• Tidak ada hasil yang ditemukan

university of the philippines los baños

N/A
N/A
Protected

Academic year: 2023

Membagikan "university of the philippines los baños"

Copied!
6
0
0

Teks penuh

(1)

i

UNIVERSITY OF THE PHILIPPINES LOS BAÑOS College of Engineering and Agro-Industrial Technology

Department of Civil Engineering

EVALUATING THE EFFECTS OF VALUE ENGINEERING AS APPLIED TO THE COLUMN DESIGN STRENGTH AT

AVIDA TOWERS MAKATI WEST PROJECT

KATRINA SALORIO LAMERY

BACHELOR OF SCIENCE IN CIVIL ENGINEERING

APRIL 2010

(2)

EVALUATING THE EFFECTS OF VALUE ENGINEERING AS APPLIED TO THE COLUMN DESIGN STRENGTH AT

AVIDA TOWERS MAKATI WEST PROJECT

KATRINA SALORIO LAMERY 2004 – 39120

SUBMITTED TO THE FACULTY OF THE

COLLEGE OF ENGINEERING AND AGRO-INDUSTRIAL TECHNOLOGY UNIVERSITY OF THE PHILIPPINES LOS BAÑOS

IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE

DEGREE OF

BACHELOR OF SCIENCE IN CIVIL ENGINEERING

APRIL 2010

(3)

vi TABLE OF CONTENTS

Title Page i

Acceptance Sheet ii

About the Author iii

Acknowledgements iv

Table of Contents vi

List of Tables viii

List of Figures ix

1. INTRODUCTION 1.1 Background of the Study 1

1.2 Significance of the Study 2

1.3 Objectives of the Study 3

1.4 Scope and Limitations 3

1.5 Date and Place of the Study 4

2. REVIEW OF RELATED LITERATURE 2.1 Value Engineering 5

2.1.1 Goals 5

2.1.2 Proper Timing 6

2.1.3 Job Plan 7

2.1.3.1 Pre-workshop Activities 8

2.1.3.2 Workshop Activities 8

2.1.3.2.1 Information Phase 9

2.1.3.2.2 Functional Analysis Phase 9

2.1.3.2.3 Creative Phase 9

2.1.3.2.4 Evaluation Phase 9

2.1.3.2.5 Development Phase 10

2.1.3.2.6 Presentation Phase 10

2.1.3.3 Post – Workshop Activities 10

2.2 Applications in Construction 11

3. STUDY METHODOLOGY 12

4. OBSERVATIONS 4.1 Concrete Strength 13

4.2 Working Methodologies 15

4.2.1 Placement of Formworks and Reinforcement Bars 15

4.2.1.1 Slabs 15

4.2.1.2 Columns 17

4.2.1.3 Wall Panels 19

4.2.2 Placement of Concrete 21

4.2.2.1 Second to Fifteenth Floor 22

4.2.2.2 Sixteenth Floor to Roof Deck 24

4.2.2.3 Pre-cast Wall Panels 25

4.3 Columns and Shear Walls 26

4.4 Change Order 30

(4)

5. RESULTS AND DISCUSSION

5.1 Leading Factors 31

5.2 Resulting Factors 32

5.2.1 Costs 32

5.2.1.1 Deductive Costs 32

5.2.1.1.1 Column Formworks 32

5.2.1.1.2 Rebar Works 37

5.2.1.1.3 Labor Cost 40

5.2.1.2 Additive Costs 48

5.2.1.2.1 Ready-mix Concrete 48

5.2.1.2.2 Additional Formworks at joint areas 49

5.2.2 Labor Productivity 51

5.3 Assessment of Effectiveness 54

6. CONCLUSIONS 61

7. RECOMMENDATIONS 63

BIBLIOGRAPHY 64

APPENDICES Appendix A. Change Order for Column Concrete Strength Revision 65

Appendix B. Change Order Requesting for Additional Formworks 66

Appendix C-1. Column and Shear Wall Designation at Tower 1 67

Appendix C-2. Column and Shear Wall Designation at Tower 2 68

Appendix D-1. Column and Shear Wall Formworks at Tower 1 69

Appendix D-2. Column and Shear Wall Formworks at Tower 2 73

Appendix E-1. Concrete Volume for Columns and Shear Walls at Tower 1 77

Appendix E-2. Concrete Volume for Columns and Shear Walls at Tower 2 81

Appendix F. Additional Formworks for Joint Areas at Towers 1 and 2 85

Appendix G-1. Detailed Breakdown of Over-all Costs for Tower 1 89

Appendix G-2. Detailed Breakdown of Over-all Costs for Tower 2 92

(5)

viii LIST OF TABLES

Table No. Title Page No.

Table 4-1. Height of Columns and Shear Walls per Floor Level 27 Table 4-2. Column and Shear Wall Quantities per Floor Level 28 Table 4-3. Actual Volume of Concrete Poured from Foundation

up to Fifteenth Floor 29

Table 4-4. Actual Volume of Concrete Poured from Sixteenth Floor

up to Roof Deck 29

Table 5-1. Total Area of Formworks for Column C1 at Tower 1 34 Table 5-2. Total Area of Formworks for Column C1 at Tower 2 34 Table 5-3. Summary of Total Area of Formworks for All Columns

and Shear Walls at Tower 1 35

Table 5-4. Summary of Total Area of Formworks for All Columns

and Shear Walls at Tower 2 36

Table 5-5. Rebar Quantities for Tower 1 38

Table 5-6. Rebar Quantities for Tower 2 39

Table 5-7. Total Concrete Volume for Column C1 at Tower 1 43 Table 5-8. Total Concrete Volume for Column C1 at Tower 2 44 Table 5-9. Summary of Total Concrete Volume for All Columns

and Shear Walls at Tower 1 45

Table 5-10. Summary of Total Concrete Volume for All Columns

and Shear Walls at Tower 2 46

Table 5-11. Summary of Deducted Labor Costs 47

Table 5-12. Additional Area of Formworks for Joint Areas 50 Table 5-13. Summary of Costs Incurred for Tower 1 56

Table 5-14. Summary of Costs Incurred for Tower 2 57

(6)

LIST OF FIGURES

Table No. Title Page No.

Figure 1-1. Avida Towers Makati West 1

Figure 1-2. Location Map of Avida Towers Makati West 4 Figure 2-1. Timing of Value Engineering Opportunities 6

Figure 2-2. Modern Value Engineering Process 8

Figure 4-1. Result of Slump Testing Done on Concrete 14 Figure 4-2. Concrete Sample Homogenization of Temperature

Inside the Curing Tank 14

Figure 4-3. Installation of Formworks for Slabs 16

Figure 4-4. Installation of Bottom Bars on Slabs 16

Figure 4-5. Installation of Ties by Fitting Closed Hoops of 16 mmØ Rebars 17 Figure 4-6. Location of Columns Laid Out by Use of Form Shoe

Adjusting by 40 mm for Concrete Cover 18

Figure 4-7. Inspection of Column Formworks by Measuring from

A Given Gridline to a 50 mm Offset 19

Figure 4-8. Formworks for the Concrete Wall Panels 20

Figure 4-9. Actual Reinforcement Done on the Concrete Wall Panels 20 Figure 4-10. Filling of Bucket with Ready-Mix Concrete 21 Figure 4-11. Concrete Pouring on Column Joint Areas with 8000 psi

Concrete Mix 22

Figure 4-12. Concrete Pouring on Column Joint Areas and Slabs

Using 5000 psi Concrete Mix 23

Figure 4-13. Concrete Finishing Done on the Slabs 23

Figure 4-14. Concrete Curing Done on the Slabs 24

Figure 4-15. Concrete Pouring on Columns and Slabs

Using 7000 psi Concrete Mix 24

Figure 4-16. Pre-Casting on Concrete Wall Panels Using

4000 psi Concrete Mix 25

Figure 4-17. Installation of Pre-Cast Walls Using Chain Blocks 26 Figure 5-1. Dimensions of Column C1 between Foundation

to Second Floor 33

Figure 5-2. Proper Sequence for Concrete Pouring of 5000 psi and

8000 psi Concrete Mix 52

Figure 5-3. Graph of Value Engineered Vs Original Cumulative

Costs at Tower 1 58

Figure 5-4. Graph of Value Engineered Vs Original Cumulative

Costs at Tower 2 59

Referensi

Dokumen terkait

UNIVERSITY OF THE PHILIPPINES LOS BAÑOS Office of the Vice-Chancellor for Research and Extension 3F UPLB Main Library Building, UPLB, College, Laguna 4031 Telefax Nos: 049 536-2354 and

Proposal UNIVERSITY OF THE PHILIPPINES LOS BAÑOS Office of the Vice-Chancellor for Research and Extension 3F UPLB Main Library Building, UPLB, College, Laguna 4031 Telefax Nos: 049