• Tidak ada hasil yang ditemukan

Results and Findings

University of Cape Town

6. Results and Findings

6.1Profile of Respondents

The profile of the respondents for the survey is presented in Table 1.

36 B. S. Waziri/ Journal of Construction Business and Management (2018) 2(1). 33-40 Table 1: Profile of Respondents

Characteristics Frequency Percent Category of Respondent

Government Concessionaire Developers Lenders

24 21 19 22

27.91 24.42 22.09 25.58 Educational Qualification

High School Diploma

University Degree/HND Master/ PhD

0 18 51 17

0.00 20.93 59.30 19.70 Work Experience

Less than 5 years 5 to 10 years 11 to 15 years 16 to 20 years Greater than 20 years

11 16 19 24 16

12.79 18.60 22.09 27.90 18.60 Position

Managing Director Principal officer Senior Personnel Others

21 25 28 12

24.42 29.01 32.56 13.95 Designated Profession

Engineering Architecture Quantity Surveying Building

Estate Surveying Others

19 16 12 17 12 10

22.09 18.60 13.95 19.76 13.95 11.63

The demographic profile of the respondents revealed that 27.9% of the survey participants are from government establishments whereas 24.42%, 22.09% and 25.58% are from the offices of concessionaires, developers and lenders respectively. The profile further revealed that most of the respondents (59%) are first degree holders and 19% either have a Masters or PhD degree. The results also show that the majority of the respondents occupy management positions as either principal, deputy directors or directors in their organisations. These results indicate that the information obtained from these categories of respondents can be considered adequate.

6.2Risk Factors of BOT

The results of Mean Item Scores of risk factors are presented in Table 2. The results indicated that changes in government policy which falls under the political risk factor is ranked first which is followed by unfavorable business environment, project company default, time performance risk and cost performance risk. The factors considered to have the least risk are an outbreak of hostilities, strong public opposition and inclement weather.

. Table 2: Mean Item Score of Risk Factors

S/No Risk Factors MIS MD Rank

1 Change in government policy 4.3953 0.7658 1

2 Unfavourable general business environment 4.2093 0.5797 2

3 Project company default 4.2093 0.5797 3

4 Time performance risk 4.1279 0.4983 4

5 Cost performance risk 4.0814 0.4518 5

6 Excessive development cost 4.0581 0.4286 6

7 Instability in government 4.0116 0.3821 7

8 Failure to raise finance for the project 4.0116 0.3821 7

9 Lack of experience in handling the project 3.8837 0.2542 8

10 Termination of concession 3.8721 0.2425 9

11 Changes in project specifications 3.7558 0.1262 10

12 Quality performance risk 3.7326 0.1030 11

13 Variation 3.7326 0.1030 11

14 Force majeure 3.7326 0.1030 11

15 Inflation risk 3.7093 0.0797 12

16 Currency risk 3.7093 0.0797 12

17 Lack of integrity in the tendering process 3.6977 0.0681 12

18 Change in economic policies 3.6628 0.0332 13

19 Production target slippage 3.6047 0.0249 14

20 Default by concessionaire 3.6047 0.0249 14

21 Nonexistence of legal and regulatory system 3.6047 0.0249 14

22 Delays in design approval 3.6047 0.0249 14

23 Foreign exchange 3.5930 0.0365 15

24 Changes in general legislation affecting the project 3.5930 0.0365 14

25 Resources risk 3.5814 0.0482 16

26 Error in operation and maintenance cost estimate 3.5814 0.0482 16

27 Changes in design during construction 3.5814 0.0482 16

B. S. Waziri/ Journal of Construction Business and Management (2018) 2(1). 33-40 37

28 Lack of commitment to concession contract 3.5698 0.0598 17

29 Adverse action of the government 3.5465 0.0831 18

30 Lack of expertise 3.5465 0.0831 18

31 Delay in feasibility study 3.5349 0.0947 19

32 Changes in demand for the facility over concession period 3.4767 0.1528 20

33 Complicated negotiations 3.4535 0.1761 21

34 Labor risk 3.4419 0.1877 22

35 Delay in settling claims 3.4302 0.1993 23

36 Flaws in contractual documentation 3.3953 0.2342 24

37 Unfavorable local conditions 3.3953 0.2342 25

38 Expensive and lengthy tendering process 3.3605 0.2691 26

39 Material unavailability 3.2791 0.3505 27

40 Labor shortage 3.2209 0.4086 38

41 Unavailability of quality personnel to operate facility 3.1628 0.4668 29

42 Inappropriate operating methods 3.1628 0.4668 30

43 Outbreak of hostilities (wars, riots and terrorism) 3.1163 0.5133 31

44 Strong public opposition 2.9651 0.6645 32

45 Inclement weather 2.9535 0.6761 33

6.3Pareto Analysis

To develop the Pareto chart, the cumulative percentages from the mean scores were calculated and presented in Table 3. The risk factors were assigned the codes (RF) for the 45 factors investigated. The factors were arranged in

descending order as required by the principle of Pareto analysis to compute the cumulative percentage for constructing the cumulative frequency curve (Haughey, 2014).

Table 3: Cumulative Percentages of Risk Factors

Code Risk Factors MIS Count % of Total Cumulative

Percent

RF1 Change in government policy 4.3953 2.6973 2.6973

RF2 Unfavorable general business environment 4.2093 2.5831 5.2804

RF3 Project company default 4.2093 2.5831 7.8635

RF4 Time performance risk 4.1279 2.5332 10.3967

RF5 Cost performance risk 4.0814 2.5046 12.9013

RF6 Excessive development cost 4.0581 2.4903 15.3917

RF7 Instability in government 4.0116 2.4618 17.8535

RF8 Failure to raise finance for the project 4.0116 2.4618 20.3153

RF9 Lack of experience in handling the project 3.8837 2.3833 22.6986

RF10 Termination of concession 3.8721 2.3762 25.0748

RF11 Changes in project specifications 3.7558 2.3048 27.3796

RF12 Quality performance risk 3.7326 2.2906 29.6702

RF13 Variation 3.7326 2.2906 31.9608

RF14 Force majeure 3.7326 2.2906 34.2514

RF15 Inflation risk 3.7093 2.2763 36.5277

RF16 Currency risk 3.7093 2.2763 38.8040

RF17 Lack of integrity in the tendering process 3.6977 2.2692 41.0732

RF18 Change in economic policies 3.6628 2.2478 43.3209

RF19 Production target slippage 3.6047 2.2121 45.5330

RF20 Default by concessionaire 3.6047 2.2121 47.7451

RF21 Nonexistence of legal and regulatory system 3.6047 2.2121 49.9572

RF22 Delays in design approval 3.6047 2.2121 52.1693

RF23 Foreign exchange 3.593 2.2049 54.3743

RF24 Changes in general legislation affecting the project 3.593 2.2049 56.5792

RF25 Resources risk 3.5814 2.1978 58.7770

RF26 Error in operation and maintenance cost estimate 3.5814 2.1978 60.9748

RF27 Changes in design during construction 3.5814 2.1978 63.1726

RF28 Lack of commitment to concession contract 3.5698 2.1907 65.3633

RF29 Adverse action of the government 3.5465 2.1764 67.5397

RF30 Lack of expertise 3.5465 2.1764 69.7160

RF31 Delay in feasibility study 3.5349 2.1693 71.8853

RF32 Changes in demand for the facility over concession period 3.4767 2.1336 74.0189

RF33 Complicated negotiations 3.4535 2.1193 76.1382

38 B. S. Waziri/ Journal of Construction Business and Management (2018) 2(1). 33-40

RF34 Labor risk 3.4419 2.1122 78.2504

RF35 Delay in settling claims 3.4302 2.1050 80.3554

RF36 Flaws in contractual documentation 3.3953 2.0836 82.4390

RF37 Unfavorable local conditions 3.3953 2.0836 84.5226

RF38 Expensive and lengthy tendering process 3.3605 2.0622 86.5848

RF39 Material unavailability 3.2791 2.0123 88.5971

RF40 Labor shortage 3.2209 1.9766 90.5737

RF41 Unavailability of quality personnel to operate facility 3.1628 1.9409 92.5146

RF42 Inappropriate operating methods 3.1628 1.9409 94.4555

RF43 Outbreak of hostilities (wars, riots and terrorism) 3.1163 1.9124 96.3679

RF44 Strong public opposition 2.9651 1.8196 98.1875

RF45 Inclement weather 2.9535 1.8125 100.00

The Pareto chart presented in Figure 1 was constructed using the cumulative percentage counts of the risk factors based on the procedure outlined by Haughey (2014). The

broken line on the chart separates the vital few (top 20%) from the trivial many (80%).

Figure 1 Pareto Chart of Risk Factors

From the Pareto chart, the nine highest risk factors are established to be the vital few (20%). These factors are a change in government policy, unfavorable general business environment, project company default, time performance risk, cost performance risk, excessive development cost, instability in government, failure to raise finance for the project and lack of experience in handling the project.

Dokumen terkait