• Tidak ada hasil yang ditemukan

Power System Planning

N/A
N/A
Protected

Academic year: 2024

Membagikan "Power System Planning"

Copied!
15
0
0

Teks penuh

(1)

Power System Planning

Introduction

Chapter 1

By

Introduction

Turaj Amraee

Fall 2012

K.N.Toosi University of Technology

(2)

Outline Outline

™

™

11-- IntroductionIntroduction

™

™

22-- Power System ElementsPower System Elements

™

™

™

™

33-- Power System StructurePower System Structure

™

™

44-- Power System PlanningPower System Planning

™

™

55 PP SS S dS d TT S lS l

™

™

55-- Power System Studies, Power System Studies, Time Time SclaesSclaes

™

™

66-- Planning TypesPlanning Types

™

™

77 PlPl i H ii H i

™

™

77-- Planning HorizonsPlanning Horizons

™

™

88-- Planning Planning ProcessProcess

™

™

99 Planning ToolsPlanning Tools

™

™

99-- Planning ToolsPlanning Tools
(3)

Introduction- Challenges g

‰

High plant margins and extensive control facilities due to

Limited Sources - Growing Demand

supply follows demand philosophy .

‰

Environmental concerns: global warming, greenhouse effect, acid rain, related air-borne pollution .

‰

High fossil fuel cost and nuclear option into question

o

Three Mile Island (28 March 1979)

o

Chernobyl (26 April 1986

)
(4)

Power System Elements y

A typical power system is comprised of enormous A typical power system is comprised of enormous

number of elements. The main elements are

™

Generation facilities

™

Generation facilities

™

Transmission facilities

™

– Substations

™

Substations

™

– Network (lines, cables)

™

Loads

™

Loads

(5)

Power System Structure y

™Transmission (for example, 230 kV and higher)

™Sub transmission (for example 63 132 kV

™Low Voltage: < 1KV

™M di V lt > 1KV 20 KV 11 KV 33KV

™Sub-transmission (for example, 63, 132 kV

™Distribution (for example, 20 kV and 400 V).

™Medium Voltage: > 1KV: 20 KV, 11 KV, 33KV

™High Voltage: 63KV, 132KV

™Extra High Voltage: 230KV, 400KV

™Ultra High Voltage: 765KV

(6)

Power System Planning y g

™

Power system operation:

Focuses on running the current situation, ED, UC g , ,

™

Power System Planning:

Focuses on the actions required for the future

Focuses on the actions required for the future.

(7)

Power System Planning y g

Power system planning is a process in which the aim is to decide on new as well as upgrading existing system elements, to adequately satisfy the loads for a foreseen future.

…

Where to allocate

…

When to install

…

What to select, element specifications

(8)

Power System Studies y

Economic Aspects

Technical Aspects

(9)

Planning Types g yp

Planning

Static

Planning Dynamic

Planning

Planning Planning

focuses on

planning for a single stage

focuses on

planning for all stage

Static Planning leads to impractical results

the solutions for a year cannot be independent from the preceding years.y p p g y Semistatic, semi-dynamic, quasi-static or quasi-dynamic

(10)

Planning Horizons g

Planning

Short

Term Long

Term

Term Term

1-3 years 3-10 years

LF GEP NEP VEP

LF

• Load Forecasting

GEP

• Generation Expansion Planning

NEP

• Network Expansion Planning

VEP

• Volt-Var Expansion Planning

(11)

Load Forecasting g

Sh T f i di di i h

LF is the first crucial step for any planning study

™

Short Term: for operation studies predicting the load for each hour of the coming week

L T f l i di l k l d

™

Long Term: for planning studies, annual peak loads

for next 10 years

(12)

Generation Expansion Planning p g

GEP : the next step is to determine the generation requirements to satisfy the load.

A i l l i P Pd P

™What types of power plants to be installed (thermal gas turbine nuclear etc ) An simple solution Pg=Pd+Preserve

™What types of power plants to be installed (thermal, gas turbine, nuclear,etc.)

™ Where to be installed (distributed among 5 specific buses, 10 specific buses, etc.)

™What capacities to be constructed (5 *1000 MW, or 2 * 1000 MW and 6 * 500 MW, …)

™When and how to be installed

(13)

Substation Expansion Planning p g

SEP

is the next step to determine the substation requirements, both, in terms of

™

Expanding the existing ones,

™

Installing some new ones

™

Installing some new ones.

9

Substation Type

9

Substation Location

(14)

Network Expansion Planning p g

NEP is the next step to determine the network NEP is the next step to determine the network (transmission lines, cables, etc.) specifications

As inputs to the NEP problem, GEP and SEP results are assumed to be known.

NEP is for 63kv and higher voltage level.

Reactive Power Planning

NEP is normally based on using Direct Current Load Flow (DCLF).

Upon running GEP, SEP and NEP, the network topology is determinedp g , , p gy

™Where to install these devices?

™What capacities do we have to employ?

™Wh t t d h t ?

™What types do we have to use?

(15)

Planning Tools and Programs g g

Matpower

• PF/OPF WASP

• GEP GAMS

• Optimization PF/OPF

• Editable *.m file

GEP

Optimization

Referensi

Dokumen terkait

Figure 2 and 3 show the total active power outputs of the hydroelectric power system, the total active power outputs of the thermoelectric generators, and load changes over the

Based on the discussion of the Backpropagation Artificial Neural Network (ANN) algorithm applied to forecasting the power transformer peak load in Bumiayu

Based on the highly controllable power generation and accurate load forecast, the system is operated by unit commitment UC and economic dispatch ED with N-1 contingency [3], which

ENERGY MANAGEMENT The term energy management leads to many exercises in practice to enhance system efficiency such as: 4.1 Load Side Management: It is very necessary to know the

Comparison of the dynamic response of frequency deviation with and without integral control for a step change in the load for hydro turbine with and without compensation Figure 3..

Figure 16 – Voltage and current of the PV with variable irradiance Figure 17 – Power injected to the load at node 3 including ECS Figure 18 – Voltage at node 3 after using ECS