JUMLAH HARGA
(Rp)
I
MATERIAL
1
Tiang besi 11 meter 200 daN
Btg
213
2
Isolator tumpu 20 kV
Bh
577
3
Isolator tarik 20 kV
Bh
174
4
Cut Out 20 kV + Fuse
Bh
3
5
Lighting Arester 20 kV
Bh
3
6
Konduktor AAAC 70 mm2
km
28,397
JUMLAH I
II ANGKUTAN
1
Tiang besi 11 meter 200 daN
btg
213
2
Isolator tumpu 20 kV
m3
8,251
3
Isolator tarik 20 kV
m3
4,019
4
Cut Out 20 kV + Fuse
m3
0,025
5
Lighting Arester 20 kV
m3
0,025
6
Konduktor AAAC 70 mm2
m3
5,679
JUMLAH II
TOTAL I + II
PPN 10 %
JUMLAH
DIBULATKAN
Terbilang ;
RENCANA ANGGARAN BIAYA (RAB)
PEMBANGUNAN JARINGAN TEGANGAN MENENGAH 20 kV
KABUPATEN TIMOR TENGAH UTARA
DESA TUNTUN, DESA JAK DAN DESA TUNOE KEC. MIOMAFO TIMUR
030.DL/611/LISDES.NTT/2015
NO
URAIAN
STN
VOL
HARGA SATUAN
JUMLAH HARGA
(Rp)
I MATERIAL
1. Trafo 3 P 50 KVA 20 KV - B2
Buah
3
-2. Cut Out 20 KV 100 A + Fuse Link
Bh
9
-3. L Arrester 20 KV 10 kA
Bh
9
JUMLAH I
II ANGKUTAN
1. Trafo 3 P 50 KVA 20 KV - B2
m3
2,078
2. Cut Out 20 KV 100 A + Fuse Link
m3
0,208
3. L Arrester 20 KV 10 kA
m3
0,075
JUMLAH II
TOTAL I + II
PPN 10 %
JUMLAH
DIBULATKAN
Terbilang ;
RENCANA ANGGARAN BIAYA (RAB)
PEMBANGUNAN GARDU TRAFO DISTRIBUSI 20 kV
KABUPATEN TIMOR TENGAH UTARA
DESA TUNTUN, DESA JAK DAN DESA TUNOE KEC. MIOMAFO TIMUR
030.DL/611/LISDES.NTT/2015
NO
URAIAN
STN
VOL
HARGA SATUAN
JUMLAH HARGA
(Rp)
I
MATERIAL
1
Tiang Besi 9 meter 100 daN
btg
71
2
LVTC 3 X 50+1X35 mm2
km
9,833
JUMLAH I
II ANGKUTAN
1
Tiang Besi 9 meter 100 daN
btg
71
2
LVTC 3 X 50+1X35 mm2
m3
11,799
JUMLAH II
TOTAL I + II
PPN 10 %
JUMLAH
DIBULATKAN
Terbilang ;
RENCANA ANGGARAN BIAYA (RAB)
PEMBANGUNAN JARINGAN TEGANGAN RENDAH (LVTC)
KABUPATEN TIMOR TENGAH UTARA
DESA TUNTUN, DESA JAK DAN DESA TUNOE KEC. MIOMAFO TIMUR
NO
JENIS MATERIAL
STN
VOL
HARGA SATUAN
(Rp)
030.DL/611/LISDES.NTT/2015
PAKET 014
A3C 70 mm2 =
9,280 kms
SA-
JUMLAH
NO.
JENIS MATERIAL
TU-
BAHAN
UPAH
BAHAN
UPAH
HARGA
AN
RP
RP
RP
RP
RP
I
MATERIAL UTAMA
1
Tiang besi 11 meter 200 daN
Btg
210
2
Isolator tumpu 20 kV
Bh
568
3
Isolator tarik 20 kV
Bh
174
4
Cut Out 20 kV + Fuse
Bh
3
5
Lighting Arester 20 kV
Bh
3
6
Konduktor AAAC 70 mm2
kms
9,28
II MATERIAL NON UTAMA
1
Perlengkapan druck schoor
set
29
2
Perlengkapan kontramast
set
6
3
Treck schoor
set
60
4
Cross Arm UNP 100 (Balance) :
a. Type A1
set
112
b. Type A2
set
32
c. Type A3
set
42
d. Type B3
set
-5
H. Type Conector 70 mm2
Bh
90
6
Alluminium Bending wire
Mtr
852,00
7
Joint sleeve 70 mm2
Bh
30
8
Penghalang panjat
Bh
49
9
Tanda kilat
Bh
175
10 Arde TM u/ Arrester
Set
1
11 Beton kaki tiang
Btg
210
III PEKERJAAN PERSIAPAN
1
Angkutan Material
m3
43,39
2
Angkutan Tiang Besi
Btg
210
3
Pembersihan Trase
Kms
9,28
IV PEKERJAAN FINISHING
1
Foto dokumentasi
Lbr
30
2
Gambar
Lbr
8
3
Pengecatan tiang
Btg
210
4
Komisioning
Kms
9,28
SUB. JUMLAH
Rp
PPN 10 %
Rp
JUMLAH
Rp
DIBULATKAN
Rp
VOLUME
HARGA SATUAN
HARGA BAGIAN
RENCANA ANGGARAN BIAYA (RAB)
PEMBANGUNAN JARINGAN TEGANGAN MENENGAH 20 kV
KABUPATEN TIMOR TENGAH UTARA
DESA TUNTUN, DESA JAK DAN DESA TUNOE KEC. MIOMAFO TIMUR
030.DL/611/LISDES.NTT/2015
PAKET 014
TRAFO 3 PHS 50 KVA =
3
BH
SA-
JUMLAH
NO.
JENIS MATERIAL
TU-
BAHAN
UPAH
BAHAN
UPAH
HARGA
AN
RP
RP
RP
RP
RP
I
MATERIAL UTAMA
1
Tiang besi 11 meter 200 daN
Btg
3
2
Isolator tumpu 20 kV
Bh
9
3
Cut Out 20 kV + Fuse
Bh
9
4
Lighting Arester 20 kV
Bh
9
5
Trafo 3 phs 50 kVA - 20 kV
Bh
3
II MATERIAL NON UTAMA
1
Penghalang panjat
Bh
3
2
Tanda kilat
Bh
3
3
Rangka Dudukan u/.trafo 3 phs
Set
3
4
Cross Arm type A1
Set
3
5
Cross Arm u/ dudukan CO
Set
3
6
Cross Arm u/ dudukan Arester
Set
3
7
LV Board 3 phs 1 tiang 2 Jurusan 2 Pintu
Set
3
8
Pipa Inlet-Outlet Medium B + Invoring
Set
3
9
Alluminium Bending wire
Mtr
13,50
10 Arde Gardu
Set
3
11 Arde TM u/ Arrester
Set
3
12 Pondasi Lantai Kerja
Bh
3
13 Paralel Grove 35 - 70 mm
Bh
18
14 Kabel NYY 50 mm2
mtr
288,00
15 Sepatu Kabel AL-CU 35-50 mm2
Bh
12
16 Sepatu Kabel CU 50 mm2
Bh
48
17 Beton kaki tiang
Btg
3
III PEKERJAAN PERSIAPAN
1
Pengedropan Material
m3
4,68
2
Pengedropan Tiang Besi
btg
3
IV PEKERJAAN FINISHING
1
Foto dokumentasi
Lbr
6
2
Penomoran Tiang
Btg
3
3
Penomoran Tiang
Btg
3
4 Komisioning
Bh
3
SUB. JUMLAH
Rp
PPN 10 %
Rp
JUMLAH
Rp
DIBULATKAN
Rp
RENCANA ANGGARAN BIAYA (RAB)
PEMBANGUNAN GARDU TRAFO DISTRIBUSI 20 kV
KABUPATEN TIMOR TENGAH UTARA
DESA TUNTUN, DESA JAK DAN DESA TUNOE KEC. MIOMAFO TIMUR
030.DL/611/LISDES.NTT/2015
VOLUME
PAKET 014
LVTC 3X50+1X35 MM2 =
9,640 KMS
SA-
JUMLAH
NO.
JENIS MATERIAL
TU-
BAHAN
UPAH
BAHAN
UPAH
HARGA
AN
RP
RP
RP
RP
RP
I
MATERIAL UTAMA
1
Tiang besi 9 mtr 100 daN
Btg
71
3
LVTC 3 x 50- + 1 x 35 mm2
km
9,64
II MATERIAL NON UTAMA
1
Perlengkapan druck schoor
Set
6
2
Perlengkapan kontramast
Set
-3
Treck schoor
Set
28
4
Beton kaki tiang
btg
71
ACCESSORIES LVTC :
5
Suspension Assembly
Set
129
6
Large Angle Assembly
Set
38
7
Fixed Dead End Assembly
Set
14
8
Adjustable Dead End Assembly
Set
14
9
Bundle End Protection
Set
14
10 Bimetalic Joint 50 mm2
Bh
16
11 Joint Sleves 50 mm2
Bh
40
12 Arde TR ( 5 ohm )
Set
20
13 Tap Conector
Bh
32
III PEKERJAAN PERSIAPAN
1
Pengedropan Material
m3
15,47
2
Pengedropan Tiang Besi
Btg
71
3
Pembersihan Trase
kms
9,64
IV PEKERJAAN FINISHING
1
Foto dokumentasi
Lbr
16
2
Gambar revisi
Lbr
8
3
Penomoran tiang
Btg
181
4
Pengecatan tiang
Btg
71
5
Komisioning
kms
9,64
SUB. JUMLAH
Rp
PPN 10 %
Rp
JUMLAH
Rp
DIBULATKAN
Rp
VOLUME
HARGA SATUAN
HARGA BAGIAN
RENCANA ANGGARAN BIAYA (RAB)
PEMBANGUNAN JARINGAN TEGANGAN RENDAH (LVTC)
KABUPATEN TIMOR TENGAH UTARA
DESA TUNTUN, DESA JAK DAN DESA TUNOE KEC. MIOMAFO TIMUR
030.DL/611/LISDES.NTT/2015
SATUAN KERJA LISTRIK PERDESAAN PROVINSI NUSA TENGGARA TIMUR
I
JARINGAN TEGANGAN MENENGAH
- PENGADAAN
- PEMASANGAN
II
GARDU DISTRIBUSI
3
150
- PENGADAAN
- PEMASANGAN
III
JARINGAN TEGANGAN RENDAH
- PENGADAAN
- PEMASANGAN
Terbilang :
KMS
9,640
KMS
BH/KVA
PT. PLN (PERSERO)REKAPITULASI
RENCANA ANGGARAN BIAYA (RAB)
PEMBANGUNAN JARINGAN DISTRIBUSI DAN GARDU
KABUPATEN TIMOR TENGAH UTARA
DESA TUNTUN, DESA JAK DAN DESA TUNOE KEC. MIOMAFO TIMUR
030.DL/611/LISDES.NTT/2015
NO
URAIAN
SATUAN
VOLUME
JUMLAH HARGA
RP
PT. PLN (Persero) UNIT PELAKSANA KONTRUKSI (UPK) SATKER LISTRIK PERDESAAN NTT
JUMLAH
URAIAN STN VOLUME HARGA
( Rp.) (Rp.)
1 Type A1 Balance UNP 100x50x5x2000
1 UNP 100x50x5x2000 mm Btg 1
2 Pole band 1/2, 4" (6x50) Bh 1 3 Pole band 2/2, 4" (6x50) set 1 4 Arm Tie ( Besi L. 50x4x1270 mm) btng 1
5 Steel plat type 2 bh 2
6 Bollt & nut 5/8 x 70 + ring (galvanis) Bh 5 7 Bollt & nut 5/8 x 140 + ring (galvanis) bh 2
Jumlah Pembulatan
2 Type A2 Balance UNP 100x50x5x2000
1 UNP 100x50x5x2000 mm Btg 2
2 Pole band 2/2, 4" (6x50) bh 2 3 Steel Plate typre I (6x100x37,5) bh 4 4 Steel Plate typre II (6x100x12) bh 4 5 Arm Tie ( Besi L. 50x4xx 1270 mm) btng 1 6 Bollt & nut 5/8 x 70 + ring (galvanis) Bh 3 7 Bollt & nut 5/8 x 140 + ring (galvanis) bh 14
Jumlah Pembulatan
3 Type A3 Balance UNP 100x50x5x2000
1 UNP 100x50x5x2000 mm btng 2
2 Pole band 2/2, 4" (6x50) bh 2 3 Steel Plate typre I (6x100x37,5) bh 4 4 Steel Plate typre II (6x100x12) bh 4 5 Arm Tie ( Besi L. 50x4xx 1270 mm) btng 1 6 Bollt & nut 5/8 x 70 + ring (galvanis) Bh 3 7 Bollt & nut 5/8 x 140 + ring (galvanis) bh 14
Jumlah Pembulatan
4 Type B3 Balance UNP 100x50x5x2200
1 UNP 10x50x5x2200 mm btng 2
2 Pole band 2/2, 4" (6x50) set 2 3 Steel Plate typre I (6x100x37,5) bh 6 4 Bollt & nut 5/8 x 140 + ring (galvanis) bh 12 5 Bollt & nut 5/8 x200 + 4 mur (galv) bh 4
Jumlah Pembulatan
5 Treck scoor - Guy Wire TM
1 Stall drad 64 mm2 mtr 15
2 Pole band 2/2, 4" (6x50) set 1 3 Bolt nut + Plat & spring plat 5/8" x 50 mm galv bh 2 4 Spanschroef 3/4" / Turn Bucle 50 KN bh 1 5 Guy isolator/tui isolator bh 1
6 Wire clip/cros by 35 mm2 bh 4
7 Stay road 16 mm2 panjang = 2500 mm (anker) btng 1 8 Cousen gegalv 64 mm2/guy wire thimble 70 mm2 Set 2
9 Beton Block 40x40x10 bh 1
10 U-Bolt 19mm with nut+plat 120x50x5 u/beton blok set 1
Jumlah Pembulatan
6 Kontramast - Horizontal Guy Wire
1 Stall drad 64 mm2 mtr 26
2 Pole band 2/2, 4" (6x50) set 2 3 Bolt nut + Plat & spring plat 5/8" x 50 mm galv bh 4 4 Spanschroef 3/4" / Turn Bucle 50 KN bh 2 5 Guy isolator/tui isolator bh 2
6 Wire clip/cros by 12 mm2 bh 6
7 Stay road 16 mm2 panjang = 2500 mm (anker) bh 1 8 Cousen gegalv 64 mm2/guy wire thimble 70 mm2 Set 4 9 Beton Block 40 cmx40 cmx10 cm bh 1 10 U-Bolt 19mm with nut+plat 120x50x5 u/beton blok set 1
Jumlah Pembulatan
ANALISA HARGA SATUAN MATERIAL AKSSESORIS
TAHUN 2015
HARGA SATUAN HARGA BAGIAN NO.
7 Druck Schoor TM
1 Pole band galvanise 1/2 4" bh 1 2 Pole band galvanise 2/2 4" (atas) bh 2 3 Pole band galvanise 2/2 8' (bawah) u/sekang bh 2 4 Pipa galvanise Diameter 2"- panajang 2000 mm btng 1 5 Besi UNP 100x50x5x200 mm u/stop druck btng 1 6 Bolt nut + plat & spring plat 5/8' x 50 mm galv bh 9
Jumlah Pembulatan
1 M2 CAT TIANG BESI
Cat dasar Kg 0,1 Minyak cat Ltr 0,05 Cat besi Kg 0,15 kuas Lbr 0,1 Pekerja HO 0,3 Mandor HO 0,125 Tukang HO 0,25 Jumlah Pembulatan 8 Pengecatan T. besi 9 mtr (1 batang) - Material m2/btg 2,814
Upah m2/btg 2,814
Jumlah Pembulatan
9 Pengecatan T. besi 11 mtr (1 batang) - Material m2/btg 4,691 Upah m2/btg 4,691 Jumlah Pembulatan 8 ARDE ARESTER 1 Grounding Rod 16 mm2 L = 1750 mm bh 2,00 2 BC 50 mm2 Mtr 15,00 3 Pipa Galvanis 1/2" L= 6000 mm Btg 1,00 4 Klem Steinless Steel 4 titik mtr 4,00 5 Connector CU 35 - 50 mm2 Buah 3,00 6 Stoping Bukle bh 4,00 7 Link 25 x 25 bh 4,00 Jumlah Pembulatan 9 ARDE GARDU 1 Grounding Rod 16 mm2 L = 1750 mm bh 1,00 2 BC 50 mm2 Mtr 11,00 3 Pipa Galvanis 1/2" L = 2000 mm bh 1,00 4 Klem Steinless Steel 4 titik mtr 4,00 5 Connector Cu 35 - 50 mm mm2 bh 2,00 6 Sepatu Kabel CU 50 mm2 bh 1,00 7 Stoping Bukle bh 4,00 8 Link bh 4,00 Jumlah Pembulatan
10 RANGKA DUDUKAN TRAFO 25-50 KVA (CANTOL) :
1 UNP 100 x 45x4x1500 mm galv Btg 2,00 2 UNP 100 x 45x4x750 mm galv Btg 2,00 3 UNP 100 x 45x4x 600mm galv btg 2,00 4 Arm tie galvanise 50x50x5 1000 mm btg 2,00 5 Arm tie galvanise 50x50x5 1200 mm btg 2,00 6 Bolt nut + plat & spring plat 5/8" 300 mm bh 2,00 7 Bolt nut + plat & spring plat 5/8" 50 mm bh 18,00 8 Pole band 1/2 6" u penahan dudukan trafo bh 4,00
Jumlah
Pembulatan
-11 TRAVERS UNTUK CUT OUT DAN ARRESTER :
1 UNP 100x50x5x2000 mm u/dudukan CO dan Arester btg 1,00 2 Pole band 1/2, 4" (6 X 70) bh 1,00 3 Bolt nut + plat & spring plat 5/8" 50 mm bh 2,00
Jumlah Pembulatan
12 BETON BLOCK UNTUK SCHOOR TARIK
1 Beton Cor : 1 ; 2 ; 3 (40cmx40 cm x10 cm) M3 0,0160 2 Besi Beton 16 mm2 Galvanis L=2500 mm btg 1,0000 3 U. Bolt 3/4" Buah 1,00
Jumlah
-13 LV Board ( Lemari bagi TR) 2 Jurusan 2 Pintu
1 LV Board ( Lemari bagi TR) 2 Jurusan 2 Pintu set 1,00 2 UNP 100 x 50x100 mm L 1000 mm galv btg 2,00 3 Pole band 1/2, 7" bh 2,00 4 Bolt nut + plat & spring plat 5/8" 50 mm bh 4,00
Jumlah
Pembulatan
14 Pipa Inlet / Oulet Gardu
1 Pipa 2" Galvanise btg 3,00 2 L - bow pipa PVC 2" u/ bagian atas bh 3,00 3 UNP 100 x 50 x 5 x 500 mm u/ dudukan pipa galv btng 2,00 4 Pole band 1/2 4" bh 2,00 5 Pole band 1/2 2" bh 6,00 6 Bolt nut + plat & spring plat 5/8" 50 mm bh 16,00
Jumlah Pembulatan
15 PONDASI COR BETON MANSET : 1 M3 COR BETON 1:2:3 :
1 Semen (PC) Zak 8,30
2 Kerikil Beton M3 0,83
3 Pasir Pasangan M3 0,54
4 Pekerja Org 6,00
5 Tukang Batu Org 1,00
6 Kepala Tukang Org 0,10
7 Mandor Org 0,30
Jumlah Pembulatan
8 Cor Kaki Tiang Besi 11 mtr 200 daN m3 0,118 9 Cor Kaki Tiang Besi 9 mtr 100 daN m3 0,093 10 Cor Lantai Kerja Gardu 120cm x 100 cm x 10 cm m3 0,269
Jumlah Pembulatan
16 1 M3 GALIAN TANAH BIASA SEDALAM 2 M :
1 Pekerja OH 0,667 2 Tukang Batu OH 0,333 3 Tukang Listrik OH 4 Mandor OH 0,333 Jumlah Pembulatan
17 1 M3 GALIAN BATU CADAS SEDALAM 2 M :
1 Pekerja OH 2,500 2 Tukang Batu OH 1,250 3 Tukang Listrik OH 4 Mandor OH 1,250 Jumlah Pembulatan 18 1 M3 URUGAN KEMBALI : 1 Pekerja OH 0,400 2 Tukang Batu OH -3 Kepala Tukang OH -4 Mandor OH 0,200 Jumlah Pembulatan 19 1 M3 PEMADATAN TANAH : 1 Pekerja OH 0,250 2 Tukang Batu OH 3 Kepala Tukang OH 4 Mandor OH 0,125 Jumlah Pembulatan
RATA2 GALIAN PER M3 NTT(1/2 CADAS+1/2 TANAH) m3 1,00 Volumer galian satu lubang tiang 11m 200 daN m3 0,45 Volumer galian satu lubang tiang 9m 100 daN m3 0,38 Mendirikan tiang 11 m 200 daN
Pekerja HO 0,50
Tukang Listrik HO 0,13
Mandor HO 0,13
Jumlah Pembulatan
Mendirikan tiang 9 m 100 daN
Pekerja HO 0,33
Tukang Listrik HO 0,08
Mandor HO 0,08
Jumlah Pembulatan
20 MENDIRIKAN TIANG 11 M 200 daN PERMANENT btg 1
21 MENDIRIKAN TIANG 9 M 100 daN PERMANENT btg 1
22 Alluminium Bending wire mtr 1
23 Joint sleeve 70 mm2 bh 1
24 Penghalang panjat bh 1
25 Tanda kilat Kecil bh 1
26 Tanda kilat Besar u. Gardu bh 1
27 Parel Grove 35-70 mm bh 1
28 Sepatu Kabel Cu 50 mm bh 1
PT. PLN (Persero) UNIT PELAKSANA KONTRUKSI (UPK) SATKER LISTRIK PERDESAAN NTT
JUMLAH
NO. URAIAN STN VOL HARGA
( Rp.) ( Rp.) (Rp.)
1 Suspension Assembly
1 Suspension Clamp bh 1
2 Pole Bracket bh 1
3 Stainless Steel Strip 20 x 0,7 mm mtr 1,75
4 Stopping bukle bh 2
5 Plastic strip bh 3
Jumlah Pembulatan
2 Large Angle Assembly
1 Strain Clamp 25 - 70 bh 2
2 Pole Bracket bh 1
3 Stainless Steel Strip 20 x 0,7 mm mtr 1,75
4 Stopping bukle bh 2
5 Plastic strip bh 3
Jumlah Pembulatan
3 Fixed Dead And Assembly
1 Strain Clamp 25 - 70 bh 1
2 Pole Bracket bh 1
3 Stainless Steel Strip 20 x 0,7 mm mtr 1,75
4 Stopping bukle bh 2
5 Plastic strip bh 2
Jumlah Pembulatan
4 Adjustable Dead And Assembly
1 Strain Clamp 25 - 70 bh 1
2 Pole Bracket bh 1
3 Stainless Steel Strip 20 x 0,7 mm mtr 1,75
4 Stopping bukle bh 2
5 Plastic strip bh 2
6 Turn Buckle/Span Scroef bh 1
Jumlah Pembulatan
5 Bundle Protection
1 Pipa PVC 2" 50 cm bh 1
2 Stainless Steel Strip 20 x 0,7 mm mtr 1,75
3 Stopping bukle Bh 2
4 Link Set 2
5 End cap Set 4
Jumlah Pembulatan
ANALISA HARGA SATUAN MATERIAL SUTR
TAHUN 2015
HARGA SATUAN
HARGA BAGIAN
PT. PLN (Persero) UNIT PELAKSANA KONTRUKSI (UPK) SATKER LISTRIK PERDESAAN NTT
JUMLAH
NO. URAIAN STN VOL HARGA
( Rp.) ( Rp.) (Rp.)
ANALISA HARGA SATUAN MATERIAL SUTR
TAHUN 2015
HARGA SATUAN
HARGA BAGIAN 6 Treck scoor - Guy Wire TR
1 Stall drad 35 mm2 mtr 11
2 Pole band 2/2" dia 4" (45 x 4 mm) bh 1
3 Mur Baut 5/8"-50 mm +Plat+Ring Plat bh 2
4 Spanschroef/ Turn Bucle 17 KN bh 1
5 Guy isolator/tui isolator dia 8 mm bh 1
6 Cousen gegalv 8 mm2 bh 2
7 Stay road 16 mm2 panjang = 1800 mm bh 1
8 Cros by 8 mm2 bh 4
9
Beton Block 40x40x10 dengan besi penguat 8 mm
bh 110
U bolt 16 mm + nut plat u. Beton block
bh 1Jumlah Pembulatan -7 Kontramast - Horizontal Guy Wire 1 Stall drad 35 mm2 mtr 26
2 Pole band 2/2, 4" (6x50) bh 2
3 Bolt nut + Plat & spring plat 5/8" x 50 mm galv bh 4
4 Spanschroef 3/4" / Turn Bucle 17 KN bh 2
5 Guy isolator/tui isolator bh 2
6 Wire clip/cros by 12 mm2 bh 8
7 Stay road 16 mm2 panjang = 2500 mm (anker) bh 1
8 Cousen gegalv 64 mm2/guy wire thimble 70 mm2 Set 4
9 Beton Block 40 cmx40 cmx10 cm bh 1
10 U bolt 16 mm + nut plat u. Beton block bh 1
Jumlah Pembulatan -8 Druck Schoor TR 1 Pole band galvanise 1/2 3" bh 1
2 Pole band galvanise 2/2 3" (atas) bh 2
3 Pole band galvanise 2/2 5' (bawah) u/sekang bh 2
4 Pipa galvanise Diameter 2"- panjang 1200 mm btng 1
5 Besi UNP 8 L=160 mm btng 1
6 Bolt nut + plat & spring plat 5/8' x 50 mm galv bh 9
Jumlah Pembulatan -9 GROUNDING TR 1 Grounding Rod 16 mm2 L = 1750 mm bh 1 2 BC 50 mm2 Mtr 10 3 Pipa Galvanis 1/2" L= 6000 mm Btg 1
4 Klem Steinless Steel 4 titik 3 titik mtr 4
5 AL/CU 35 - 50 mm2 bh 1 6 Electroda clam cu bh 1 7 Stoping bukle bh 4 8 Link 25 x 25 bh 4 Jumlah -Pembulatan -10 Tap Connector 25 - 50 mm2 bh 1