PLANNING & PREPARATION
Defect list is up-to-date and major defects are transferred to dry dock file Running hours of all engine room machinery are updated and machinery with completed running hours are scheduled for overhauling
Running hours of all deck machinery are updated and machinery with completed running hours are scheduled for overhauling
Running hours of all electrical machinery systems are updated and machinery with completed running hours are scheduled for overhauling All overboard valves are noted and marked for overhauling in dry dock All leaky sea water valves are marked for overhauling
All leaky sea water pipes are noted in dry dock repair list
All temporary repaired pipes/ structures/ plates etc. are noted in dry dock file
Spares for engine room machinery are checked for their inventory Required spares are ordered via company through requisition Special tools for machinery are checked
Missing special tools are noted and reported to the company Precision equipment and measuring tools are noted
Shortcomings in precision and measuring tools are reported to the company Last dry dock report is ready
Last measurement reports of main engine and auxiliary machinery are ready
A Guide To Master Dry Dock Operations
www.marineinsight.com
The sewage disposal requirement is checked for dry dock and reported to the company
Fresh water requirement in dry dock is reported to the company Separate landing report file is prepared for the dry dock
Separate valves open/close checklist file is prepared for dry dock All important machinery manuals are available for the dry dock
All important machinery drawing photocopies are available for the dry dock All ship certificates are checked for the expiry date
CMS requirement for all machinery is understood
Job allocation for ship's crew and dry dock workshop is clarified All lifting tools are checked and prepared
All engine room workshop tools are painted in different colors for easy identification
Enough required chemicals are available for cleaning in the dry dock
Enough dosing chemicals are available for dosing once dry dock is finished Chemical requirement is sent to the company via requisition
Gas bottles, welding rods, brazing etc. are ordered prior to dry dock All electrical meters, lamps etc. are checked for operation
All fire alarms and fire fighting systems are checked for operation
www.marineinsight.com