PATIMBAN PORT ADDITIONAL HIGHMAST LAMPS PROJECT

INSTALLATION METHOD

HIGHMAST LIGHTING

(2)

1. OVERVIEW OF THE SYSTEM

HIGH MAST LIGHTING SYSTEM

ADDITIONAL LIGHTING SIMULATION 3. OPERATING THE EQUIPMENT

OPERATING THE HIGH MAST POLE

WORKING AREA COVERAGE

PANEL BOX HIGH MAST

LIGHTING INSTALLATION

AIMING HIGH MAST LIGHTING SYSTEM

INSTALLATION METHOD :

2. INTRODUCTION OF THE MAIN EQUIPMENT

HIGH MAST LIGHTING ADDITIONAL

DRAWING POWER SUPPLY

3. ADDITIONAL METHOD 4. TIME LINE

(3)

PATIMBAN PORT ADDITIONAL HIGHMAST LAMPS PROJECT

: High Mast Lighting System Existing

: High Mast Lighting System Additional

LEGEND:

2

set

5

set

5

set

1.1 High Mast Lighting Additional

(4)

GENSET 650KVA, 0.4KV TR G

1250KVA LIGHTING SYSTEM

POWER SUPPLY

LVSB‐AD (LVMDB)

MDB‐L

T.1 MDB‐L

T.2 MDB‐L

T.3

HMP1.1 HMP

5.1 HMP

HMP 2.3

3.1 HMP

5.2 HMP

HMP 2.3

2.1 HMP

3.2 HMP

5.3 HMP

HMP 4.1

1.2 HMP

5.4 HMP

4.2

LP‐ FEG LP‐ OM LVDB

LVDB EF LVDB B CD

LVDB A LVSB‐XR

C A P

N P

P L N

A T S

E P MV‐SWGR

RMU‐AD

1.2 Drawing Power Supply

HMP SPARE MCB

NYM CABLE 3x4mm2 + FLEXIBLE CONDUIT

ADD LIGHTING UNIT

(5)

2.1. HIGH MAST LIGHTING SYSTEM

PATIMBAN PORT ADDITIONAL HIGHMAST LAMPS PROJECT

NYM Cable 3x4mm2 + Flexible Conduit Connecting for Additional Lamps

Spare MCB for each group

(6)

2.2 ADDITIONAL LIGHTING SIMULATION LEGEND:

: New Additional Lamps Directions (12 set) : Existing Wide Lamps

Directions

: Existing Narrow Lamps Directions

2

set

5

set

5

set

(7)

2.2A. ADDITIONAL LIGHTING SIMULATION (BEFORE & AFTER)

PATIMBAN PORT ADDITIONAL HIGHMAST LAMPS PROJECT

BEFORE AFTER

(8)

Ensure to Check all the locking

the cable so it will not entangled

Lower until all support holds the ring safely

Lower the ring carefully while arranging

Install Ring Support

Turn OFF all sub mcb except for motor

Take off socket Clear Surround Area before lowering plug inside HMP

Lower the ring using provided remote

3.1. Operating The High Mass Pole (By Others)

(9)

PATIMBAN PORT ADDITIONAL HIGHMAST LAMPS PROJECT 3.2. Panel Box High Mast

813 Watt 813 Watt 749 Watt

Existing Lamp

Existing Lamp Each Ring Layer 8 set with 3 Layer the total lighting unit 24 set

Spare MCB Slot 12

3 4 5

6 7

Existing MCB 10A is 7 set Maximum for 35 set Lighting Unit

MCB 3P 20A

749 Watt

ADD LIGHTING UNIT 960 Watt ADD LIGHTING UNIT

960 Watt

(10)

3.3. Working Area Coverage

(11)

PATIMBAN PORT ADDITIONAL HIGHMAST LAMPS PROJECT

Additional Lamps can be mounted using scaffolding with wheels approx. 2 layers about 3 meters height

New Type Panasonic Lamps will be mounted using : 1. Mounted Direct Drill & Mounting using Nut & Bolt

15 cm Galvanized

2. NYM 3x4mm2 Cable c/w Flexible Conduit

Following Lighting Simulation Each Pole Each Ring

3.3. Lighting Installation

(12)

Aiming Process still using Scaffolding c/w Wheels & Following from Lighting Simulations Coordinate One By One during Day Light Work Hours

3.4. Aiming High Mast Lighting System

(13)

PATIMBAN PORT ADDITIONAL HIGHMAST LAMPS PROJECT

4. ADDITIONAL METHODE

(14)

5. TIME LINE

TIME SCHEDULE

PEKERJAAN PEMASANGAN LAMPU HIGH MAST PATIMBAN INTERNATIONAL CAR TERMINAL

NO KETERANGAN

DECEMBER 2023

MINGGU 1 MINGGU 2 MINGGU 3 MINGGU 4

4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 Pekerjaan pendahuluan

MINGGU MINGGU MINGGU MINGGU

2 Pemasangan instalasi kabel & lampu 3 Pemasangan instalasi di box panel dan

control

4 Perapihan support out door 5 Test Comm

Keterangan :

Pekerjaan Pendahuluan a. Persiapan Tempat b. Persiapan Alat Kerja c. Perijinan Kerja d. Persiapan Direksi Kit e. Persiapan Mess Pekerja

Pemasangan Instalasi Kabel & Lampu a. Persiapan Zona Area Instalasi b. Off Panel Utama

c. Off Panel Sekunder

d. Peniurunan ring Lampu Pole via Operator e. Persiapan alat bantu kerja (Scaffolding) f. Pembolongan lubang diudukan bracket lamppu g. Pemasangan lampu

h. Penyambungan kabel & flexible conduit

Pemasangan Instalasi Box Panel a. Penambahan/Penggantian MCB 20A Perapihan support out door

a. Penaikkan ring lampu Pole via Operator b. Pembersihan area kerja

Test Commisioning

a. Test nyala dan iluminasi sesuai design dari Pak Agung Principal Panasonic