BAGAN ALIR PELAKSANAAN PEKERJAAN
SMPK
MOBILISASI
SDM ALAT BAHAN
CEK
PEK. PENGUKURAN
SHOPDRAWING & PERHIT. MC O
CEK
PEKERJAAN BOWPLANK
GAL. TANAH BIASA/ CADAS
CEK GALIAN JADI
PAS. BEGESTING CEK
PAS. BEGESTING
JADI
PEK. KISTDAM & PEKERJAAN PENGERINGAN PAS. BATU KALI 1 : 4
CEK
PEKERJAAN PEK.PEMBESIAN
PEK. KISTDAM & PENG. PAS. BATU KALI 1 : 4
JADI JADI
PEMBESIAN
JADI
CEK CEK
CEK
PEK. BETON COR K225
PEK. SIARAN 1 : 2 TIMBUANAN & PDT
PEK. BETON COR K225 JADI
PEK. SIARAN 1 : 2 TIMBUNAN & PEMAD.
JADI JADI
CEK CEK
ANGKUTAN TANAH HASIL GALIAN TANAH
PLESTERAN 1 : 3
ANGKUTAN TANAH
JADI PLESTERAN 1 : 3
JADI
PEMBERSIHAN AKHIR
CEK PEMBERSIHAN JADI