Cost Estimating

T

HE

R

OLE OF THE

P

ROJECT

M

ANAGER

AND

C

OST

E

STIMATING

T

he project manager plays an important role in develop- ment of the overall estimate of the total costs of the project. In addition the project manager develops check- points to ensure the overall project is completed within budget.

The project manager usually develops the budget in conjunction with a cost estimating department.

The purpose of this chapter is to review how to estimate a project’s costs in conjunction with other engineers, construction man- agers, financial staff and a cost estimating department if available.

G

ENERAL

a) Quality of Estimate

This chapter on estimating of engineering/procurement/con- struction (EPC) is roughly divided into conceptual and detailed estimating. The general range in the quality of these two phases of estimating is about 40% to 10%, respectively. The measure of the quality of an estimate is usually categorized by the amount of contingency that is contained in the estimate. For example, a 10%

estimate would have a 10% contingency. Due to the high develop- ment cost and the time necessary to produce a 10% quality esti- mate, most companies approve the funding and full execution of EPC type projects at the ± 20% estimate quality. It is possible, in the “specialist equipment” areas and building industry, to pro- duce 10% quality estimates from preliminary design information.

73

The accuracy of estimates varies considerably and is largely dependent on the quality of the estimating program and experi- ence of the estimator. Quality also can be controlled to a substan- tial extent, by increasing or decreasing estimating manpower and time. The relationship is not linear. Appropriate, modest invest- ments of time and resources will, usually, provide capital cost estimates of acceptable reliability. Further improvement becomes increasingly expensive, with only modest improvements in accu- racy, resulting from substantial expenditures of time and re- sources. A point is soon reached where estimate quality is almost completely controlled by problems of forecasting economic condi- tions, local project conditions and quality of project performance.

No significant improvement in estimate quality can be made thereafter, except by incorporation of actual design and cost infor- mation as it develops.

b) Purpose(s) of Estimates

Owner and constructor estimates are prepared at various stages of project development. They have two major purposes:

1. To establish cost levels for economic evaluation and financial investment.

2. To provide a base for cost control as the project develops.

This second purpose of “project control” is often ignored by

“professional” estimators as they perceive their only purpose is to develop a quality estimate. In such cases, the resulting estimate may be of a high quality for investment purposes, but of a low quality from a project execution/control point of view. As most conceptual estimating bases are structured on a system basis, rather than on an area basis, it requires considerable effort at an early estimating stage, to develop an estimate on an “area” basis that, in turn, maximizes the “controlability aspect.”

Even though a contractor’s first early estimate can be of a lesser quality than an owner’s estimate, it is recommended that a contractor provide an estimate early, after a contract award. This

very quickly establishes a base for contractor cost control and should provide the contractor with a sense of commitment and responsibility for the financial basis of the project.

Due to the lack of time, it is probable that this early concep- tual estimate would be a capacity-cost or curve-type estimate for direct costs with indirects on a percentage basis. Even though lacking time, the contractor should be encouraged to put as much quality (definition) into the estimate as possible, as this estimate may become the control base for the project.

The “appropriation” estimate, prepared by the owner, is on the same basis as the contractor’s estimate, but statistically broken down into further detail so as to provide a checking basis of the contractor’s first estimate.

The following could be the further breakdown:

• Itemized equipment list: material cost and labor man-hours

• Bulk materials: material costs and labor man-hours by cat- egory

• Off-site systems: material costs and labor man-hours

• Home office costs and engineering man-hours

• Field indirects: material costs, labor and staff man-hours

• Owner costs: capital and expenses

• Estimating allowance: risk analysis

The statistical development of man-hours provides informa- tion for overall scheduling and manpower resource evaluations.

c) Typical Estimating Categories

The following estimating methods or systems are the ones most commonly used:

1. Proration, Budget, Rough Order or Magnitude, etc.

2. Cost Capacity Curves 3. Equipment Ratio (curves)

The above methods are generally in the “Conceptual” category.

4. Quantity/Unit Cost

This last method is generally referred to as a detailed cost esti- mate.

P

RORATION

E

STIMATES

This method takes the cost of a similar, previously built facil- ity, and “prorates” the cost for the new facility, based on changes for project conditions, capacity, escalation, productivity, design differences, and time. This method is based on some historical data and a lot of statistical relationships and assumptions. It is, therefore, not very accurate and is generally around ±40%.

C

OST

C

APACITY

C

URVES

(O

VERALL

)

An historical data base is developed for similar plants where the total cost is related to capacity. This method is usually more accurate, generally around ± 30%, but does depend on the quality of the data base.

This method is also used, at a lower level of detail, for indi- vidual pieces of equipment and/or process/utility systems.

The above two conceptual estimating systems are generally used to give a quick and early indication of required investment level. The resulting evaluations are only used for “budget” pur- poses and investment possibilities. The information is not suffi- ciently accurate to make firm investment decisions. Sometimes investment decisions are made on this preliminary information, where economic viability is not the first priority. Projects to meet environmental standards, “stay in business” criteria, or R&D pro- grams would fall into this category. Another purpose of these

“early” estimating programs is to provide technical and economic information on investment and resource requirements to advance the technical basis and estimating quality to a higher level. Thus, many projects are funded on a partial or phased approach.

E

QUIPMENT

R

ATIO

(C

URVES

)

This method calculates the costs of “bulk” materials, such as concrete, electrical, structural, piping, etc., as a percentage of

the major equipment cost. Ratio methods can be used only with an appropriate data base. The accuracy of this method is gener- ally ± 20%. This quality of estimate is usually the minimum re- quirement for a “full investment” decision of an EPC project.

This “appropriation” estimate for an EPC project should be produced after completion of conceptual design and process selec- tion and would be an update of the conceptual estimate prepared during feasibility studies.

The following would be the design/scope basis:

• Overall process flow diagrams

• Heat and material balances

• On-site and off-site facilities and layouts (power, steam, air, electricity, water)

• Preliminary plot plans/building layouts

• Equipment list—by size and category

• Preliminary execution plan/organization/resources/sched- ule

• Completed survey of appropriate estimating data

This would be an equipment and bulk ratio estimate for di- rect labor and material costs. Indirect costs would be factored from direct costs. A further statistical breakdown would be made to develop engineering and construction man-hours for schedul- ing and resource evaluation.

Q

UANTITY

U

NIT

/C

OST

E

STIMATES

This method is the most accurate, generally ± 10%, but it can be costly and time-consuming, as detailed takeoffs must be made of all labor and material units in the system. This method requires that engineering be sufficiently advanced so that accurate material quantity takeoffs can be produced. It also requires detailed histori- cal data for applying unit man-hour rates and monetary costs to the estimated quantities.

This last, general category is usually referred to as a detailed

cost estimate.

This estimate can be developed only when the process design has essentially been completed. It will also require a significant amount of detailed engineering to be completed so that bulk material takeoffs can be developed for civil work, mechanical, piping, electrical, etc.

The following would be typical for an EPC project:

a) Approved process descriptions—feedstock and product slate

b) Licensor engineering (schedule A package) c) Approved flow sheets

d) Heat and material balances

e) Approved process piping and instrumentation diagrams (PIDs) (process and utilities)

f) Approved plot plans g) General specifications

h) Equipment specifications and data sheets i) Completed site-soil survey and report j) Site development and grading drawings k) Underground piping and electrical layouts l) Concrete foundation layouts

m) Above-ground piping layouts n) One-line electrical drawings o) Milestone schedule

p) Detailed project-owner conditions and requirements q) Project-owner conditions and requirements

r) Environmental and governmental requirements s) Equipment quotations—transportation costs t) Bulk material takeoffs

u) Labor cost-productivity data

v) Layouts for construction temporary facilities

w) Organization charts (project, engineering, and construc- tion)

x) Personnel schedules and manpower histograms y) Construction equipment schedules

A detailed estimate would be quantity based with separate unit costs for material, labor, and man-hours. Construction would be based on an area breakdown rather than on the “system” basis of a conceptual estimate. This estimate could be an updated, trended version of the first conceptual estimate and subsequent updates or a completely separate exercise. In most cases, it would be a separate exercise, as the format and work breakdown struc- ture would be different and more detailed than that of a concep- tual estimate. In particular, the construction estimate would be on an area basis with takeoffs by work units and man-hour unit rates.

Apart from “trend” updates, this estimate breakdown could be sufficient to control costs to completion of the project. This estimate could be developed about 6-8 months after contract award, on an EPC reimbursable type project, as this amount of time would be required to provide an adequate completion of detailed engineering.

The most significant element of a high quality estimate is the maximizing of quantities and minimizing of factors and statistical relationships.

“F

UDGING

THE

D

ETAILED

E

STIMATE

Many companies have a policy that requires a detailed 10%

estimate before the project appropriation will be approved. These same organizations, typically manufacturing companies, also re- quire that the project be started “yesterday.” Manufacturing and plant management are able to “insist” on these conflicting objec- tives. These two objectives are incompatible. In most cases, the practical resolution of this management inconsistency is for the estimate to be “fudged.” This is to say, the estimate shows a 10%

contingency, “below the line,” with a similar amount of money

“buried above the line” in individual categories where the risk is deemed to be the greatest. Whereas this “process” meets the com- pany financial approval policy, it, nevertheless, provides a poor basis to execute and manage the project. From a project manage-

ment viewpoint, it is poor practice. It is also quite common for such companies to execute projects on a “crisis management”

basis. In most cases, this type of approach will increase the capital costs of their projects. However, this may increase the economic return as the product can reach the marketplace at an earlier time.

P

ROJECT

M

ANAGEMENT

E

STIMATING

R

ESPONSIBILITY

As many companies have a formal estimating section, the relationship between the estimator and project manager should be clearly defined and properly understood by all parties.

The project manager should “direct” the estimate(s) develop- ment, approve the estimate(s) prior to issue, and ensure the estimate(s) properly reflects:

a) Project objectives and their priorities b) Design scope and design specifications

c) Maximizing of quantities and minimizing of factors (num- bers of drawings and construction work units)

d) Correct evaluation of design and labor productivities e) Current project and site conditions (access, congestion, etc.) f) Proposed execution plan/contract strategy

g) Schedule requirements (economic versus acceleration) h) Adequate contingency evaluation

As can be seen from the above “definition,” the project man- ager is actively involved in the development of the estimate and is responsible for the final product.

D

EVELOPING OR

C

HECKING AN

E

STIMATE

a) Scope Review

To ensure that the scope definition is of the required quality,

the estimator/project manager should make a detailed review of all basic design documents, their revision numbers, and dates of issue:

1) Check that all major equipment is included and is listed by equip- ment number.

2) Review all items shown on plot plans, flow sheets, PIDs, and equip- ment lists to ensure their inclusion in the estimate.

3) Equipment and system capacities, flow rates, temperatures, and pressures should be checked for deviation.

4) Check that owner costs are to be included, or shown separately.

5) Evaluate deviations in the scope, design, or estimating basis from those assumed in the earlier estimate and include these on a “puts and takes” list.

6) Specialist engineers assigned to the project should review and verify the design scope.

b) Project Conditions Review

Prior to developing the line-by-line details of the estimate, an overall evaluation should consider the following.

1) Project location considerations, i.e., site characteristics (high winds, weather, soil conditions) and local affiliate-govern- mental practices or regulations.

2) Schedule, i.e., start of engineering, start of construction, me- chanical completion, and milestone dates.

3) Labor basis, e.g., subcontract or direct hire.

4) Economic outlook.

5) Contracting mode and execution plan.

6) Estimate is compatible with contract conditions.

c) Reviewing Significant Overall Relationships

A comparison should be made of significant relationships including:

1) Engineering man-hours per piece of equipment.

2) Construction man-hours per piece of equipment.

3) Ratio of direct field man-hours to engineering man-hours.

4) Contractor’s home office and engineering cost as a percent of total cost.

5) Contractor’s fee as a percent of total cost.

6) Indirect construction costs as a percent of direct labor cost.

7) Percent breakdown of engineering man-hours by prime account.

8) Percent breakdown of construction man-hours by prime account.

9) All-in engineering man-hour rate.

10) All-in field man-hour rate.

11) Escalation allowances for material and labor.

12) Productivity factors for engineering and construction.

13) Currency exchange rates (for overseas purchases).

d) Major Equipment and Material

The cost of major equipment can be established by actual quotations or from historical data. The method depends on the type of equipment involved and its relative cost. For example, quotations should be obtained for large compressors, but small mixers may be estimated from catalogues or estimating manuals.

1) Developmental (or growth) allowances for “Fast Track”

projects: Estimates based on vendor quotes, catalogue prices, or initial inquiries should include an allowance for future increases in scope. Costs can rise as much as 15% from an original purchase price as a result of design changes. Verify that the estimate has included an appropriate design allow- ance (typically 5-10%) for future changes. Based on the gen- eral specifications and detailed equipment specifications and data sheets, evaluate as follows.

2) Vessels (towers, reactors, drums): Check unit costs; adjust for size, material, shop versus field fabrication, operating tem- perature-pressure, metallurgy, number of manholes and plat- forms, internals required, and the need for insulation-stiffening rings and lifting lugs.

3) Heat exchangers: Check the cost per square foot of useful transfer surface.

4) Heaters and furnaces: Check the cost per British thermal unit of heat absorbed. Evaluate the degree of prefabrication prior to field erection.

5) Boilers and superheaters: Check the cost per pound of steam generated.

6) Pumps: Check the cost per horsepower. Pumps of similar capacity can vary greatly in price depending on type and materials of construction. It is important to know all special service requirements and design characteristics.

7) Storage Tanks: Check the cost per barrel capacity and the cost per pound of fabricated weight. Ensure that tank foundations are adequate for duty and soil conditions.

8) Evaluate project-schedule conditions which could influence prices, e.g.:

i. Market conditions

ii. Purchasing preference/plant compatibility/mainte- nance costs

iii. Schedule acceleration (premium costs) iv. Escalation/currency exchange rates

v. Freight, duties, taxes

vi. Size of order/quantity discount

Use a “cheapest source” program for guidance on the source for a worldwide purchasing program.

e) Bulk Materials: Quantities and Costs Evaluation 1) Concrete:

i. Spot-check design quantities for large equipment foun- dations

ii. Average cost per cubic yard installed (with rebar, formwork, excavation, and backfill)

iii. Quantity of rebar, formwork, excavation, and backfill per cubic yard of concrete.

2) Roads and paving: Cost per square foot installed—overall areas from plant layout.

3) Underground piping and sewers:

i. Total linear feet from drawing layout ii. Location and number of manholes

iii. Cost per linear foot of installed piping, including exca- vation, backfill, manholes and sumps.

On large projects, underground quantities are often under- estimated.

4) Miscellaneous concrete work: Ensure sufficient require- ments for cooling tower basins, API separators, pipe sleep- ers, culverts, and particularly road and electrical crossings.

5) Fireproofing:

i. Check the cost per area of surface fireproofed.

ii. Ensure adequate allowance for cutouts and rework.

6) Buildings, structures: Review individual costs for the sub- structure, heating, ventilation, air conditioning, plumbing, and lighting as a function of the floor area and total cost.

Look at all-in square-foot costs of building.

7) Site preparation:

i. Review grading and site preparation; check costs per cubic yard.

ii. Check soil conditions, i.e., type, frost depth, de-water- ing, sheet piling, and draining requirements.

iii. Consider possible underground obstructions.

On large grass roots projects, earth-moving quantities are often underestimated.

8) Piling:

i. Check the all-in cost per linear foot (including mobiliza- tion and demobilization) and the type of piles (e.g., pre- cast, in situ, or timber) and the cutting of pile caps.

ii. Check who does the layout work (the prime contractor or a subcontractor?).

9) Fencing and railroads (usually subcontracted):

i. Total linear feet.

ii. All-in subcontract installed costs.

10) Piping estimating methods: Following are four method’s of preparing a piping estimate. The specific method would depend on detail and accuracy of the estimate.

i. “Estimating by Length Method.” This method is based on historical data and assumes an average number of fittings and flanges for a “standard” piping configura- tion. Costs would be on a unit length basis by pipe size and schedule. Fabrication would be separated from field installation. It is necessary to add only the cost of valves, pipe supports, testing, etc. to arrive at a total direct cost for the piping system. Care should be taken to check allowances for unusual complexity of piping arrange- ments (especially on-site units or revamps).

ii. “Estimating by Weight Method.” In this method, piping materials are assumed to have a value approximately proportional to their weight. Pipe is assigned a cost per pound for material and a number of man-hours per ton for fabrication and erection. Adjustments should be made for unusual materials and labor productivity for the plant location.

iii. “Estimating by Ratio Method.” This method calculates piping as a percentage of the major equipment cost.

Ratio methods can be used only with an appropriate data base. This is not a very accurate method and is usually applied to conceptual estimates.

iv. “Estimating by Unit Cost Method.” This method is more accurate but is costly and time-consuming as detailed takeoffs must be made of all labor and material units in the system. This method requires that engineering be well advanced before accurate takeoffs can be produced.

It also requires detailed historical data.

v. “Piping Estimate Review.” Examine the method and extent of takeoff by sampling line takeoffs, and compare actual quantities and costs with estimate. Review the basis of fabrication, impact of special materials, etc. Also check the following: