PEKERJAAN : PEMBANGUNAN 3 UNIT LABORATORIUM MAN PATAS
LOKASI : DI DESA PATAS, KEC. GEROKGAK, KABUPATEN BULELENG
TAHUN : 2017
JUMLAH HARGA
( Rp )
I PEKERJAAN PONDASI DAN SLOOF 8,620,925.25 II PEKERJAAN DINDING DAN BETON 82,293,262.50 III PEKERJAAN ATAP DAN ACC 26,029,500.00 IV PEKERJAAN KUSEN, PINTU, JENDELA DAN ACC 38,404,260.00 V PEKERJAAN LANTAI DAN PLAFOND 104,438,472.80 VI PEKERJAAN INSTALASI LISTRIK DAN AIR 17,053,055.45 VII PEKERJAAN FINISHING 62,879,479.20
REAL COST 339,718,955.20 PPN 10% 33,971,895.52 TOTAL COST 373,690,850.72 DIBULATKAN 373,690,000.00
Biaya Fisik 373,690,000.00 Biaya Perencanaan 30,754,687.00 Biaya Pengawasan 19,992,415.00 AP 52,316,600.00 Total Biaya Perbangunan 476,753,702.00 Dikalikan 3 Bangunan 1,430,261,106.00 Dibulatkan 1,430,261,000.00