Production I- Production I-
Chapter 3 Part B
3.7. Streamlining the Best Concept
3.7.3. Scenarios for Gantry Systems
The scenanos presented in this section are of level two possibly level three abstraction and have followed from an initial inspection and evaluation of level one abstractions. To reiterate, a level one abstraction are the physical laws and or
phenomenon governing a task. This is very general. Level two abstraction would be the developed or tangible components available for the realization of a level onc abstraction. Level three would describe a specific component or device type. It is however possible for the levels to overlap into each other in some cases.
Table 3.4. Level two morphological chart
Support Track Wheels Air Slides Pedi- Beam
cushion pulator
Prop- Driven Air thrust Moving Linear Hand
ulsion wheels cable induction Chain
Power Electric Diesel or Hydraulic Sottled Steam Man-
Petrol Gas ual
force Trans- Selts Chains Gears and Hydraulic Flexible
mission shafts cable
Stopping Brakes Reverse Ratchet Thrust
Lifting Hyd- Pneumatic Rack and Chain Or Link-
raulic Ram Pinion Rope age
Ram Hoist
Locate Photo Proximity Human Sensor Switch Vision
Using Table 3.4. above together design handbooks the following gantry concepts have been presented.
3.7.3.1. Single Girder Overhead Runway Cranes
This consisted of an f-beam supported by four wheels attached to a carnage traveling on a runway. The trolley traveling on the lower nanges carries the electric chain hoist, fOfllling the lifting unit. The crane could have been moved by hand chain tUfIling a sprocket wheel, which is keyed to a shaft. The pinions on the shaft could bc designed to mesh with gears, keyed to the axles of two wheels. An under slung construction could have also been used with the pairs of wheels at each comer which riding on the lower Oange of the I-beam rails as shown above.
One wheel axle on each carriage could be coupled directly to a shaft which transmits power from a gear reducer. Or each of the two sets of wheels on opposite ends of the girders could be driven by a separate motor accompanied by the appropriate gearboxes and braking systems. Figure 3.9 below shows a crane girder and traveling unit that travels on and is supported by an erected runway.
The travcling unit concept is depicted in Figure 3.10.
1 ,
r I
I
[
Figure 3.9. Single girder runway crane
-.' 11 11
Figure 3.10, The traveting unit concept
3.7.3.2. Double Girder Cnllles
This scenario consisted of two bridge girders, as opposed to une in Figure 3.9, traveling on parallel runways, on top of which were rails on which the self contained hoisting unit, called the trolley, traveled, see Figure 3.11. The girders were supported at the ends by trucks (carriages) with two wheels. The crane would be designed to move along the track by a motor, through shafting and gearing to the truck wheels. The bridge girders could be of the I-beam or box section, with the latter being employed to give torsional and lateral stiffness for long spans.
- 950.0
!
700.0I W -
350.0--i ~~
120.0Figure 3.11. The trolley for a double girder gantry (standard dimensions-mm)
The girders were designed for rigid attachment to the carriage, which carried/
housed double nangcd wheels for supporting the bridge. As a measure of safety the girders would project over the rail so that in the case of a broken wheel or axle, the girder would rest on the rail. The wheels could be driven as outlined in the preceding section.
The trolley would consist of a frame which carried the hoisting machinery and is supported on wheels for travel along the bridge the bridge rails. The wheels are coupled to the trolley traverse motor through suitable gear reduction. The hoisting machinery would consist of a motor, motor brake, load brake, gear reduction, and rope drum.
Wire rope winding in helical grooves on the drum could be designed to be reeved over sheaves in the upper block and lower hook block for additional mechanical advantage. Limit switches could be provided to stop the motor when the limits of travel are reached.
3.7.3.3. The clcctrics involved for the Double and Single girders
Current could be brought to the crane by sliding or rolling collectors in contact with the conductors attached to or running parallel to the runway. Current to the trolley could be effected in a similar manner. Festooned multiconductor cables were also available as an option for the transfer of current.
The motors, either altemating or direct current, lIsed for the application would be those intended and designed for crane application. Direct current motors would probably be of the series wound type and alternating current could be of the wound rotor or squirrel cage type.
3.7.3.4. Gantry Cranes
This scenario was a modi ficaliol1 of the travcling cranes orthe single and double girder type. It could find application were there would be difficulty in erecting an
overhead runway. The bridge/s would be carried at the ends by legs, supported by carriages on wheel at either end at either cnd so that the crane could traverse. As with options above the hoisting unit would be attached to the lower nange in the case of a single girder and attached to a trolley in the case of a double girder. The crane could be driven by a motor through gear reduction to shall, which drives vertical shafts through bevel gears. Bevel and spur gear reductions connect the axles orthe wheels with the vertical shafls. As an alternative, the crane could have been built without the cross shaft, using separate motors, brakes and gear reducers at each end of the crane. The carriage travel unit concept for the gantry crane was essentially the same as that depicted in Figure 3.10.
I • k
;
,n
r I
I I I \
\
\
\I I I
I 1 \ \ I
• \ \
1
~
\Figure 3.12. The gantry crane
FEM analysis. preliminary calculations and consulting with material suppliers and catalogues revealed firstly that, there was no need for a double girder set uP. as the load was under 3 t. Secondly that the denection was directly proportional to the length of the girder. The runway crane girder Figure 3.9 extended from the timber
bay right across the tunnel to the opposite side. There was little rool11 for experimentation except perhaps to consider the use of stiffcners to decrease the dellection. As mentioned the gantry crane in Figure 3.12 was to be implemented when it became inconvenient to erect an overhead runway.
Whilst it would not be entirely impossible to do design and erect a runway on the side wall, one would have a host of constraints to contend with. Amongst which were the vibration and stresses associated with rock masses. The gantry crane had the Ilexibility to have it's length modified as it could have been designed to extend into the tunnel by a distance fitting for it's purpose. A track could be layed alongside the main track to facilitate the operation of this structure. Therefore the gantry crane was chosen for development.