Trimester, Year: T3, Y3 Study week no.: Week 3 Student Name & ID: Laan Wei Yi 19ACB01708

Supervisor: Mr.Su Lee Seng

Project Title: Development of Decentralised Apps (DApps) using Blockchain Technology to Improve Insurance Process in Malaysia

1. WORK DONE: Complete combination of previous report to current report.

2. WORK TO BE DONE: Content improvement for report.

3. PROBLEMS ENCOUNTERED: No issue.

4. SELF EVALUATION OF THE PROGRESS: Project is on scheduled.

_________________________

_________________________

Supervisor’s signature Student’s signature

FINAL YEAR PROJECT WEEKLY REPORT

(Project II)

Trimester, Year: T3, Y3 Study week no.: Week 4 Student Name & ID: Laan Wei Yi 19ACB01708

Supervisor: Mr.Su Lee Seng

Project Title: Development of Decentralised Apps (DApps) using Blockchain Technology to Improve Insurance Process in Malaysia

1. WORK DONE: Complete content enhancement in the report.

2. WORK TO BE DONE: Draw system diagram and complete new added section for FYP2 report.

3. PROBLEMS ENCOUNTERED: No issue

4. SELF EVALUATION OF THE PROGRESS: Project is on scheduled.

_________________________ _________________________

Supervisor’s signature Student’s signature

FINAL YEAR PROJECT WEEKLY REPORT

(Project II)

Trimester, Year: T3, Y3 Study week no.: Week 5 Student Name & ID: Laan Wei Yi 19ACB01708

Supervisor: Mr.Su Lee Seng

Project Title: Development of Decentralised Apps (DApps) using Blockchain Technology to Improve Insurance Process in Malaysia

1. WORK DONE: Complete all drawings and elaboration.

2. WORK TO BE DONE: Continue on new report section.

3. PROBLEMS ENCOUNTERED: New section is out of expectation, need to spend extra time than planning to complete.

4. SELF EVALUATION OF THE PROGRESS: Need to be more focus on new section.

_________________________ _________________________

Supervisor’s signature Student’s signature

FINAL YEAR PROJECT WEEKLY REPORT

(Project II)

Trimester, Year: T3, Y3 Study week no.: Week 6 Student Name & ID: Laan Wei Yi 19ACB01708

Supervisor: Mr.Su Lee Seng

Project Title: Development of Decentralised Apps (DApps) using Blockchain Technology to Improve Insurance Process in Malaysia

1. WORK DONE: Completed new section and draft of survey.

2. WORK TO BE DONE: Distribute survey and start system development.

3. PROBLEMS ENCOUNTERED: No issue

4. SELF EVALUATION OF THE PROGRESS: Project is on scheduled.

_________________________ _________________________

Supervisor’s signature Student’s signature

FINAL YEAR PROJECT WEEKLY REPORT

(Project II)

Trimester, Year: T3, Y3 Study week no.: Week 7 Student Name & ID: Laan Wei Yi 19ACB01708

Supervisor: Mr.Su Lee Seng

Project Title: Development of Decentralised Apps (DApps) using Blockchain Technology to Improve Insurance Process in Malaysia

1. WORK DONE: Developed View Policy features.

2. WORK TO BE DONE: Development of Request Claim features.

3. PROBLEMS ENCOUNTERED: No issue.

4. SELF EVALUATION OF THE PROGRESS: Project is on scheduled.

_________________________ _________________________

Supervisor’s signature Student’s signature

FINAL YEAR PROJECT WEEKLY REPORT

(Project II)

Trimester, Year: T3, Y3 Study week no.: Week 8 Student Name & ID: Laan Wei Yi 19ACB01708

Supervisor: Mr.Su Lee Seng

Project Title: Development of Decentralised Apps (DApps) using Blockchain Technology to Improve Insurance Process in Malaysia

1. WORK DONE: Undergoing development of Request Claim features.

2. WORK TO BE DONE: Complete development of request claim and conclude survey results.

3. PROBLEMS ENCOUNTERED: No issue.

4. SELF EVALUATION OF THE PROGRESS: Project is on scheduled.

_________________________ _________________________

Supervisor’s signature Student’s signature

FINAL YEAR PROJECT WEEKLY REPORT

(Project II)

Trimester, Year: T3, Y3 Study week no.: Week 9 Student Name & ID: Laan Wei Yi 19ACB01708

Supervisor: Mr.Su Lee Seng

Project Title: Development of Decentralised Apps (DApps) using Blockchain Technology to Improve Insurance Process in Malaysia

1. WORK DONE: Report: Collect and evaluate survey results. System: Request Claim module complete.

2. WORK TO BE DONE: Proceed with Verify Claim module.

3. PROBLEMS ENCOUNTERED: No issue.

4. SELF EVALUATION OF THE PROGRESS: Project is on scheduled.

_________________________ _________________________

Supervisor’s signature Student’s signature

FINAL YEAR PROJECT WEEKLY REPORT

(Project II)

Trimester, Year: T3, Y3 Study week no.: Week 10 Student Name & ID: Laan Wei Yi 19ACB01708

Supervisor: Mr.Su Lee Seng

Project Title: Development of Decentralised Apps (DApps) using Blockchain Technology to Improve Insurance Process in Malaysia

1. WORK DONE: 50% Verfiy Claim module.

2. WORK TO BE DONE: Complete development of Verfiy Claim module and proceed with last module Claim Approval module.

3. PROBLEMS ENCOUNTERED: No issue

4. SELF EVALUATION OF THE PROGRESS: Project is on scheduled.

_________________________ _________________________

Supervisor’s signature Student’s signature

FINAL YEAR PROJECT WEEKLY REPORT

(Project II)

Trimester, Year: T3, Y3 Study week no.: Week 11 Student Name & ID: Laan Wei Yi 19ACB01708

Supervisor: Mr.Su Lee Seng

Project Title: Development of Decentralised Apps (DApps) using Blockchain Technology to Improve Insurance Process in Malaysia

1. WORK DONE: Complete report writing and Claim Approval module.

2. WORK TO BE DONE: Test on bugs for current works and FYP submission.

3. PROBLEMS ENCOUNTERED: No issue.

4. SELF EVALUATION OF THE PROGRESS: Project is on scheduled.

_________________________ _________________________

Supervisor’s signature Student’s signature

FINAL YEAR PROJECT WEEKLY REPORT

(Project II)

Trimester, Year: T3, Y3 Study week no.: Week 12 Student Name & ID: Laan Wei Yi 19ACB01708

Supervisor: Mr.Su Lee Seng

Project Title: Development of Decentralised Apps (DApps) using Blockchain Technology to Improve Insurance Process in Malaysia

1. WORK DONE: Finalise system and submit report.

2. WORK TO BE DONE: Prepare presentation.

3. PROBLEMS ENCOUNTERED: No issue

4. SELF EVALUATION OF THE PROGRESS: Project is on scheduled.