2) Balok B4 (270) x (470) mm(Lantai 2)

Kolom K1 (770) x (770) mm(Lantai 2) Kolom K2 (670) x (670) mm(Lantai 2) Kolom K3 (570) x (570) mm(Lantai 2) Plat Lantai t=15 cm(Lantai 2)

LANTAI 3

Balok B1 (470) x (720) mm(Lantai 3) Balok B2 (420) x (570) mm(Lantai 3) Balok B3 (370) x (520) mm(Lantai 3) Balok B4 (270) x (470) mm(Lantai 3)

Balok Kantiliver BK 1 (150) x (300) mm(Lantai 3) Balok Kantiliver BK 2 (100) x (375) mm(Lantai 3)

Kolom K1 (770) x (770) mm(Lantai 3) Kolom K3 (570) x (570) mm(Lantai 3)

B M E B M E B M E B M E B M E B

(2)

40 Plat Lantai t=10 cm(Lantai 3) 5 days Thu 19/10/23 Wed 25/10/23 37SS

41 Plat Lantai t=15 cm(Lantai 3) 5 days Thu 19/10/23 Wed 25/10/23 40SS

42 LANTAI 4 11 days Fri 03/11/23 Fri 17/11/23

43 Balok B1 (470) x (720) mm(Lantai 4) 5 days Fri 03/11/23 Thu 09/11/23 39

44 Balok B2 (420) x (570) mm(Lantai 4) 5 days Fri 03/11/23 Thu 09/11/23 43SS

45 Balok B3 (370) x (520) mm(Lantai 4) 5 days Fri 03/11/23 Thu 09/11/23 44SS

46 Balok B4 (270) x (470) mm(Lantai 4) 5 days Fri 03/11/23 Thu 09/11/23 45SS

47 Kolom K1 (770) x (770) mm(Lantai 4) 6 days Fri 10/11/23 Fri 17/11/23 46

48 Kolom K3 (570) x (570) mm(Lantai 4) 6 days Fri 10/11/23 Fri 17/11/23 47SS

49 Plat Lantai t=15 cm(Lantai 4) 5 days Fri 03/11/23 Thu 09/11/23 46SS

50 LANTAI ATAP 7 days Mon 20/11/23 Tue 28/11/23

51 Balok B1 (470) x (720) mm(Lantai Atap) 5 days Mon 20/11/23 Fri 24/11/23 48

52 Balok B2 (420) x (570) mm(Lantai Atap) 5 days Mon 20/11/23 Fri 24/11/23 51SS

53 Balok B3 (370) x (520) mm(Lantai Atap) 5 days Mon 20/11/23 Fri 24/11/23 52SS

54 Balok B4 (270) x (470) mm(Lantai Atap) 7 days Mon 20/11/23 Tue 28/11/23 53SS

55 Balok Kantiliver BK 1 (150) x (300) mm(Lantai Atap) 5 days Mon 20/11/23 Fri 24/11/23 54SS

56 Balok Kantiliver BK 2 (100) x (375) mm(Lantai Atap) 5 days Mon 20/11/23 Fri 24/11/23 55SS

57 Plat Lantai t=10 cm(Lantai Atap) 5 days Mon 20/11/23 Fri 24/11/23 56SS

58 PEKERJAAN BAJA 20 days Mon 27/11/23 Fri 22/12/23

59 Kolom (WF 300.150.6.5.9) 4 days Mon 27/11/23 Thu 30/11/23 57

60 Kolom (WF 250.150.6.9) 4 days Mon 27/11/23 Thu 30/11/23 59SS

61 Rafter (WF 250.125.6.9) 8 days Fri 01/12/23 Tue 12/12/23 59

62 Gording (C 150) 8 days Wed 13/12/23 Fri 22/12/23 61

63 Angkur Baja 4 days Mon 27/11/23 Thu 30/11/23 59SS

64 Baut D10 mm 8 days Wed 13/12/23 Fri 22/12/23 62SS

65 Baut D16 mm 10 days Fri 01/12/23 Thu 14/12/23 61SS

66 Plat Sambungan 10 days Fri 01/12/23 Thu 14/12/23 61SS

67 Profil Sambungan 10 days Fri 01/12/23 Thu 14/12/23 66SS

68 PEKERJAAN STRUKTUR TANGGA 23 days Wed 11/10/23 Fri 10/11/23

69 Beton Tangga Lt.1 ke Lt.2 7 days Thu 12/10/23 Fri 20/10/23 30

70 Beton Tangga Lt.2 ke Lt.3 7 days Thu 26/10/23 Fri 03/11/23 41

71 Beton Tangga Lt.3 ke Lt.4 7 days Fri 10/11/23 Mon 20/11/23 49

72 PEKERJAAN ARSITEKTURAL 59 days Thu 19/10/23 Tue 09/01/24

73 LANTAI 1 31 days Thu 19/10/23 Thu 30/11/23

74 PEKERJAAN DINDING 7 days Thu 19/10/23 Fri 27/10/23

75 Pasangan Bata Hebel(Lantai 1) 7 days Thu 19/10/23 Fri 27/10/23 32SS

76 Plesteran Dinding(Lantai 1) 5 days Thu 19/10/23 Wed 25/10/23 75SS

77 Acian(Lantai 1) 5 days Thu 19/10/23 Wed 25/10/23 76SS

78 PEKERJAAN PINTU DAN JENDELA 3 days Tue 28/11/23 Thu 30/11/23

Plat Lantai t=10 cm(Lantai 3) Plat Lantai t=15 cm(Lantai 3)

LANTAI 4

Balok B1 (470) x (720) mm(Lantai 4) Balok B2 (420) x (570) mm(Lantai 4) Balok B3 (370) x (520) mm(Lantai 4) Balok B4 (270) x (470) mm(Lantai 4)

Kolom K1 (770) x (770) mm(Lantai 4) Kolom K3 (570) x (570) mm(Lantai 4) Plat Lantai t=15 cm(Lantai 4)

LANTAI ATAP

Balok B1 (470) x (720) mm(Lantai Atap) Balok B2 (420) x (570) mm(Lantai Atap) Balok B3 (370) x (520) mm(Lantai Atap)

Balok B4 (270) x (470) mm(Lantai Atap)

Balok Kantiliver BK 1 (150) x (300) mm(Lantai Atap) Balok Kantiliver BK 2 (100) x (375) mm(Lantai Atap) Plat Lantai t=10 cm(Lantai Atap)

PEKERJAAN BAJA Kolom (WF 300.150.6.5.9) Kolom (WF 250.150.6.9)

Rafter (WF 250.125.6.9) Gording (C 150) Angkur Baja

Baut D10 mm Baut D16 mm Plat Sambungan Profil Sambungan PEKERJAAN STRUKTUR TANGGA Beton Tangga Lt.1 ke Lt.2

Beton Tangga Lt.2 ke Lt.3

Beton Tangga Lt.3 ke Lt.4

LANTAI 1 PEKERJAAN DINDING

Pasangan Bata Hebel(Lantai 1) Plesteran Dinding(Lantai 1) Acian(Lantai 1)

PEKERJAAN PINTU DAN JENDELA

B M E B M E B M E B M E B M E B

(3)

79 Pintu P1(Lantai 1) 3 days Tue 28/11/23 Thu 30/11/23 135

80 Pintu P2(Lantai 1) 3 days Tue 28/11/23 Thu 30/11/23 79SS

81 Pintu P3(Lantai 1) 3 days Tue 28/11/23 Thu 30/11/23 80SS

82 Jendela J1(Lantai 1) 3 days Tue 28/11/23 Thu 30/11/23 81SS

83 Jendela J2(Lantai 1) 3 days Tue 28/11/23 Thu 30/11/23 82SS

84 Jendela J3(Lantai 1) 3 days Tue 28/11/23 Thu 30/11/23 83SS

85 Jendela Boven(Lantai 1) 3 days Tue 28/11/23 Thu 30/11/23 84SS

86 PEKERJAAN LANTAI 4 days Thu 02/11/23 Tue 07/11/23

87 Pasangan Keramik 60x60 Titanium Statuario Grey(Lantai 1) 4 days Thu 02/11/23 Tue 07/11/23 88SS

88 Pasangan Keramik 60x60 Infinity Sandstone Grey(Lantai 1) 4 days Thu 02/11/23 Tue 07/11/23 89SS

89 Mortar Pas. Keramik(Lantai 1) 4 days Thu 02/11/23 Tue 07/11/23 92

90 PEKERJAAN PLAFON 5 days Thu 26/10/23 Wed 01/11/23

91 Pasangan Plafon Kalsiboard 4,5 mm(Lantai 1) 5 days Thu 26/10/23 Wed 01/11/23 77

92 Pasangan Plafon Gypsum 9 mm(Lantai 1) 5 days Thu 26/10/23 Wed 01/11/23 91SS

93 LANTAI 2 23 days Fri 03/11/23 Tue 05/12/23

94 PEKERJAAN DINDING 4 days Fri 03/11/23 Wed 08/11/23

95 Pasangan Bata Hebel(Lantai 2) 4 days Fri 03/11/23 Wed 08/11/23 43SS

96 Plesteran Dinding(Lantai 2) 3 days Fri 03/11/23 Tue 07/11/23 95SS

97 Acian(Lantai 2) 3 days Fri 03/11/23 Tue 07/11/23 96SS

98 PEKERJAAN PINTU DAN JENDELA 3 days Fri 01/12/23 Tue 05/12/23

99 Pintu P2(Lantai 2) 3 days Fri 01/12/23 Tue 05/12/23 85

100 Pintu P3(Lantai 2) 3 days Fri 01/12/23 Tue 05/12/23 99SS

101 Jendela J1(Lantai 2) 3 days Fri 01/12/23 Tue 05/12/23 100SS

102 Jendela J2(Lantai 2) 3 days Fri 01/12/23 Tue 05/12/23 101SS

103 Jendela J3(Lantai 2) 3 days Fri 01/12/23 Tue 05/12/23 102SS

104 Jendela Boven(Lantai 2) 3 days Fri 01/12/23 Tue 05/12/23 103SS

105 PEKERJAAN LANTAI 4 days Wed 15/11/23 Mon 20/11/23

106 Pasangan Keramik 60x60 Titanium Statuario Grey(Lantai 2) 4 days Wed 15/11/23 Mon 20/11/23 107SS

107 Pasangan Keramik 60x60 Infinity Sandstone Grey(Lantai 2) 4 days Wed 15/11/23 Mon 20/11/23 108SS

108 Mortar Pas. Keramik(Lantai 2) 4 days Wed 15/11/23 Mon 20/11/23 111

109 PEKERJAAN PLAFOND 5 days Wed 08/11/23 Tue 14/11/23

110 Pasangan Plafon Kalsiboard 4,5 mm(Lantai 2) 5 days Wed 08/11/23 Tue 14/11/23 97

111 Pasangan Plafon Gypsum 9 mm(Lantai 2) 5 days Wed 08/11/23 Tue 14/11/23 110SS

112 LANTAI 3 15 days Mon 20/11/23 Fri 08/12/23

113 PEKERJAAN DINDING 4 days Mon 20/11/23 Thu 23/11/23

114 Pasangan Bata Hebel(Lantai 3) 4 days Mon 20/11/23 Thu 23/11/23 51SS

115 Plesteran Dinding(Lantai 3) 3 days Mon 20/11/23 Wed 22/11/23 114SS

116 Acian(Lantai 3) 3 days Mon 20/11/23 Wed 22/11/23 115SS

117 PEKERJAAN PINTU DAN JENDELA 3 days Wed 06/12/23 Fri 08/12/23

Pintu P1(Lantai 1) Pintu P2(Lantai 1) Pintu P3(Lantai 1) Jendela J1(Lantai 1) Jendela J2(Lantai 1) Jendela J3(Lantai 1) Jendela Boven(Lantai 1) PEKERJAAN LANTAI

Pasangan Keramik 60x60 Titanium Statuario Grey(Lantai 1) Pasangan Keramik 60x60 Infinity Sandstone Grey(Lantai 1) Mortar Pas. Keramik(Lantai 1)

PEKERJAAN PLAFON

Pasangan Plafon Kalsiboard 4,5 mm(Lantai 1) Pasangan Plafon Gypsum 9 mm(Lantai 1)

LANTAI 2 PEKERJAAN DINDING

Pasangan Bata Hebel(Lantai 2) Plesteran Dinding(Lantai 2) Acian(Lantai 2)

PEKERJAAN PINTU DAN JENDELA Pintu P2(Lantai 2)

Pintu P3(Lantai 2) Jendela J1(Lantai 2) Jendela J2(Lantai 2) Jendela J3(Lantai 2) Jendela Boven(Lantai 2) PEKERJAAN LANTAI

Pasangan Keramik 60x60 Titanium Statuario Grey(Lantai 2) Pasangan Keramik 60x60 Infinity Sandstone Grey(Lantai 2) Mortar Pas. Keramik(Lantai 2)

PEKERJAAN PLAFOND

Pasangan Plafon Kalsiboard 4,5 mm(Lantai 2) Pasangan Plafon Gypsum 9 mm(Lantai 2)

LANTAI 3 PEKERJAAN DINDING

Pasangan Bata Hebel(Lantai 3) Plesteran Dinding(Lantai 3) Acian(Lantai 3)

PEKERJAAN PINTU DAN JENDELA

B M E B M E B M E B M E B M E B

(4)

118 Pintu P2(Lantai 3) 3 days Wed 06/12/23 Fri 08/12/23 104

119 Pintu P3(Lantai 3) 3 days Wed 06/12/23 Fri 08/12/23 118SS

120 Jendela J1(Lantai 3) 3 days Wed 06/12/23 Fri 08/12/23 119SS

121 Jendela J2(Lantai 3) 3 days Wed 06/12/23 Fri 08/12/23 120SS

122 Jendela J3(Lantai 3) 3 days Wed 06/12/23 Fri 08/12/23 121SS

123 Jendela Boven(Lantai 3) 3 days Wed 06/12/23 Fri 08/12/23 122SS

124 PEKERJAAN LANTAI 4 days Thu 30/11/23 Tue 05/12/23

125 Pasangan Keramik 60x60 Titanium Statuario Grey(Lantai 3) 4 days Thu 30/11/23 Tue 05/12/23 126SS

126 Pasangan Keramik 60x60 Infinity Sandstone Grey(Lantai 3) 4 days Thu 30/11/23 Tue 05/12/23 127SS

127 Mortar Pas. Keramik(Lantai 3) 4 days Thu 30/11/23 Tue 05/12/23 130

128 PEKERJAAN PLAFOND 5 days Thu 23/11/23 Wed 29/11/23

129 Pasangan Plafon Kalsiboard 4,5 mm(Lantai 3) 5 days Thu 23/11/23 Wed 29/11/23 116

130 Pasangan Plafon Gypsum 9 mm(Lantai 3) 5 days Thu 23/11/23 Wed 29/11/23 129SS

131 LANTAI 4 15 days Thu 23/11/23 Wed 13/12/23

132 PEKERJAAN DINDING 4 days Thu 23/11/23 Tue 28/11/23

133 Pasangan Bata Hebel(Lantai 4) 4 days Thu 23/11/23 Tue 28/11/23 116

134 Plesteran Dinding(Lantai 4) 3 days Thu 23/11/23 Mon 27/11/23 133SS

135 Acian(Lantai 4) 3 days Thu 23/11/23 Mon 27/11/23 134SS

136 PEKERJAAN PINTU DAN JENDELA 3 days Mon 11/12/23 Wed 13/12/23

137 Pintu P2(Lantai 4) 3 days Mon 11/12/23 Wed 13/12/23 123

138 Pintu P3(Lantai 4) 3 days Mon 11/12/23 Wed 13/12/23 137SS

139 Jendela J1(Lantai 4) 3 days Mon 11/12/23 Wed 13/12/23 138SS

140 Jendela J2(Lantai 4) 3 days Mon 11/12/23 Wed 13/12/23 139SS

141 Jendela J3(Lantai 4) 3 days Mon 11/12/23 Wed 13/12/23 140SS

142 Jendela Boven(Lantai 4) 3 days Mon 11/12/23 Wed 13/12/23 141SS

143 PEKERJAAN LANTAI 4 days Tue 05/12/23 Fri 08/12/23

144 Pasangan Keramik 60x60 Titanium Statuario Grey(Lantai 4) 4 days Tue 05/12/23 Fri 08/12/23 145SS

145 Pasangan Keramik 60x60 Infinity Sandstone Grey(Lantai 4) 4 days Tue 05/12/23 Fri 08/12/23 146SS

146 Mortar Pas. Keramik(Lantai 3) 4 days Tue 05/12/23 Fri 08/12/23 149

147 PEKERJAAN PLAFOND 5 days Tue 28/11/23 Mon 04/12/23

148 Pasangan Plafon Kalsiboard 4.5 mm(Lantai 4) 5 days Tue 28/11/23 Mon 04/12/23 135

149 Pasangan Plafon Gypsum 9 mm(Lantai 4) 5 days Tue 28/11/23 Mon 04/12/23 148SS

150 LANTAI ATAP 2 days Fri 15/12/23 Mon 18/12/23

151 PEKERJAAN DINDING 2 days Fri 15/12/23 Mon 18/12/23

152 Pasangan Bata Hebel(Lantai Atap) 2 days Fri 15/12/23 Mon 18/12/23 67

153 Plesteran Dinding(Lantai Atap) 2 days Fri 15/12/23 Mon 18/12/23 152SS

154 Acian(Lantai Atap) 2 days Fri 15/12/23 Mon 18/12/23 153SS

155 PEKERJAAN PENGECATAN 6 days Tue 19/12/23 Tue 26/12/23

156 Pengecatan Cat Nippon Paint Pecan Smell 6 days Tue 19/12/23 Tue 26/12/23 154

Pintu P2(Lantai 3) Pintu P3(Lantai 3) Jendela J1(Lantai 3) Jendela J2(Lantai 3) Jendela J3(Lantai 3) Jendela Boven(Lantai 3) PEKERJAAN LANTAI

Pasangan Keramik 60x60 Titanium Statuario Grey(Lantai 3) Pasangan Keramik 60x60 Infinity Sandstone Grey(Lantai 3) Mortar Pas. Keramik(Lantai 3)

PEKERJAAN PLAFOND

Pasangan Plafon Kalsiboard 4,5 mm(Lantai 3) Pasangan Plafon Gypsum 9 mm(Lantai 3)

LANTAI 4 PEKERJAAN DINDING

Pasangan Bata Hebel(Lantai 4) Plesteran Dinding(Lantai 4) Acian(Lantai 4)

PEKERJAAN PINTU DAN JENDELA Pintu P2(Lantai 4)

Pintu P3(Lantai 4) Jendela J1(Lantai 4) Jendela J2(Lantai 4) Jendela J3(Lantai 4) Jendela Boven(Lantai 4) PEKERJAAN LANTAI

Pasangan Keramik 60x60 Titanium Statuario Grey(Lantai 4) Pasangan Keramik 60x60 Infinity Sandstone Grey(Lantai 4) Mortar Pas. Keramik(Lantai 3)

PEKERJAAN PLAFOND

Pasangan Plafon Kalsiboard 4.5 mm(Lantai 4) Pasangan Plafon Gypsum 9 mm(Lantai 4)

LANTAI ATAP

PEKERJAAN DINDING

Pasangan Bata Hebel(Lantai Atap) Plesteran Dinding(Lantai Atap) Acian(Lantai Atap)

PEKERJAAN PENGECATAN

Pengecatan Cat Nippon Paint Pecan Smell

B M E B M E B M E B M E B M E B

(5)

157 Pengecatan Cat Nippon Paint Swanlike 6 days Tue 19/12/23 Tue 26/12/23 156SS

158 Pengecatan Cat Nippon Paint Warm Toast 6 days Tue 19/12/23 Tue 26/12/23 157SS

159 PEKERJAAN PENUTUP ATAP 2 days Tue 19/12/23 Wed 20/12/23

160 Penutup Atap 2 days Tue 19/12/23 Wed 20/12/23 152

161 Lisplang 2 days Tue 19/12/23 Wed 20/12/23 160SS

162 PEKERJAAN ENDING PLAFON 7 days Tue 05/12/23 Wed 13/12/23

163 Ending Plafon Gypsum 9 mm 7 days Tue 05/12/23 Wed 13/12/23 149

164 PEKERJAAN FAÇADE 10 days Wed 27/12/23 Tue 09/01/24

165 Pemasangan Kaca Curtain Wall 10 days Wed 27/12/23 Tue 09/01/24 158

166 Pemasangan Mullion 10 days Wed 27/12/23 Tue 09/01/24 165SS

Pengecatan Cat Nippon Paint Swanlike Pengecatan Cat Nippon Paint Warm Toast PEKERJAAN PENUTUP ATAP

Penutup Atap Lisplang

PEKERJAAN ENDING PLAFON Ending Plafon Gypsum 9 mm

B M E B M E B M E B M E B M E B

Referensi

Dokumen terkait

Lampiran B2 SULIT KERAJAAN ……… JADUAL TENDER Nombor Tender : Tajuk : Tarikh Tender Ditutup Jenis Tender: Kelas/Kepala/Sub-Kepala Haribulan: yang ditetapkan: Jam: Anggaran

Jadual menyenaraikan hospital-hospital di Sumatera Utara berserta maklumat seperti nama, lokasi, jenis kelas, kepemilikan, tarikh kemas kini, nombor surat izin operasi, tarikh surat izin operasi, masa berlakunya operasi, kerjasama BPJS, tarikh akreditasi, status akreditasi, masa berlakunya akreditasi, bank darah, jumlah katil bukan Covid dan jumlah katil