SERVICE DELIVERY ANNUAL REPORT 2010/2011

Dalam dokumen 2010/2011 Annual Report (Halaman 67-79)

Electricity

The Council spended in the region of R62 million to upgrade Electrical bulk supply in Lesedi area the past two years to have a stable electrical supply to the communitee and for future development.

Heidelberg main supply upgraded from 40 mva to 60 mva.

Ratanda Electrical Bulk supply from 10 mva to 40 mva.

Jameson Park bulk supply from 5 mva to 20 mva.

Build a new 22 kv switching substation in Impumelelo

Build a new 11 kv switching substation and install two new bulk supply cables Ext 23.

Build a new 11 kV switching substation and install two new supply cables from Rat6anda substation in Ext 7.

Upgrade bulk supply to Industrial area installation of two electrical cables.

The Council budget every year R11 million to maintain the electrical reticulation.

Water and Sewer

The Council build a new 6 Ml reservoir for water supply to Heidelberg and Ratanda – R9 million.

The Council is busy with a project War against water leakages. Impumelelo water leakages are repaired and busy in Ext 23. DWAF funded R700 000.

The installation of a new motor control unit for the Main Reservoir of Ratanda and Heidelberg were also completed. Total amount spended R312 935,70.

The upgrading of Ratanda Floating Reservoir were completed – amount R975 871,60.

The Council budget every year R2 million to maintain the water and sewer network.

Roads and Stormwater

The Council completed 22 km of roads in Lesedi area the last two years and used R44 million and in the 2011/2012 budget the Council will complete 13 km of roads – R30 million.

The Council budget every year R2 million to do resealing work in Lesedi area.

The Council budget every year R2 million to maintain Roads and Stormwater. Total km of roads to maintain is 692 km.

Waste Removal

The Council bought two new waste removal trucks in the 2010/2011 budget – R3 million.

General

All above projects the past 2 years created 720 temporary work and 15 CLO’s.

PROJECTS 2010/2011

WATER PROJECTS DEPARTMENT ENGINEERING SERVICES

PROJECTS UNDERTAKEN FOR THE PERIOD JULY 2010 TO JUNE 2011 PROJECT NAME & COST

Network Extensions and Upgrading Upgrade Floating Reservoir Budget: R1 000 000

Funds Used: R975 871,00 Consultant: Scip

Contractor: Aquatan

Consultant was appointed and tenders were invited to appoint a contractor.

Contractor was appointed during February 2011. The work was completed 15 June 2011.

The water networks are constantly upgraded and extended in order to ensure better service delivery and to reduce operation and maintenance costs.

Bulk Water Supply Obed Nkosi Pipeline Funds roll over

Budget: R3 275 176 million Funds Used: R3 275 176 million Consultant: SCIP

Contractor: Mamohato Construction Cession: Fukama

Project 100% completed. Project will be completed during 2010/2011 budget.

Project delayed due to rainfall and due to the incompetence of Main

Contractor. Cession with a new

Contractor and will be completed end of December 2010.

Maintenance of Water Network Budget: R1 149 000

Funds Used: R1 133 575 In-house

The water network is constantly maintained and repaired.

Motor Control Unit Reservoir Heidelberg

Budget: R315 000

Funds used: R312 935,70

Contractor: CMS Water Engineering

Installation of a New Control Panel for the reservoir by a Contractor. Project completed end of June 2011.

Bulk Water Supply Obed Nkosi

Motor Control Unit Reservoir Heidelberg

New Floating Roof Reservoir

SEWAGE PROJECTS DEPARTMENT ENGINEERING SERVICES

PROJECTS UNDERTAKEN FOR THE PERIOD JULY 2010 TO JUNE 2011 PROJECT NAME & COST

Maintenance of Sewer Network Upgrading Lesedi (Ongoing) Budget: R1 150 000

(In-house)

Funds Used: R1 100 727

The sewer network is constantly maintained

The sewer networks are constantly upgraded and extended in order to ensure better service delivery and to reduce operation and maintenance costs.

ROADS, STORMWATER AND PUBLIC WORKS PROJECTS DEPARTMENT ENGINEERING SERVICES

PROJECTS UNDERTAKEN FOR THE PERIOD JULY 2010 TO DECEMBER 2010 PROJECT NAME & COST

Building of New Paved Roads Lesedi, Ratanda 1,6,7,5,23 and Impumelelo Ext

2.

Budget: R14 602 000 (2009/2010) Funds Used: R8 902 000

Funds roll over 2010/2011: R5 700 000 Funds Used: R5 700 000

Consultant: SCIP

Contractor: Century Civils

Madiba Road Ext 23: Budget: R1 800 000 – completed.

Project 100% completed. Project delayed due to rainfall ± 3 months.

Build 6.6 km paved roads. Employed a Contractor making use of Black

Empowered Sub Contractors, making use of 2 CLO and 6 Sub contractors was used. 153 Local laboures were used. Project was completed end of December 2010.

Road Resealing Lesedi.

Budget: R2 000 000

Funds Used: R1 064 322,60 Consultant: Civil Consultants

Contractor: TDR Civils (Cession with KPG)

Project was completed end of June 2011. 3 km of road will be resealed, at the back of the old Council building in Heidelberg, Hendri Schleckamp Rensburg, Wessels St Jordaan Park, Merz St.

General Maintenance Roads Budget: R1 506 329

(In House)

Funds Used: R1 506 318

Maintenance of roads

Appointed 30 temporary workers to clean streets in Ratanda.

Building of New Roads Lesedi Impumelelo, Ext 23, Ext 7, 8, 1 and

Jameson Park.

Budget MIG: R19 239 000 MIG Funds used: R19 239 000 Budget Council: R5 171 700

Council Funds Used: R1 854 796,28

Build 11 km paved roads. Employed 4 BBBEE Contractors making use of Black Empowered Sub Contractors, making use of 6 CLO. 260 Local

Consultants: Civil Consultants

Contractor: Masphi Bambella & Century Civils JV, (Ext 23/26 and Jameson Park).

Contractor: Kwinjabols (Impumelelo) Consultants: Scip

Contractor: Mopani Makweteng Civils (Ext 7 & 8).

Contractor: Peter Abraham Moagi Civils (Ext 1).

laboures were used.

Ext 23 – project completed.

Jameson Park – project completed.

Impumelelo – project completed.

Ext 7 – project completed.

Ext 1 – project completed.

Ext 8 – project completed.

New Paved Roads in Ratanda Ext 1,7,8, Impumelelo, Jameson Park and Ext 23

Impumelelo Roads & Stormwater

Maintenance Roads in Lesedi

Grading of Gravel Roads in Rural Areas

Grading of Gravel Roads in Ratanda Area

Resealing of Roads in Lesedi

Maintenance of Kismet Street – Shalimar Ridge

SPORT RECREATION & CULTURE PROJECTS DEPARTMENT ENGINEERING SERVICES

PROJECTS UNDERTAKEN FOR THE PERIOD JULY 2010 TO JUNE 2011 PROJECT NAME & COST

Palisade Fencing Library Shalimar Ridge

Budget: R200 000

Funds Used: R107 949.75

Contractor: Nhlanhla Yami Trading

Project Completed. Employed a Black Empowered Company.

Ratanda Cemetery Entrance Paving Budget: R150 000

Funds Used: R101 445.15 Contractor: TDR Civils

Project Completed. Employed a Black Empowered Company.

Upgrade of Union Sport Grounds Budget: R400 000

Funds Used: R396 544 Contractor: Odd Jobs

Project completed

Palisade Fencing Library Shalimar Ridge

Ratanda Cemetery Entrance Paving

Union Sport Grounds

ELECTRICITY PROJECTS DEPARTMENT ENGINEERING SERVICES

PROJECTS UNDERTAKEN FOR THE PERIOD JULY 2010 TO JUNE 2011 PROJECT NAME & COST

Upgrade Low Tension Network:

Heidelberg Budget: R600 000

(In House)

Funds Used: R599 973,52

Project is 100% completed. Install a underground cables and upgrading of low tension lines. To ensure a stable electrical supply to the consumers.

Appointed 10 temporary workers.

Upgrade Electrical Bulk Supply:

Heidelberg, Ratanda & Jameson Park Heidelberg Sub

Budget: R400 000 Funds Used: R398 899 Ratanda Sub

Budget: R300 000 Funds Used: R287 234 Jameson Park Sub Budget: R500 000 Funds Used: R494 610 Consultant: Lyo Emfuleni

Contractor: Immediate Electrical

Eskom will complete the project in July 2012. The project on the Council side was completed by the end of Nov 2010.

Project will be completed in 2 years.

Council paid already R27 million to ESKOM for upgrade of the substations.

Upgrade Ext 23 Electrical Feeder and Internal New Substation

Revised Budget: R10 585 735 Funds Used: R9 183 728,42 Funds budgeted 2011/2012 budget Consultants: Lyon & Partners Contractor: Siza-Mekaar

Consultant was appointed, tender closed 1/7/2010 and tender for Contractor closed on the 29/11/2010.

Project was completed 26 August 2011.

DEPARTMENT ENGINEERING SERVICES

PROJECTS UNDERTAKEN FOR THE PERIOD JULY 2010 TO JUNE 2011

Upgrade Ext 7 Electrical Feeder and Internal New Substation Revised Budget: R5 640 350 Funds Used: R4 640 350

Funds budgeted 2011/2012 budget Consultants: Lyon & Partners Contractor: Immediate Electrical

Consultant was appointed, tender closed 1/7/2010 and tender for Contractor closed on the 29/11/2010.

Project was completed 24 August 2011.

Upgrade Bulk Supply Industrial Area Revised Budget: R6 580 930

Funds Used: R5 296 818,87 Funds budgeted 2011/2012 budget Consultants: Lyon & Partners Contractor: Immediate Electrical

Consultant was appointed, tender closed 1/7/2010 and tender for Contractor closed on the 29/11/2010.

Project will be completed end of September 2011.

General Maintenance Budget: R11 240 000

In-house

Funds Used: R11 205 671

Regularly maintenance is done on substations, underground reticulations and overhead lines and repair 11 kV cable and substations faults.

General Maintenance streetlights Budget: R620 520

In-house

Funds Used: R620 518

Regularly maintenance is done on 2500 streetlights and 125 High Mast Lights.

Upgrade Load Control System Heidelberg Substation Budget: R1 600 000

Funds Used: R1 594 407,00 Consultant: Lyon & Partners Contractor: Farad (PTY)LTD

Installation of New Load Control

System for the new Eskom supply point in Heidelberg substation.

Project completed.

Retief Substation New 11 kV Switchgear

Ratanda Substation New 11 kV Switchgear

New 20 mVa Transformers Heidelberg and Ratanda Substation

Cables installed in Ext 23,7 and Industrial Area

Ratanda Ext 7 New Switching Substation

Temporary workers busy in Marchall street to dig trenches to install underground electrical network and remove overhead lines.

Installation of New Load Control System Heidelberg Substation (Geyser Control)