1 PRAKTIKUM SOFTWARE BIM 112 days Mon 07/08/23 Tue 09/01/24
2 PEKERJAAN STRUKTUR 100 days Mon 07/08/23 Fri 22/12/23
3 PONDASI 32 days Mon 07/08/23 Tue 19/09/23
4 Spun Pile D (400) mm 14 days Mon 07/08/23 Thu 24/08/23
5 Pilecap PC 1 (2500) x (3000) x (870) mm 14 days Fri 25/08/23 Wed 13/09/23 4
6 Pilecap PC 2 (2500) x (2500) x (770) mm 14 days Fri 25/08/23 Wed 13/09/23 5SS
7 Pilecap PC 3 (2500) x (5000) x (670) mm 14 days Fri 25/08/23 Wed 13/09/23 6SS
8 Kolom K1 (770) x (770) mm(Pedestal) 4 days Thu 14/09/23 Tue 19/09/23 7
9 Kolom K2 (670) x (670) mm(Pedestal) 4 days Thu 14/09/23 Tue 19/09/23 8SS
10 Kolom K3 (570) x (570) mm(Pedestal) 3 days Thu 14/09/23 Mon 18/09/23 9SS
11 LANTAI 1 11 days Wed 20/09/23 Wed 04/10/23
12 Sloof S1 (470) x (720) mm(Lantai 1) 5 days Wed 20/09/23 Tue 26/09/23 8
13 Sloof S2 (420) x (570) mm(Lantai 1) 5 days Wed 20/09/23 Tue 26/09/23 12SS
14 Sloof S3 (320) x (520) mm(Lantai 1) 5 days Wed 20/09/23 Tue 26/09/23 13SS
15 Sloof S4 (270) x (470) mm(Lantai 1) 5 days Wed 20/09/23 Tue 26/09/23 14SS
16 Kolom K1 (770) x (770) mm(Lantai 1) 6 days Wed 27/09/23 Wed 04/10/23 15
17 Pekerjaan Pembesian(Lantai 1) 5 days Wed 20/09/23 Tue 26/09/23 12SS
18 Kolom K2 (670) x (670) mm(Lantai 1) 6 days Wed 27/09/23 Wed 04/10/23 16SS
19 Kolom K3 (570) x (570) mm(Lantai 1) 6 days Wed 27/09/23 Wed 04/10/23 18SS
20 Plat Lantai t=15 cm(Lantai 1) 5 days Wed 20/09/23 Tue 26/09/23 12SS
21 LANTAI 2 11 days Thu 05/10/23 Thu 19/10/23
22 Balok B1 (470) x (720) mm(Lantai 2) 5 days Thu 05/10/23 Wed 11/10/23 19
23 Pekerjaan Pembesian(Lantai 2) 5 days Thu 05/10/23 Wed 11/10/23 22SS
24 Balok B2 (420) x (570) mm(Lantai 2) 5 days Thu 05/10/23 Wed 11/10/23 23SS
25 Balok B3 (370) x (520) mm(Lantai 2) 5 days Thu 05/10/23 Wed 11/10/23 24SS
26 Balok B4 (270) x (470) mm(Lantai 2) 5 days Thu 05/10/23 Wed 11/10/23 25SS
27 Kolom K1 (770) x (770) mm(Lantai 2) 6 days Thu 12/10/23 Thu 19/10/23 26
28 Kolom K2 (670) x (670) mm(Lantai 2) 6 days Thu 12/10/23 Thu 19/10/23 27SS
29 Kolom K3 (570) x (570) mm(Lantai 2) 5 days Thu 12/10/23 Wed 18/10/23 28SS
30 Plat Lantai t=15 cm(Lantai 2) 5 days Thu 05/10/23 Wed 11/10/23 26SS
31 LANTAI 3 11 days Thu 19/10/23 Thu 02/11/23
32 Balok B1 (470) x (720) mm(Lantai 3) 5 days Thu 19/10/23 Wed 25/10/23 29
33 Balok B2 (420) x (570) mm(Lantai 3) 5 days Thu 19/10/23 Wed 25/10/23 32SS
34 Balok B3 (370) x (520) mm(Lantai 3) 5 days Thu 19/10/23 Wed 25/10/23 33SS
35 Balok B4 (270) x (470) mm(Lantai 3) 5 days Thu 19/10/23 Wed 25/10/23 34SS
36 Balok Kantiliver BK 1 (150) x (300) mm(Lantai 3) 5 days Thu 19/10/23 Wed 25/10/23 35SS
37 Balok Kantiliver BK 2 (100) x (375) mm(Lantai 3) 5 days Thu 19/10/23 Wed 25/10/23 36SS
38 Kolom K1 (770) x (770) mm(Lantai 3) 6 days Thu 26/10/23 Thu 02/11/23 37
39 Kolom K3 (570) x (570) mm(Lantai 3) 6 days Thu 26/10/23 Thu 02/11/23 38SS
PEKERJAAN STRUKTUR PONDASI
Spun Pile D (400) mm
Pilecap PC 1 (2500) x (3000) x (870) mm Pilecap PC 2 (2500) x (2500) x (770) mm Pilecap PC 3 (2500) x (5000) x (670) mm Kolom K1 (770) x (770) mm(Pedestal) Kolom K2 (670) x (670) mm(Pedestal) Kolom K3 (570) x (570) mm(Pedestal)
LANTAI 1
Sloof S1 (470) x (720) mm(Lantai 1) Sloof S2 (420) x (570) mm(Lantai 1) Sloof S3 (320) x (520) mm(Lantai 1) Sloof S4 (270) x (470) mm(Lantai 1)
Kolom K1 (770) x (770) mm(Lantai 1) Pekerjaan Pembesian(Lantai 1)
Kolom K2 (670) x (670) mm(Lantai 1) Kolom K3 (570) x (570) mm(Lantai 1) Plat Lantai t=15 cm(Lantai 1)
LANTAI 2
Balok B1 (470) x (720) mm(Lantai 2) Pekerjaan Pembesian(Lantai 2) Balok B2 (420) x (570) mm(Lantai 2) Balok B3 (370) x (520) mm(Lantai 2) Balok B4 (270) x (470) mm(Lantai 2)
Kolom K1 (770) x (770) mm(Lantai 2) Kolom K2 (670) x (670) mm(Lantai 2) Kolom K3 (570) x (570) mm(Lantai 2) Plat Lantai t=15 cm(Lantai 2)
LANTAI 3
Balok B1 (470) x (720) mm(Lantai 3) Balok B2 (420) x (570) mm(Lantai 3) Balok B3 (370) x (520) mm(Lantai 3) Balok B4 (270) x (470) mm(Lantai 3)
Balok Kantiliver BK 1 (150) x (300) mm(Lantai 3) Balok Kantiliver BK 2 (100) x (375) mm(Lantai 3)
Kolom K1 (770) x (770) mm(Lantai 3) Kolom K3 (570) x (570) mm(Lantai 3)
B M E B M E B M E B M E B M E B
40 Plat Lantai t=10 cm(Lantai 3) 5 days Thu 19/10/23 Wed 25/10/23 37SS
41 Plat Lantai t=15 cm(Lantai 3) 5 days Thu 19/10/23 Wed 25/10/23 40SS
42 LANTAI 4 11 days Fri 03/11/23 Fri 17/11/23
43 Balok B1 (470) x (720) mm(Lantai 4) 5 days Fri 03/11/23 Thu 09/11/23 39
44 Balok B2 (420) x (570) mm(Lantai 4) 5 days Fri 03/11/23 Thu 09/11/23 43SS
45 Balok B3 (370) x (520) mm(Lantai 4) 5 days Fri 03/11/23 Thu 09/11/23 44SS
46 Balok B4 (270) x (470) mm(Lantai 4) 5 days Fri 03/11/23 Thu 09/11/23 45SS
47 Kolom K1 (770) x (770) mm(Lantai 4) 6 days Fri 10/11/23 Fri 17/11/23 46
48 Kolom K3 (570) x (570) mm(Lantai 4) 6 days Fri 10/11/23 Fri 17/11/23 47SS
49 Plat Lantai t=15 cm(Lantai 4) 5 days Fri 03/11/23 Thu 09/11/23 46SS
50 LANTAI ATAP 7 days Mon 20/11/23 Tue 28/11/23
51 Balok B1 (470) x (720) mm(Lantai Atap) 5 days Mon 20/11/23 Fri 24/11/23 48
52 Balok B2 (420) x (570) mm(Lantai Atap) 5 days Mon 20/11/23 Fri 24/11/23 51SS
53 Balok B3 (370) x (520) mm(Lantai Atap) 5 days Mon 20/11/23 Fri 24/11/23 52SS
54 Balok B4 (270) x (470) mm(Lantai Atap) 7 days Mon 20/11/23 Tue 28/11/23 53SS
55 Balok Kantiliver BK 1 (150) x (300) mm(Lantai Atap) 5 days Mon 20/11/23 Fri 24/11/23 54SS
56 Balok Kantiliver BK 2 (100) x (375) mm(Lantai Atap) 5 days Mon 20/11/23 Fri 24/11/23 55SS
57 Plat Lantai t=10 cm(Lantai Atap) 5 days Mon 20/11/23 Fri 24/11/23 56SS
58 PEKERJAAN BAJA 20 days Mon 27/11/23 Fri 22/12/23
59 Kolom (WF 300.150.6.5.9) 4 days Mon 27/11/23 Thu 30/11/23 57
60 Kolom (WF 250.150.6.9) 4 days Mon 27/11/23 Thu 30/11/23 59SS
61 Rafter (WF 250.125.6.9) 8 days Fri 01/12/23 Tue 12/12/23 59
62 Gording (C 150) 8 days Wed 13/12/23 Fri 22/12/23 61
63 Angkur Baja 4 days Mon 27/11/23 Thu 30/11/23 59SS
64 Baut D10 mm 8 days Wed 13/12/23 Fri 22/12/23 62SS
65 Baut D16 mm 10 days Fri 01/12/23 Thu 14/12/23 61SS
66 Plat Sambungan 10 days Fri 01/12/23 Thu 14/12/23 61SS
67 Profil Sambungan 10 days Fri 01/12/23 Thu 14/12/23 66SS
68 PEKERJAAN STRUKTUR TANGGA 23 days Wed 11/10/23 Fri 10/11/23
69 Beton Tangga Lt.1 ke Lt.2 7 days Thu 12/10/23 Fri 20/10/23 30
70 Beton Tangga Lt.2 ke Lt.3 7 days Thu 26/10/23 Fri 03/11/23 41
71 Beton Tangga Lt.3 ke Lt.4 7 days Fri 10/11/23 Mon 20/11/23 49
72 PEKERJAAN ARSITEKTURAL 59 days Thu 19/10/23 Tue 09/01/24
73 LANTAI 1 31 days Thu 19/10/23 Thu 30/11/23
74 PEKERJAAN DINDING 7 days Thu 19/10/23 Fri 27/10/23
75 Pasangan Bata Hebel(Lantai 1) 7 days Thu 19/10/23 Fri 27/10/23 32SS
76 Plesteran Dinding(Lantai 1) 5 days Thu 19/10/23 Wed 25/10/23 75SS
77 Acian(Lantai 1) 5 days Thu 19/10/23 Wed 25/10/23 76SS
78 PEKERJAAN PINTU DAN JENDELA 3 days Tue 28/11/23 Thu 30/11/23
Plat Lantai t=10 cm(Lantai 3) Plat Lantai t=15 cm(Lantai 3)
LANTAI 4
Balok B1 (470) x (720) mm(Lantai 4) Balok B2 (420) x (570) mm(Lantai 4) Balok B3 (370) x (520) mm(Lantai 4) Balok B4 (270) x (470) mm(Lantai 4)
Kolom K1 (770) x (770) mm(Lantai 4) Kolom K3 (570) x (570) mm(Lantai 4) Plat Lantai t=15 cm(Lantai 4)
LANTAI ATAP
Balok B1 (470) x (720) mm(Lantai Atap) Balok B2 (420) x (570) mm(Lantai Atap) Balok B3 (370) x (520) mm(Lantai Atap)
Balok B4 (270) x (470) mm(Lantai Atap)
Balok Kantiliver BK 1 (150) x (300) mm(Lantai Atap) Balok Kantiliver BK 2 (100) x (375) mm(Lantai Atap) Plat Lantai t=10 cm(Lantai Atap)
PEKERJAAN BAJA Kolom (WF 300.150.6.5.9) Kolom (WF 250.150.6.9)
Rafter (WF 250.125.6.9) Gording (C 150) Angkur Baja
Baut D10 mm Baut D16 mm Plat Sambungan Profil Sambungan PEKERJAAN STRUKTUR TANGGA Beton Tangga Lt.1 ke Lt.2
Beton Tangga Lt.2 ke Lt.3
Beton Tangga Lt.3 ke Lt.4
LANTAI 1 PEKERJAAN DINDING
Pasangan Bata Hebel(Lantai 1) Plesteran Dinding(Lantai 1) Acian(Lantai 1)
PEKERJAAN PINTU DAN JENDELA
B M E B M E B M E B M E B M E B
79 Pintu P1(Lantai 1) 3 days Tue 28/11/23 Thu 30/11/23 135
80 Pintu P2(Lantai 1) 3 days Tue 28/11/23 Thu 30/11/23 79SS
81 Pintu P3(Lantai 1) 3 days Tue 28/11/23 Thu 30/11/23 80SS
82 Jendela J1(Lantai 1) 3 days Tue 28/11/23 Thu 30/11/23 81SS
83 Jendela J2(Lantai 1) 3 days Tue 28/11/23 Thu 30/11/23 82SS
84 Jendela J3(Lantai 1) 3 days Tue 28/11/23 Thu 30/11/23 83SS
85 Jendela Boven(Lantai 1) 3 days Tue 28/11/23 Thu 30/11/23 84SS
86 PEKERJAAN LANTAI 4 days Thu 02/11/23 Tue 07/11/23
87 Pasangan Keramik 60x60 Titanium Statuario Grey(Lantai 1) 4 days Thu 02/11/23 Tue 07/11/23 88SS
88 Pasangan Keramik 60x60 Infinity Sandstone Grey(Lantai 1) 4 days Thu 02/11/23 Tue 07/11/23 89SS
89 Mortar Pas. Keramik(Lantai 1) 4 days Thu 02/11/23 Tue 07/11/23 92
90 PEKERJAAN PLAFON 5 days Thu 26/10/23 Wed 01/11/23
91 Pasangan Plafon Kalsiboard 4,5 mm(Lantai 1) 5 days Thu 26/10/23 Wed 01/11/23 77
92 Pasangan Plafon Gypsum 9 mm(Lantai 1) 5 days Thu 26/10/23 Wed 01/11/23 91SS
93 LANTAI 2 23 days Fri 03/11/23 Tue 05/12/23
94 PEKERJAAN DINDING 4 days Fri 03/11/23 Wed 08/11/23
95 Pasangan Bata Hebel(Lantai 2) 4 days Fri 03/11/23 Wed 08/11/23 43SS
96 Plesteran Dinding(Lantai 2) 3 days Fri 03/11/23 Tue 07/11/23 95SS
97 Acian(Lantai 2) 3 days Fri 03/11/23 Tue 07/11/23 96SS
98 PEKERJAAN PINTU DAN JENDELA 3 days Fri 01/12/23 Tue 05/12/23
99 Pintu P2(Lantai 2) 3 days Fri 01/12/23 Tue 05/12/23 85
100 Pintu P3(Lantai 2) 3 days Fri 01/12/23 Tue 05/12/23 99SS
101 Jendela J1(Lantai 2) 3 days Fri 01/12/23 Tue 05/12/23 100SS
102 Jendela J2(Lantai 2) 3 days Fri 01/12/23 Tue 05/12/23 101SS
103 Jendela J3(Lantai 2) 3 days Fri 01/12/23 Tue 05/12/23 102SS
104 Jendela Boven(Lantai 2) 3 days Fri 01/12/23 Tue 05/12/23 103SS
105 PEKERJAAN LANTAI 4 days Wed 15/11/23 Mon 20/11/23
106 Pasangan Keramik 60x60 Titanium Statuario Grey(Lantai 2) 4 days Wed 15/11/23 Mon 20/11/23 107SS
107 Pasangan Keramik 60x60 Infinity Sandstone Grey(Lantai 2) 4 days Wed 15/11/23 Mon 20/11/23 108SS
108 Mortar Pas. Keramik(Lantai 2) 4 days Wed 15/11/23 Mon 20/11/23 111
109 PEKERJAAN PLAFOND 5 days Wed 08/11/23 Tue 14/11/23
110 Pasangan Plafon Kalsiboard 4,5 mm(Lantai 2) 5 days Wed 08/11/23 Tue 14/11/23 97
111 Pasangan Plafon Gypsum 9 mm(Lantai 2) 5 days Wed 08/11/23 Tue 14/11/23 110SS
112 LANTAI 3 15 days Mon 20/11/23 Fri 08/12/23
113 PEKERJAAN DINDING 4 days Mon 20/11/23 Thu 23/11/23
114 Pasangan Bata Hebel(Lantai 3) 4 days Mon 20/11/23 Thu 23/11/23 51SS
115 Plesteran Dinding(Lantai 3) 3 days Mon 20/11/23 Wed 22/11/23 114SS
116 Acian(Lantai 3) 3 days Mon 20/11/23 Wed 22/11/23 115SS
117 PEKERJAAN PINTU DAN JENDELA 3 days Wed 06/12/23 Fri 08/12/23
Pintu P1(Lantai 1) Pintu P2(Lantai 1) Pintu P3(Lantai 1) Jendela J1(Lantai 1) Jendela J2(Lantai 1) Jendela J3(Lantai 1) Jendela Boven(Lantai 1) PEKERJAAN LANTAI
Pasangan Keramik 60x60 Titanium Statuario Grey(Lantai 1) Pasangan Keramik 60x60 Infinity Sandstone Grey(Lantai 1) Mortar Pas. Keramik(Lantai 1)
PEKERJAAN PLAFON
Pasangan Plafon Kalsiboard 4,5 mm(Lantai 1) Pasangan Plafon Gypsum 9 mm(Lantai 1)
LANTAI 2 PEKERJAAN DINDING
Pasangan Bata Hebel(Lantai 2) Plesteran Dinding(Lantai 2) Acian(Lantai 2)
PEKERJAAN PINTU DAN JENDELA Pintu P2(Lantai 2)
Pintu P3(Lantai 2) Jendela J1(Lantai 2) Jendela J2(Lantai 2) Jendela J3(Lantai 2) Jendela Boven(Lantai 2) PEKERJAAN LANTAI
Pasangan Keramik 60x60 Titanium Statuario Grey(Lantai 2) Pasangan Keramik 60x60 Infinity Sandstone Grey(Lantai 2) Mortar Pas. Keramik(Lantai 2)
PEKERJAAN PLAFOND
Pasangan Plafon Kalsiboard 4,5 mm(Lantai 2) Pasangan Plafon Gypsum 9 mm(Lantai 2)
LANTAI 3 PEKERJAAN DINDING
Pasangan Bata Hebel(Lantai 3) Plesteran Dinding(Lantai 3) Acian(Lantai 3)
PEKERJAAN PINTU DAN JENDELA
B M E B M E B M E B M E B M E B
118 Pintu P2(Lantai 3) 3 days Wed 06/12/23 Fri 08/12/23 104
119 Pintu P3(Lantai 3) 3 days Wed 06/12/23 Fri 08/12/23 118SS
120 Jendela J1(Lantai 3) 3 days Wed 06/12/23 Fri 08/12/23 119SS
121 Jendela J2(Lantai 3) 3 days Wed 06/12/23 Fri 08/12/23 120SS
122 Jendela J3(Lantai 3) 3 days Wed 06/12/23 Fri 08/12/23 121SS
123 Jendela Boven(Lantai 3) 3 days Wed 06/12/23 Fri 08/12/23 122SS
124 PEKERJAAN LANTAI 4 days Thu 30/11/23 Tue 05/12/23
125 Pasangan Keramik 60x60 Titanium Statuario Grey(Lantai 3) 4 days Thu 30/11/23 Tue 05/12/23 126SS
126 Pasangan Keramik 60x60 Infinity Sandstone Grey(Lantai 3) 4 days Thu 30/11/23 Tue 05/12/23 127SS
127 Mortar Pas. Keramik(Lantai 3) 4 days Thu 30/11/23 Tue 05/12/23 130
128 PEKERJAAN PLAFOND 5 days Thu 23/11/23 Wed 29/11/23
129 Pasangan Plafon Kalsiboard 4,5 mm(Lantai 3) 5 days Thu 23/11/23 Wed 29/11/23 116
130 Pasangan Plafon Gypsum 9 mm(Lantai 3) 5 days Thu 23/11/23 Wed 29/11/23 129SS
131 LANTAI 4 15 days Thu 23/11/23 Wed 13/12/23
132 PEKERJAAN DINDING 4 days Thu 23/11/23 Tue 28/11/23
133 Pasangan Bata Hebel(Lantai 4) 4 days Thu 23/11/23 Tue 28/11/23 116
134 Plesteran Dinding(Lantai 4) 3 days Thu 23/11/23 Mon 27/11/23 133SS
135 Acian(Lantai 4) 3 days Thu 23/11/23 Mon 27/11/23 134SS
136 PEKERJAAN PINTU DAN JENDELA 3 days Mon 11/12/23 Wed 13/12/23
137 Pintu P2(Lantai 4) 3 days Mon 11/12/23 Wed 13/12/23 123
138 Pintu P3(Lantai 4) 3 days Mon 11/12/23 Wed 13/12/23 137SS
139 Jendela J1(Lantai 4) 3 days Mon 11/12/23 Wed 13/12/23 138SS
140 Jendela J2(Lantai 4) 3 days Mon 11/12/23 Wed 13/12/23 139SS
141 Jendela J3(Lantai 4) 3 days Mon 11/12/23 Wed 13/12/23 140SS
142 Jendela Boven(Lantai 4) 3 days Mon 11/12/23 Wed 13/12/23 141SS
143 PEKERJAAN LANTAI 4 days Tue 05/12/23 Fri 08/12/23
144 Pasangan Keramik 60x60 Titanium Statuario Grey(Lantai 4) 4 days Tue 05/12/23 Fri 08/12/23 145SS
145 Pasangan Keramik 60x60 Infinity Sandstone Grey(Lantai 4) 4 days Tue 05/12/23 Fri 08/12/23 146SS
146 Mortar Pas. Keramik(Lantai 3) 4 days Tue 05/12/23 Fri 08/12/23 149
147 PEKERJAAN PLAFOND 5 days Tue 28/11/23 Mon 04/12/23
148 Pasangan Plafon Kalsiboard 4.5 mm(Lantai 4) 5 days Tue 28/11/23 Mon 04/12/23 135
149 Pasangan Plafon Gypsum 9 mm(Lantai 4) 5 days Tue 28/11/23 Mon 04/12/23 148SS
150 LANTAI ATAP 2 days Fri 15/12/23 Mon 18/12/23
151 PEKERJAAN DINDING 2 days Fri 15/12/23 Mon 18/12/23
152 Pasangan Bata Hebel(Lantai Atap) 2 days Fri 15/12/23 Mon 18/12/23 67
153 Plesteran Dinding(Lantai Atap) 2 days Fri 15/12/23 Mon 18/12/23 152SS
154 Acian(Lantai Atap) 2 days Fri 15/12/23 Mon 18/12/23 153SS
155 PEKERJAAN PENGECATAN 6 days Tue 19/12/23 Tue 26/12/23
156 Pengecatan Cat Nippon Paint Pecan Smell 6 days Tue 19/12/23 Tue 26/12/23 154
Pintu P2(Lantai 3) Pintu P3(Lantai 3) Jendela J1(Lantai 3) Jendela J2(Lantai 3) Jendela J3(Lantai 3) Jendela Boven(Lantai 3) PEKERJAAN LANTAI
Pasangan Keramik 60x60 Titanium Statuario Grey(Lantai 3) Pasangan Keramik 60x60 Infinity Sandstone Grey(Lantai 3) Mortar Pas. Keramik(Lantai 3)
PEKERJAAN PLAFOND
Pasangan Plafon Kalsiboard 4,5 mm(Lantai 3) Pasangan Plafon Gypsum 9 mm(Lantai 3)
LANTAI 4 PEKERJAAN DINDING
Pasangan Bata Hebel(Lantai 4) Plesteran Dinding(Lantai 4) Acian(Lantai 4)
PEKERJAAN PINTU DAN JENDELA Pintu P2(Lantai 4)
Pintu P3(Lantai 4) Jendela J1(Lantai 4) Jendela J2(Lantai 4) Jendela J3(Lantai 4) Jendela Boven(Lantai 4) PEKERJAAN LANTAI
Pasangan Keramik 60x60 Titanium Statuario Grey(Lantai 4) Pasangan Keramik 60x60 Infinity Sandstone Grey(Lantai 4) Mortar Pas. Keramik(Lantai 3)
PEKERJAAN PLAFOND
Pasangan Plafon Kalsiboard 4.5 mm(Lantai 4) Pasangan Plafon Gypsum 9 mm(Lantai 4)
LANTAI ATAP
PEKERJAAN DINDING
Pasangan Bata Hebel(Lantai Atap) Plesteran Dinding(Lantai Atap) Acian(Lantai Atap)
PEKERJAAN PENGECATAN
Pengecatan Cat Nippon Paint Pecan Smell
B M E B M E B M E B M E B M E B
157 Pengecatan Cat Nippon Paint Swanlike 6 days Tue 19/12/23 Tue 26/12/23 156SS
158 Pengecatan Cat Nippon Paint Warm Toast 6 days Tue 19/12/23 Tue 26/12/23 157SS
159 PEKERJAAN PENUTUP ATAP 2 days Tue 19/12/23 Wed 20/12/23
160 Penutup Atap 2 days Tue 19/12/23 Wed 20/12/23 152
161 Lisplang 2 days Tue 19/12/23 Wed 20/12/23 160SS
162 PEKERJAAN ENDING PLAFON 7 days Tue 05/12/23 Wed 13/12/23
163 Ending Plafon Gypsum 9 mm 7 days Tue 05/12/23 Wed 13/12/23 149
164 PEKERJAAN FAÇADE 10 days Wed 27/12/23 Tue 09/01/24
165 Pemasangan Kaca Curtain Wall 10 days Wed 27/12/23 Tue 09/01/24 158
166 Pemasangan Mullion 10 days Wed 27/12/23 Tue 09/01/24 165SS
Pengecatan Cat Nippon Paint Swanlike Pengecatan Cat Nippon Paint Warm Toast PEKERJAAN PENUTUP ATAP
Penutup Atap Lisplang
PEKERJAAN ENDING PLAFON Ending Plafon Gypsum 9 mm