RENCANA ANGGARAN BIAYA PEKERJAAN KONSTRUKSI BAJA KANOPI SMAK ST LOUIS 2 SURABAYA
NO. ITEM PEKERJAAN VOLUME UNIT HARGA SATUAN
(Rupiah)
JUMLAH HARGA (Rupiah) I Persiapan
1 Bouplank/uitzet 1 ls
2 Gudang / direksi keed 1 ls
3 pagar seng pengaman 1 ls
II KONSTRUKSI BAJA 1 KUDA KUDA
Pipa 3" x 2,7 mm 2133 KG
Pipa 1,5" x 1,5mm 597,3 KG
Plat join 10 mm 177,8 KG
Tali angin besi 16mm 257,5 KG
2 KOLOM KG
WF 450x200x9x14 10250 KG
Plat plendes 20mm 662 KG
Plat rib 8mm 486 KG
Angkur HILTI HAS-E M20 270 BH
3 REGEL KG
Wf 200x100 1364,2 KG
Plat joint ( 8x200x150) 66 KG
4 GORDING KG
CNP 120 x 45 x 20 x2,3 2464,8 KG
Pangkon plat 6mm 74,2 KG
Trekstang 12 mm 297,6 KG
5 ATAP
Spandek 0,4 (KR 5) lengkung ex Utomo 802,5 M2 6 LISPLANK
Holo 4x4x1,2 50 M2
Holo 4x4x1 26 M
Penutup spandek 0,4 (KR 5) 112 M2
7 TALANG GALVALUM
Plat strip dan galvalum 0,4 64,6 M
8 PIPA PVC
Pipa 4' type D 1 LS
9 MUR DAN BAUT
M 16 x50 220 BJ
M 12 x 30 450 BJ
Jarum keras 12mm 14 BJ
10 Zincromate 1 LS
11 Mobilisasi 1 LS
II BETON DAN PONDASI
1 Strous 30cm x 4m 6,2 M3
2 Pilecap 90x90 9,4 M3
3 Kolom beton 9,72 M3
4 Sloof 17,4 M3
III LAIN2
1 Pembersihan 1 LS
TOTAL 0