• Tidak ada hasil yang ditemukan

Chapter 2...........................................................................................-......"---"----"-- 2

2.2 Extension of service life for ageing platforms

In Malaysia, about 51% of jacket platforms have exceeded 25 years of operation life.

Most of these jacket platforms were designed for 20 to 25 years service life. Table 2.1 shows the age distribution for jacket platforms in Malaysia. Due to strong production and conservative estimation of reservoir capacity, many of these platforms are still producing oil and gas beyond their intended service life. It is a challenge for the engineer to maintain and operate a huge fleet of ageing platforms. Replacement of the structure will not be a feasible option by management because of financial limitations. Many operators opt to extend the service life of their existing platforms.

The life extension of jacket platforms however depends on many requirements such

as:

I. Component strength for each element must satisfy unity check in static/linear analysis.

II. The current capability of the jacket platform to resist environmental load

must be sufficient.

III. Integrity of the structure must be intact.

IV. Feasibility of the reservoir and production of the well must be above the minimum financial requirement for profitable operation.

V. The structure must pass the minimum reliability requirement for safe operation.

VI. Air gap of superstructure must be more than 1.5 m.

VII. Re-assessment of ageing structure must give an RSR value greater than 1 with respect to 100-year wave, wind and current conditions.

VIII. Equipment, pipeline, piping and valve on the superstmcture must be certified

as fit for service in accordance with API 579 Fitness for Service.

After all the above requirements are addressed properly, the decision to extend the structure service life can be made. For existing jacket platforms, it is necessary to perform more detailed analysis, new inspections, tests, and measurements rather than redesigning and increasing the steel weight and reconfiguring the structural parts with new parts or structures. In an overview, re-assessment for ageing platform is entirely different from structural design process before installation. Kallaby (1994), Moan and Vardal (2001) discussed the differences between design criteria and re-assessment

criteria as tabulated in Table 2.2.

Table 2.1. Age distribution for jacket platforms in Malaysia

Less than 10 years

Between 10 to

20 years

20 to 25

years

25 to 30 years

More than 30 years

Peninsular

Malaysia

16(42%) 5 (13%) 9 (24%) 7(18%) 1 (3%)

Sabah 5(16%) 1 (3%) 7 (23%) 6(19%) 12 (39%)

Sarawak 3 (3%) 30(28%) 9 (8%) 20(19%) 44 (42%)

Table 2.2. Differences between design and re-assessment criteria Design criteria Re-assessment criteria

Environment Forecast from existing data

collection.

Same criteria as for design but include

recent data collection and use of current

state of the art review, experience from adjacent field and additional data from actual field sea states. Also includes

possibility for Tsunami and typhoon.

Loading Possibly conservative

evaluation from proposed use of

structure.

Use of recent survey for marine growth, appurtenances, modifications, topside weight control and wind areas.

Foundation Forecast from site investigation and laboratory testing of soil.

Includes subsidence information, maintenance, and experience from adjacent field, post-drive analysis, scour survey and maintenance.

Structural model

Topology and dimensions may be changed. No service inspection available.

Conservative modeling using global percentages to cover not- finalized details and simple geometric assumptions.

Structural configurations are fixed and known. In-service inspections maybe applied. Actual characteristic strength of

steel based on actual material certificates

may be used. Structural performance may have been measured and used to update structural analysis.

Stress

analysis

Strict compliance with code of practice and regulatory

documents.

Removing of unnecessary conservatism, redundancy study to determine ultimate strength of structure and foundation, sensitivity studies on various parameters to improve confidence level.

Results Structare has members and

joints with acceptable utilization (UC).

Structure may have some stress up to yield, but some assessment standards allow for some yielding if the structure has proven strength and redundancy.

Figure 2.1 shows the flow chart in accordance with ISO 19902 (2004) of the procedure for assessing ageing platform's capability for life extension and fitness for purpose. Level 1 is a linear analysis and component check. Level 2 is also linear analysis with component checks but with refined actions and resistances. Level 3 includes linear elastic redundancy checks. Level 4 is a non-linear analysis on system level including component checks as an integrated part of the non-linear system analysis. The final level 5 is a check by using structural reliability analysis.

Assemble structure data and history

Identify exposure level

Isassessmentiniti ator tri ggered?

Yes

Review condition of structure

Review action

Compare with similar structure

Implement prevention and mitigation measures

Implement prevention

"and mitigation measures

Implement prevention and mitigation measures

Not acceptable Determine actions

*i Level 1 assessment

Refine action and resistance

Level 2 assessment

Fail

Level 3 assessment

Fail

No

Acceptabk

Pass

Pass

Pass

Pass

Level 4 assessment ) ».

Fail

Level 5 assessment

Fail

Structure not fitfor purpose

Pass

Assessment not necessary

Assessment not necessary

Structure fit for purpose

Structure fit for purpose

Structure fit for purpose

Structure fit for purpose

Structure fit

for purpose

Figure 2.1. Procedure for ageing structure assessment

2.3 Codes and standards for re-assessment

In engineering design and assessment, the application of codes and standards as the best guidelines and practices, shall be used in conducting structural analysis of ageing platforms. In assessing reliability for any ageing stmcture, the engineer may refer to various codes and standards, depending on the region of applicability of each standard. For all the analyses used in this study, the relevant codes and standards referred to are given below:

I. API RP 2A - American Petroleum Institute "Recommended Practice for

Planning, Designing and Construction of Fixed Offshore Platform" for both WSD and LRFD, latest editions.

II. AISC - American Institution of Steel Constmction "Specification for Structural Steel Building", latest edition.

III. AWS Dl.l - American Welding Society "Structural Welding Code", latest

edition

IV. BSI PD 6493 - British Standard Institute section PD6493 "Guidance on

Some Methods for Derivation of Acceptance Level for Defects in Fusion Welded Joints", latest edition.

V. PTS - PETRONAS Technical Standard, latest edition

VI. DIM - Design Instruction Manual "Section 1-1, Common Requirements", ESSO Production Malaysia Inc, latest edition.

For Malaysia's operational regions, the substructures of existing platforms were

designed in accordance with API 20th edition or earlier editions of the same API

standards. This makes all the fixed jacket platforms in Malaysia following API RP 2A. Since Malaysia does not have its own regulatory codes and standards for jacket platforms, API RP 2A became widely accepted. API RP 2A along with company/organization in-house technical standard is used in the design level analysis and ultimate strength analysis for fixed jacket platforms. PTS is mainly for PETRONAS usage and DIM is for ESSO internal usage. These codes however do not

differmuch from API, as both are derived from API RP 2A WSD and AISC forjacket

platforms.

2.4 Risk definition for jacket platform

In assessing the risk for jacket platforms, risk based inspection (RBI) concept is a

well-accepted approach in the industry. PRSS RBI Manual (2000) states that RBI concept is a method used to assess the risk of platform structures and their components in relation to a level that is acceptable, where inspection and repair used to ensure the level of risk are well below the acceptance limit. Combined with Structural Integrity Management System (SIMS) program for Malaysia's region that was launched in 2008, the estimation of risk for jacket platforms has become more accurate and accepted by oil and gas operators. Risk is defined as the product of probability of failure (POF) and consequence of failure (COF).

Probability of failure (POF) is an estimated value based on degradation mechanisms operating in the component within the global structural system. The degradation mechanisms such as scour, damaged member, missing member, fatigue, corrosion and fire can reduce the strength and stiffness of the global stmctural system over time. POF is calculated as the area overlap in the distributions of the degradation rate. Each degradation mechanism is based on uncertainties of the resistance for each component to failure. The degradation rate for stmctural deterioration is represented on the left side in probability density function. The resistance of the component to failure is represented by the right side in probability density function. This overlap of resistance and degradation is illustrated in the Figure 2.2.

ijJLAV^TTTYMW^j

I '• Bz£i aihtionpclf

\ Resistance s^

^Probability offailure

Figure 2.2. POF in resistance and degradation relationship

Consequence of failure (COF) can be derived from the combination of consequences when the platform experiences total failure or collapse. Generally the COF can be divided into three categories as presented by Goh (1999):

I. Economy - Consequence to economy when the jacket platform collapses.

Cost of replacement, production deferment, stmctural savage cost, insurance and compensation paid are Included in this category.

II. Environment - Evaluation of environmental consequence is a complex issue and involves organizational reputation, short term and long term effects in global and local perspective in oil and gas industry.

III. Safety - It is usually estimated for failures that lead to stmctural collapse of platforms that include loss of lives of personnel on board.

Table 2.3 shows the overall consequence of platforms in Malaysia in accordance with PRSS RBI Manual (2000). Depending on the company or organization's definition of POF and COF, the definition can vary. A complete definition of POF and COF is

mandatory before any risk calculation or estimation can be done. Table 2.3 shows ttie

definition of COF for Malaysian regions according to PETRONAS.

Table 2.3. COF definition according to PETRONAS (1999) Cr.F Ranhmg Qua! it CiVf Cuantitatwe

(Abstract Value)

Dest-Jiptiun

- -'. "" j '. : : t - •• icr

very high cost.

D High US$ 75 Million -

US$ 100 Million

The consequence of failure represents high cost.

C Medium US5 45Mil!ion - US$ 75 Million

The consequence of failure represents

medium cost.

B Low US$ 6 Million -

US$45 Million

The consequence of failure represents low

cost.

A Very Low < US S6 Million The consequence of failure represents very low cost.

Risk is usually presented in the form of risk matrix. Risk matrix is presented as 3x3 or 3x5 or 5x5 matrixes. Figure 2.3 shows a typical 5x5 matrix used in SIMS.

B

Figure 2.3. 5x5 risk matrix

The risk zones can be divided into five zones according to PETRONAS RBI Manual (2000):

I. Very high exposure (Red Zone) II. High risk exposure (Orange Zone) III. Medium risk exposure (Brown Zone) IV. Low risk exposure (Yellow Zone)

V. Very low risk exposure (Green Zone)

All fixed jacket platforms in Malaysia are categorized in this manner. The decision to replace, strengthen, inspect and/or operate depends on the risk status of the particular jacket platform. The categorization is dependent on POF rather than COF since COF is defined by corporate and is financially driven. Engineers can reduce the structural POF by increasing the structural resistance. This will reduce the overlap area of resistance and degradation in the probability density function shown in Figure

2.2.

One popular technique to assess the safety performance of ageing jacket platform is by taking the ultimate limit strength instead of the yield strength and using plastic theory and non-linear analysis. By this method, the platform can resist more loads beyond the elastic limit and meet the global minimum requirement prescribed by the

codes and standards.

2.5 Reliability assessment in Malaysia

According to Guideline for Offshore Stmctural Reliability Analysis issued by DNV (1995), level of reliability is not a property of the stmcture. Unlike linear analysis, where it calculates the ratio between applied stress to allowable stress, reliability is heavily dependent on the information about the uncertainty of a parameter that will change through time.In reliability calculations, the engineers and analysts often refer to certain reference period, usually one year or the design life. In the re-assessment of ageing platform, it is recommended to use one year reference period in all cases.

Reference period, or called return period in some literature, is inversely proportional

to the global stmctural probability of failure (Pf) given by expression below:

T= j-f (2.0)

API RP 2A (2000) and PETRONAS Carigali Inspection Maintenance Guideline (CIMG 2010) clearly define the level of reliability application in operation. This definition however is unique according to the organization/company and maybe different worldwide. Three categorization of reliability known as Level I, II and III are defined to ensure safe operation in jacket platforms.Level-I provides a practical design method where suitable safety margins are provided usually on a stmctural element basis by specifying a number of partial safety factors related to some predefined characteristic values of the basic variables in the system.

In the strength model, these values usually correspond with the nominal values specified in the design such as minimum yield. No precise reliability calculation involving probability of failures and consequence of failures are undertaken and the

level of risk for different platforms, are essentially unknown. Design methods involving a number of partial safety factors are practically better compared with level II and III approaches. In day-to-day practice, level-I reliability method is good enough for the screening and overview of stmctural element safety performance.

Level-II method utilizes the properties of load and strength distributions for

component and stmctural system in terms of a reliability safety index. This

corresponds to an estimated probability of failure or reliability for each failure mode

or limits state during the life of that platform. Appropriate partial safety factors are then derived for the particular design condition. These safety checks are made only at selective points on the failure boundary as defined by the appropriate limit state rather than as a continuous process as level III. This method will not make any attempt to find the region of basic variable or state space which has the highest probability of failure density. This is important for the level II methods and provides basis for calculating partial safety factors for level III. In practice, level II reliability method is used when there is deep interest toknow the safety status of a particular structure in a precise and accurate approach compared to level I.

Level III provides the most accurate and exact probabilistic analysis for the whole stmctural system involving the convolution integral. This method is theoretically straightforward and accurate, but in practice, difficult to formulate and to solve. In addition, it cannot directly be used in design process, for specified reliability level.

This is the only approach which can satisfactorily incorporate all the modes of failure when estimating the total reliability. Clearly, these methods are not suitable for normal application in design purpose.

Level III techniques can be used for checking the validity and accuracy of the simplified level II method by analysis of specified stmctural systems. There are also numbers of reliability analysis techniques available according to different fields in engineering industry. In jacket platforms, the main reliability techniques used to assess the safety performances are:

I. Quantitative Risk Analysis (QRA)

This method is concerned with the estimation and calculation of overall risk

to ensure safe operation and minimize risk to human, environment and

economy.

II. Stmctural Reliability Analysis (SRA)

This is the most common reliability technique that addresses the stmctural probability and consequence of failure, by including estimation of reliability calculation to get reliability index or fj index. It consists of several steps and procedures with mathematical models.

III. Organizational Reliability Analysis (ORA)

In this approach, the focus of methodology is on the organizational procedures. It calculates and determines how a particular strategy and procedure gives impact to the safety, reliability of the system and quality of the products. Swain and Guttman (1983) include ORA into the field of Human Reliability (HR) engineering.

IV. Simplified Stmctural Reliability Analysis (SSRA)

This method is by far the quickest way to calculate reliability index using pre-determined value for covariance and biases from selected SRA calculations for specific collections of stmcture within same region. SSRA is based on SRA of Further Stmctural Integrity Assessment (FSIA) conducted by Petronas Research and Scientific Services (PRSS) and Det Norske Veritas (DNV) in 1997 for thirteen jacket platforms in Baram and Balingian field

Sarawak.

For this study, reliability (P) index is calculated using SSRA methodology since it is the quickest way and the most widely used in Malaysia for calculating P index for fixed jacket platforms. For a very load-sensitive and unique platform (5 legged, semisubmersible, monopod), SSRA usage is still limited. SRA needs to be performed for such platform to calculate its p index. Table 2.4 shows the differences between SSRA and SRA methodology (for Malaysia).

Table 2.4. Differences between SSRA and SRA

SRA SSRA

Time for analysis 8-12 months 3-6 months

Cost (minimum) RM 1.5 Millions RM150K

Local expertise Limited Few

Complexity High Medium

Accuracy for predicting reliability (P) index

High Medium

Basis for calculating Individual limit state function Depends on the pre reliability(P) index per structure determined COV and biases

from SRA for the particular

structure within the same

operation area

Identification of stochastic Performed in this analysis Performed in this analysis variables and parameters in

limit state functions

Specification of probability Performed in this analysis Based on SRA for particular

distributions for each structure within the same

variables and parameters for operation area

limit state functions

Interface with QRA and Possible Limited interface

ORA

Analysis pre-requisite Non-linear push over and Finite Element Analysis

Non-linear push over

Engineer's level required High (Custodian & Principal Medium (Staff & Senior Engineer level) Engineer level)

Assess whether the estimated Modification of requirement No modification for

reliability is sufficient and and limit state function is requirement and limit state able to modify the calculation possible function

concept necessary.

Covariance and biases Unique and individually Based on SRA pre

calculated for each members determined value for and failure mechanisms particular structure within the

same operation area

Software requirement Highly probabilistic such as Microsoft Excel with SSRA ProbCalc and ATENA formula embedded

Probability simulation model Performed in this analysis Not available

Monte Carlo Simulation Performed in this analysis Not available

Bayesian Probability Performed in this analysis Not available

Frequency Probability Performed in this analysis Performed in this analysis for Inspection Reference Plan (IRP) in Risk Based Inspection approach

For routine operation, due to cost restraint by operation management, SRA is not as practical as SSRA. The low cost and short period of time for execution made SSRA a popular choice by organization to assess safety performance of their assets. Figure 2.4 shows the procedure in performing SSRA calculation for reliability (P) index.

Reserve strength ratio

Biases for resistance

Non-linear push over analysis

Identified mechanism of failure

Calculation /solver

Maximum base shear resisted before total collapsed

'

Biases for dead and environmental load

probability period

1 i.

Cava ri a nee f or tota 1 environmental load

'r

Check against minimum requirement by code and standards or company requirement Calculation of annual

reliability index 1

Covariance for dead

load Ai

T

* Operating decision:

1} Operating as usual 2} Operation limitation 3) Inspection reference Cova ri a nee for tota 1

resistance

Calculation of mean strength to mean load ratio

pla 4} Str

m c n

engthening

>dification ancrepar

Figure 2.4. SSRA procedure

Dokumen terkait