Tugas RAB Rumah 2 Lantai

N/A
N/A
Protected

Academic year: 2021

Membagikan "Tugas RAB Rumah 2 Lantai"

Copied!
60
0
0

Teks penuh

(1)

NO

URAIAN PEKERJAAN

A

P E R S I A P A N

B

PEKERJAAN GALIAN

C

PEKERJAAN PONDASI

D

PEKERJAAN BETON BERTULANG

E

PEKERJAAN DINDING

F

PEKERJAAN KUSEN

G

PEKERJAAN PLAFOND

H

PEKERJAAN LANTAI

I

PEKERJAAN ATAP

J

PEKERJAAN PENGECATAN

K

PEKERJAAN TANGGA

L

PEKERJAAN INSTALASI LISTRIK

M

SANITER & INSTALASI AB / AK

N

PEKERJAAN LUAR

DIBULATKAN

PPN 10%

JUMLAH TOTAL

REKAPITULASI RENCANA ANGGARAN BIAYA

PROYEK : RENOVASI KAMAR TIDUR

LOKASI : GARUT

JUMLAH

JASA PENGAWASAN 5%

(2)

SK-GUB

JUMLAH

9,960,923.50

9,229,343.54

127,183,226.58

#VALUE!

151,946,945.90

75,552,231.67

56,368,054.07

77,784,008.57

165,652,929.16

50,311,974.09

7,298,229.15

8,716,994.00

85,155,988.34

11,583,444.98

#VALUE!

#VALUE!

#VALUE!

#VALUE!

#VALUE!

#VALUE!

REKAPITULASI RENCANA ANGGARAN BIAYA

PROYEK : RENOVASI KAMAR TIDUR

LOKASI : GARUT

(3)

RENCANA ANGGARAN BIAYA

LOKASI : GARUT

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN

A P E R S I A P A N

1 Pek. Pengukuran M1 440.00 695.75

2 Pek. Pembersihan Lahan M2 440.00 2,997.50

3 Pek. Pembuatan Kantor Direksi M2 1.00 973,456.00

4 Pek. Pembuatan Gudang Proyek M2 1.00 577,604.50

5 Pek. Pengaman Proyek M2 22.00 119,955.00

6 Pek. PemasanganPapan Nama Proyek LS 1.00 119,955.00

7 Pek. Pemasangan Papan Bouwplank M1 70.00 57,512.40

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN

B PEKERJAAN GALIAN

1 Galian Tanah Max 1M M3 239.62 25,080.00

2 Pek. Urugan Tanah Kembali M3 104.296 12,591.70

3 Pemadatan Tanah M3 106.00 17,985.00

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN

C PEKERJAAN PONDASI

1 Urugan Pasir M3 11.62 197,065.00

2 Pas. Batu Kosong (Aanstamping) M3 20.80 417,642.50

3 Pondasi Batu Kali 1 Pc : 2 Ps M3 66.035 762,569.50

4 Pondasi Plat Beton (Penulangan 150 Kg + Bekisting) M3 0.46 3,025,522.50 5 Pondasi Borpile (Penulangan 150 Kg + Bekisting) M3 20.0000 3,222,917.50

PROYEK : RENOVASI KAMAR TIDUR

Sub Jumlah Pekerjaan Persiapan

Sub Jumlah Pekerjaan Pondasi Sub Jumlah Pekerjaan Plafond

(4)

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN D PEKERJAAN BETON BERTULANG

1 Sloof 15/25 ( 200 Kg Besi + Bekisting ) M3 7.80 3,854,523.75

2 Kolom Beton 15/40 ( 99.6267 Kg Besi + Bekisting ) M3 4.62 #VALUE!

3 Kolom Beton 15/25 ( 91.334 Kg Besi + Bekisting ) M3 0.3938 2,890,197.75 4 Kolom Praktis 15/15 ( 211.5556 Kg Besi + Bekisting ) M3 3.7575 4,212,635.35 5 Balok Beton 50/30 ( 250 Kg Besi + Bekisting ) M3 20.625 4,819,553.75 6 Balok Beton 18/10 ( 217 Kg Besi + Bekisting ) M3 1.1353 4,464,473.75

7 Plat Lantai T 12 M3 24.6261 21,227,952.85

8 Plat Lantai T 10 M3 3.53 21,606,544.25

9 Ring Balok Beton 15/25 M3 5.826 21,606,544.25

10 Balok Ampig 15/25 M3 1.6389 2,954,800.75

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN

E PEKERJAAN DINDING

1 Dinding Bata Merah M2 778.3175 165,685.30

2 Plesteran + Acian Dinding M2 369.516 40,925.50

3 Keramik Dinding Toilet M2 59.10 133,139.60

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN

F PEKERJAAN KUSEN

1 Kusen Pintu & Jendela M3 3.371215 13,103,117.50

2 Daun Pintu Biasa Unit 11.00 957,951.50

3 Kusen Pintu Toilet Unit 4.00 520,025.00

4 Daun Pintu Toilet Unit 4.00 520,025.00

5 Daun Jendela Kaca Unit 0.20318 576,906.00

6 Kassa Nyamuk Lobang Angin Bh 2.00 56,874.13

7 Kaca Bening 5 mm M2 48.9983 169,845.50

8 Kaca Bening 3 mm M2 0.9075 75,267.50

9 Kunci Pintu Biasa Set 11.00 219,103.50

10 Kunci Pintu Toilet Set 4.00 218,176.75

Sub Jumlah Pekerjaan Dinding Sub Jumlah Pekerjaan Beton Bertulang

(5)

11 Engsel Pintu Bh 11.00 190,799.13

12 Engsel Jendela Bh 10.00 16,722.75

13 Slot Pintu Bh 11.00 83,165.50

14 Slot Jendela Bh 20.00 44,665.50

15 Hak Angin Jendela Bh 10.00 70,273.50

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN

G PEKERJAAN PLAFOND

1 Rangka Hollow M2 232.8875 173,181.25

2 Penutup Plafond Gypsum M2 167.3875 50,818.90

3 Penutup Plafond GRC M2 59.25 45,613.70

4 List Plafond Gypsum M1 179.21 26,936.25

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN

H PEKERJAAN LANTAI 1 Keramik 40/40 M2 315.129 171,158.63 2 Kerami 30/30 M2 10.00 165,404.25 3 Keramik 20/20 M2 55.18 74,302.25 4 Plin Lantai 10/40 M1 231.11 72,630.25 5 Plin Lantai 10/30 M1 18.00 72,630.25

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN

I PEKERJAAN ATAP

1 Kuda - Kuda Rangka Atap Baja Ringan M2 210.7138 93,225.00

2 Penutup Atap Genteng Beton M2 210.7138 684,189.00

3 Bubungan Genteng Beton M2 33.58 5,376.30

4 Papan List Plank M2 60.10 6,186.50

5 Talang M1 17.963 71,743.38

Sub Jumlah Pekerjaan Kusen

Sub Jumlah Pekerjaan Plafond

Sub Jumlah Pekerjaan Lantai

(6)

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN J PEKERJAAN PENGECATAN

1 Cat Dinding M2 1,311.235 11,745.80

2 Cat Kusen Pintu & Jendela 3 Sisi - Sisi M1 59.2205 42,176.75 3 Cat Kusen Pintu & Jendela 4 Sisi - Sisi M1 24.984 42,176.75

4 Cat daun jendela M1 60.2208 42,176.75

5 Cat Plafond M2 473.424 28,270.00

6 Cat List Plafond M1 179.21 28,270.00

7 Cat Plasing Papan list plank M1 60.10 42,176.75

8 Cat Railling Tangga & Balkon M1 40.00 39,917.90

9 Cat Railling Pagar Besi M1 7.08 39,917.90

10 Cat Bubungan M1 33.58 177,336.50

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN

K PEKERJAAN TANGGA

1 Bekisting Tangga M3 204,622.00 2 Coran Beton Bertulang M3 4,273,555.00

3 Keramik Tangga 40/40 M2 11.7075 166,414.88

4 Handrailling Tangga M1 23.21 186,862.50

5 Stairnosing M1 21.0000 48,230.88

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN

L PEKERJAAN INSTALASI LISTRIK

1 Panel Unit 1.00 484,000.00

2 Titik Lampu Gantung Ttk 2.00 242,000.00

3 Titik Lampu TL Ttk 6.00 41,140.00

4 Titik Lampu Elektrik Ttk 9.00 18,150.00

5 Titik Lampu Dinding Ttk 8.00 27,285.50

6 Titik Lampu SL Ttk 7.00 65,340.00

7 Titik Lampu Down Light Ttk 46.00 102,850.00

Sub Jumlah Pekerjaan Pengecatan

(7)

8 Titik Lampu Baret Ttk 5.00 17,600.00

9 Titik Lampu Taman Ttk 5.00 242,000.00

10 Stop Kontak Ttk 11.00 8,470.00

11 Saklar Tunggal Bh 8.00 12,584.00

12 Saklar Double Bh 14.00 17,182.00

13 Outlet Telepon Ttk 3.00 42,350.00

14 Outlet TV Ttk 2.00 36,300.00

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN

M SANITER & INSTALASI AB / AK

1 Kloset Duduk ( Lengkap ) Bh 3.00 1,259,687.00

2 Kloset Jongkok Bh 2.00 698,087.50

3 Washtafel ( Lengkap ) Bh 3.00 2,458,568.75

4 Bak Cuci Piring Bh 1.00 356,765.75

5 Jet Shower Bh 3.00 832,592.75

6 Bak Fiber Bh 1.00 373,560.00

7 Kran Dinding Bh 4.00 172,592.75

8 Kran Cuci Piring Bh 1.00 4,957,592.75

9 Tangki Air 500 Ltr Bh 3.00 282,592.75 10 Pompa Bh 1.00 62,262.75 11 Roof Drain Bh 16.00 62,262.75 12 Pipa PVC Ǿ 1" M1 114.15 24,083.40 13 Pipa PVC Ǿ 3" M1 119.75 101,339.98 14 Pipa PVC Ǿ 4" M1 46.43 169,061.48

15 Septik tank Unit 1.00 11,818,213.00

16 Bak Kontrol Unit 3.00 9,090,137.98

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN

N PEKERJAAN LUAR

1 Pasang Pagar M1 7.08 48,240.50

2 Carport M2 22.4154

-Sub Jumlah Pekerjaan Instalasi Sub Jumlah Pekerjaan Instalasi Listrik

(8)

3 Taman M2 60.2240 121,000.00

4 Paving Block M2 53.4434 73,999.75

(9)

JUMLAH 306,130.00 1,318,900.00 973,456.00 577,604.50 2,639,010.00 119,955.00 4,025,868.00 9,960,923.50 JUMLAH 6,009,669.60 1,313,263.94 1,906,410.00 9,229,343.54 JUMLAH 2,289,895.30 8,686,964.00 50,356,276.93 1,391,740.35 64,458,350.00 127,183,226.58

(10)

JUMLAH 30,065,285.25 #VALUE! 1,138,015.36 15,828,977.33 99,403,296.09 5,068,338.47 522,761,689.56 76,271,101.18 125,879,726.77 4,842,622.95 #VALUE! JUMLAH 128,955,768.48 15,122,627.06 7,868,550.36 151,946,945.90 JUMLAH 44,173,426.26 10,537,466.50 2,080,100.00 2,080,100.00 117,215.76 113,748.25 8,322,140.76 68,305.26 2,410,138.50 872,707.00

(11)

2,098,790.38 167,227.50 914,820.50 893,310.00 702,735.00 75,552,231.67 JUMLAH 40,331,748.36 8,506,448.62 2,702,611.73 4,827,245.36 56,368,054.07 JUMLAH 53,937,046.34 1,654,042.50 4,099,998.16 16,785,577.08 1,307,344.50 77,784,008.57 JUMLAH 19,643,794.01 144,168,064.11 180,536.15 371,808.65 1,288,726.25 165,652,929.16

(12)

JUMLAH 15,401,504.06 2,497,728.22 1,053,743.92 2,539,917.63 13,383,696.48 5,066,266.70 2,534,822.68 1,596,716.00 282,618.73 5,954,959.67 50,311,974.09 JUMLAH 1,948,302.15 4,337,078.63 1,012,848.38 7,298,229.15 JUMLAH 484,000.00 484,000.00 246,840.00 163,350.00 218,284.00 457,380.00 4,731,100.00

(13)

88,000.00 1,210,000.00 93,170.00 100,672.00 240,548.00 127,050.00 72,600.00 8,716,994.00 JUMLAH 3,779,061.00 1,396,175.00 7,375,706.25 356,765.75 2,497,778.25 373,560.00 690,371.00 4,957,592.75 847,778.25 62,262.75 996,204.00 2,749,120.11 12,135,462.01 7,849,524.28 11,818,213.00 27,270,413.94 85,155,988.34 JUMLAH 341,542.74

(14)

7,287,104.00 3,954,798.24 11,583,444.98

(15)

PROYEK : RUMAH TINGGLAN 2 LANTAI

URAIAN PEKERJAAN

HARGA

PERSIAPAN

A 1

1 M1 PEKERJAAN PENGUKURAN

695.75

A 2

1 M2 PEKERJAAN PEMBERSIHAN LAHAN

2,997.50

A 3

1 M2 PEMBUATAN KANTOR DIREKSI

973,456.00

A 4

1 M2 PEMBUATAN GUDANG PROYEK

577,604.50

A 5

1 M1 PEKERJAAN PENGAMAN PROYEK

119,955.00

A 6

1 UNIT PEKERJAAN PEMASANGAN PAPAN NAMA PROYEK

119,955.00

A 7

1 M1 PEKERJAAN PEMASANGAN PAPAN BOWPLANK

57,512.40

PEKERJAAN GALIAN TANAH

B 1

1 M3 GALIAN TANAH MAX 1 M

25,080.00

B 2

1 M3 PEKERJAAN URUGAN TANAH KEMBALI

12,591.70

B 3

1 M3 PEMADATAN TANAH

17,985.00

PEKERJAAN PONDASI

C 1

1 M3 URUGAN PASIR

197,065.00

C 2

1 M3 PASANG PONDASI BATU KOSONG (AANSTAMPING)

417,642.50

C 3

1 M3 PONDASI BATU KALI 1 Pc : 2 Ps

762,569.50

C 4

1 M3 MEMBUAT PONDASI PLAT BETON (PENULANGAN 150 Kg + BEKISTING)

3,025,522.50

C 5

1 M3 MEMBUAT PONDASI BETON BORPILE (PENULANGAN 150 Kg + BEKISTING)

3,222,917.50

PEKERJAAN STRUKTUR

D 1

1 M3 MEMBUAT SLOOF 15/25 BETON BERTULANG ( 200 Kg BESI + BEKISTING )

3,854,523.75

D 2

1 M3 MEMBUAT KOLOM BETON BERTULANG 15/40 ( 99.6267 Kg BESI + BEKISTING )

#VALUE!

D 3

1 M3 MEMBUAT KOLOM BETON BERTULANG 15/25 ( 91.334 Kg BESI + BEKISTING )

2,890,197.75

D 4

1 M3 MEMBUAT KOLOM BETON BERTULANG 15/15 ( 211.5556 Kg BESI + BEKISTING )

4,212,635.35

D 5

1 M3 MEMBUAT BALOK BETON BERTULANG 30/50 ( 250 Kg BESI + BEKISTING )

4,819,553.75

D 6

1 M3 MEMBUAT BALOK BETON BERTULANG 18/10 ( 217 Kg BESI + BEKISTING )

4,464,473.75

D 7

1 M3 MEMBUAT PLAT LANTAI Tb.12 cm BETON BERTULANG

21,227,952.85

D 8

1 M3 MEMBUAT PLAT LANTAI Tb.10 cm BETON BERTULANG

21,606,544.25

D 9

1 M3 MEMBUAT RING BALK BETON BERTULANG ( 175 Kg BESI + BEKISTING )

3,705,143.75

D 10

1 M3 MEMBUAT BALOK AMPIG BETON BERTULANG ( 175 Kg BESI + BEKISTING )

2,954,800.75

C

REKAPITULASI DAFTAR ANALISA

LOKASI : GARUT

NO.

B

A

(16)

PEKERJAAN DINDING

E 1

1 M2 PASANG BATA MERAH 1/2 BATA, CAMPURAN 1 PC : 2 PS

165,685.30

E 2

1 M2 PASANGAN PLESTERAN CAMPURAN 1 PC : 2 PS Tebal 2 cm + ACIAN

40,925.50

E 3

1 M2 PASANG DINDING KERAMIK UKURAN 20 X 20 cm

133,139.60

PEKERJAAN KUSEN

F 1

1 M2 PASANG KUSEN PINTU DAN JENDELA KAYU JATI

13,103,117.50

F 2

1 UNIT PASANG DAUN PINTU

957,951.50

3

1 UNIT PASANG KUSEN PINTU TOILET

520,025.00

F 4

1 UNIT PASANG DAUN PINTU TOILET

520,025.00

F 5

1 UNIT DAUN JENDELA KACA

576,906.00

F 6

1 BUAH PASANG KAIT ANGIN

56,874.13

F 7

1 M2 PASANG KACA, TEBAL 5 MM

169,845.50

F 8

1 M2 PASANG KACA, TEBAL 3 MM

75,267.50

F 9

1 BUAH PASANG KUNCI TANAM STANDAR

219,103.50

F 10

1 BUAH PASANG KUNCI TANAM KAMAR MANDI

218,176.75

F 11

1 BUAH PASANG ENGSEL PINTU

190,799.13

F 12

1 BUAH PASANG ENGSEL JENDELA KUPU - KUPU

16,722.75

F 13

1 UNIT PASANG KUNCI SELOT PINTU

83,165.50

F 14

1 UNIT PASANG KUNCI SELOT JENDELA

44,665.50

F 15

1 BUAH PASANG HAK ANGIN JENDELA

70,273.50

PEKERJAAN PLAFOND

G 1

1 M2 PASANG RANGKA PLAFOND BESI HOLLOW

173,181.25

G 2

1 M2 PASANG PLAFOND GYPSUM BOARD, TEBAL 9 MM + RANGKA BESI HOLLOW

50,818.90

G 3

1 M2 PASANG PLAFOND GRC ( 60 X 1,2 ) M, TEBAL 6 MM

45,613.70

G 4

1 M1 PASANG LIST PLAFOND PROFIL GYPSUM

26,936.25

PEKERJAAN KERAMIK

H 1

1 M2 PASANG LANTAI KERAMIK UKURAN 40 X 40 cm

171,158.63

H 2

1 M2 PASANG LANTAI KERAMIK UKURAN 20 X 20 cm

74,302.25

H 3

1 M2 PASANG KERAMIK UKURAN 30 X 30

165,404.25

H 4

1 M2 PASANG PLIN KERAMIK UKURAN 10 X 40

72,630.25

PEKERJAAN ATAP

I 1

1 M3 PASANG RANGKA ATAP BAJA RINGAN

93,225.00

I 2

1 M2 PEKERJAAN PENUTUP ATAP GENTENG BETON

684,189.00

I 3

1 M2 PEKERJAAN BUBUNGAN ATAP GENTENG BETON

5,376.30

I

E

F

G

(17)

I 4

1 M2 PASANG LIST PLANG UKURAN ( 3 x 20 ) cm, Kayu Jati

6,186.50

I 5

1 M2 PASANG TALANG DATAR

71,743.38

PEKERJAAN PENGECATAN

J 1

1 M2 PENGECATAN DINDING SEKELAS VINILEX (3 x )

11,745.80

J 2

1 M2 PENGECATAN BIDANG KAYU (3X) BERIKUT MENI

42,176.75

J 3

1 M2 PENGECATAN PLAFOND SEKELAS VINILEX (3X) LUAR

28,270.00

J 4

1 M2 PENGECATAN BESI (3X)

39,917.90

J 5

1 M2 PENGECATAN GENTENG (3X)

177,336.50

K

PEKERJAAN TANGGA

K 1

1 M2 PASANG BEKISTING UNTUK TANGGA

204,622.00

K 2

1 M3 MEMBUAT BETON BERTULANG DENGAN MUTU K 275

4,273,555.00

K 3

1 M2 PASANG LANTAI KERAMIK TANGGA UKURAN 40 X 40 cm

166,414.88

K 4

1 M1 PASANG HANDRAILING TANGGA

186,862.50

K 5

1 M1 PASANG STAIRNOSING

48,230.88

PEKERJAAN LISTRIK

L 1

PASANG LAMPU GANTUNG

242,000.00

L 2

PASANG LAMPU TL

41,140.00

L 3

PASANG LAMPU ELEKTRIK

18,150.00

L 4

PASANG LAMPU DINDING

27,285.50

L 5

PASANG LAMPU SL

65,340.00

L 6

PASANG LAMPU DOWN LIGHT

102,850.00

L 7

PASANG LAMPU BARET

17,600.00

L 8

PASANG LAMPU TAMAN

242,000.00

L 9

PASANG STOP KONTAK

8,470.00

L 10

PASANG SAKLAR TUNGGAL

12,584.00

L 11

PASANG SAKLAR GANDA

17,182.00

L 12

PASANG OUTLET TELEPON

42,350.00

L 13

PASANG OUTLET TV

36,300.00

PEKERJAAN SANITAIR & INSTALASI AB /AK

M 1

MEMASANG 1 BUAH KLOSET DUDUK

1,259,687.00

M 2

MEMASANG 1 BUAH KLOSET JONGKOK PORSELEN

698,087.50

M 3

MEMASANG 1 BUAH WASHTAFEL

2,458,568.75

M 4

MEMASANG 1 BUAH BAK CUCI PIRING

356,765.75

M 5

MEMASANG 1 BUAH JET SHOWER

832,592.75

J

L

(18)

M 6

MEMASANG 1 BUAH BAK MANDI FIBERGLASS VOLUME 0,3 M3

373,560.00

M 7

MEMASANG 1 BUAH KRAN DINDING DIAMETER 0,75" ATAU 0,5"

172,592.75

M 8

MEMASANG 1 BUAH KRAN BAK CUCI PIRING DIAMETER 0,75" ATAU 0,5"

4,957,592.75

M 9

MEMASANG 1 BUAH TANGKI AIR

282,592.75

M 10

MEMASANG 1 BUAH POMPA

62,262.75

M 11

MEMASANG 1 BUAH ROOF DRAIN

62,262.75

M 12

PASANG 1 M1 PIPA PVC TIPE AW DIAMETER 1"

24,083.40

M 13

PASANG 1 M1 PIPA PVC TIPE AW DIAMETER 3"

101,339.98

M 14

PASANG 1 M1 PIPA PVC TIPE AW DIAMETER 4"

169,061.48

M 15

1 UNIT SEPTICTANK + REMBESANNYA

11,818,213.00

M 16

1 UNIT BAK KONTROL PASANGAN BATU BATA UKURAN ( 60X60 ) TINGGI 65 CM

9,090,137.98

N

PEKERJAAN LUAR

N 1

PASANG 1 M1 PAGAR

48,240.50

N 2

PASANG 1 M2 CARPORT

-N 3

PASANG 1 M2 TAMAN

121,000.00

(19)

SATUAN

M1

M2

M2

M2

M1

LS

M1

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

REKAPITULASI DAFTAR ANALISA

LOKASI : GARUT

(20)

M2

M2

M2

M2

UNIT

UNIT

UNIT

BH

M2

M2

BH

BH

BH

BH

UNIT

UNIT

BH

M2

M2

M2

M1

M2

M2

M2

M3

M2

M2

(21)

M2

M2

M2

M2

M2

M2

M1

M2

M3

M2

M1

M1

BH

BH

BH

BH

BH

BH

BH

BH

BH

BH

BH

BH

BH

BH

BH

BH

BH

BH

(22)

BH

BH

BH

BH

BH

BH

M1

M1

M1

UNIT

UNIT

M1

M2

M2

M2

(23)

PROYEK : RUMAH TINGGLAN 2 LANTAI

KOEF. SAT. HARGA SAT. UPAH SAT. JUMLAH A 1

Pekerja 0.0200 Org 46,000.00 920.00 Tukang Batu 0.0100 Org 63,250.00 632.50 632.50 0.10 63.25 695.75 A 2 1 M2 PEKERJAAN PEMBERSIHAN LAHAN

Pekerja 0.0500 Org 46,000.00 2,300.00 Mandor 0.0050 Org 85,000.00 425.00 2,725.00 0.10 272.50 2,997.50 A 3 1 M2 PEMBUATAN KANTOR DIREKSI

Kayu Kaso5/7 borneo 0.1000 M3 3,400,000.00 340,000.00 Paku Semua Ukuran 0.2500 Kg 56,500.00 14,125.00 Semen PC ( abu - abu ) 0.1000 Zak 70,000.00 7,000.00 Pasir Pasang 0.2500 M3 210,000.00 52,500.00 Bata Merah 30.0000 Bh 800.00 24,000.00 Seng Plat BJLS 32 1.1000 M2 35,000.00 38,500.00 Kawat Harmonika 4 cm 2.0000 M2 30,000.00 60,000.00 Kaca Polos 3 mm 0.0800 M2 52,000.00 4,160.00 Kunci Tanam Standar 0.1500 M2 165,000.00 24,750.00 Triplek 120 x 240 x 0.4 cm 0.5000 Lbr 165,000.00 82,500.00 Pekerja 2.0000 Org 46,000.00 92,000.00 Tukang Kayu 1.0000 Org 65,000.00 65,000.00 Kepala Tukang 1.0000 Org 80,000.00 80,000.00 Mandor 0.0050 Org 85,000.00 425.00

DAFTAR ANALISA

Jumlah Jumlah

LOKASI : GARUT

NO. URAIAN Jumlah A.PEKERJAAN PERSIAPAN Keuntungan MAX. 10% 1 M1 PEKERJAAN PENGUKURAN Keuntungan MAX. 10% Jumlah

(24)

884,960.00 0.10 88,496.00 973,456.00

A 4 1 M2 PEMBUATAN GUDANG PROYEK

Kayu Kaso5/7 borneo 0.0200 M3 4,700,000.00 94,000.00 Papan Kayu terentang 0.1000 M3 1,400,000.00 140,000.00 Paku Semua Ukuran 0.3000 Kg 56,500.00 16,950.00 Semen PC ( abu - abu ) 0.2100 Sak 70,000.00 14,700.00 Pasir Beton 0.0300 M3 220,000.00 6,600.00 Split (Batu Pecah) 0.0500 M3 170,000.00 8,500.00 Seng Gelombang 180 x 90 x 0.05 1.2000 Lbr 44,100.00 52,920.00 Pekerja 1.0000 Org 46,000.00 46,000.00 Tukang Kayu 1.0000 Org 65,000.00 65,000.00 Kepala Tukang 1.0000 Org 80,000.00 80,000.00 Mandor 0.0050 Org 85,000.00 425.00 525,095.00 0.10 52,509.50 577,604.50

A 5 1 M1 PEKERJAAN PENGAMAN PROYEK

Tiang Kayu Borneo 5/6 0.0360 M3 2,900,000.00 104,400.00 Seng Gbl BJLS 1.4300 Lbr 44,100.00 63,063.00 Paku 5 - 10 cm 0.0200 Kg 17,500.00 350.00 Pekerja 0.1000 Org 46,000.00 4,600.00 Tukang Kayu 0.2000 Org 65,000.00 13,000.00 Kepala Tukang 0.2000 Org 80,000.00 16,000.00 Mandor 0.0050 Org 85,000.00 425.00 201,838.00 0.10 20,183.80 222,021.80

A 6 1 UNIT PEKERJAAN PEMASANGAN PAPAN NAMA PROYEK

Kayu Albasiah , Balok 0.0420 M3 1,400,000.00 58,800.00 Paku 4 - 7 cm 0.2500 ORG 18,000.00 4,500.00 Pengecatan Kayu 1.0000 Ls 40,000.00 40,000.00 Jumlah Keuntungan MAX. 10% Jumlah Jumlah Keuntungan MAX. 10% Jumlah Jumlah Keuntungan MAX. 10% Jumlah

(25)

Ongkos Pasang 0.1250 Org 46,000.00 5,750.00 109,050.00 0.10 10,905.00 119,955.00

A 7 1 M1 PEKERJAAN PEMASANGAN PAPAN BOWPLANK

Kayu Kaso5/7 Albasiah 0.0100 M3 2,227,500.00 22,275.00 Paku 5 - 10 cm 0.0380 Kg 18,000.00 684.00 Kayu Papan 3/20 Kayu Albasiah 0.0070 M3 1,400,000.00 9,800.00 Pekerja 0.1000 Org 46,000.00 4,600.00 Tukang Kayu 0.1000 Org 65,000.00 6,500.00 Kepala Tukang 0.1000 Org 80,000.00 8,000.00 Mandor 0.0050 Org 85,000.00 425.00 52,284.00 0.10 5,228.40 57,512.40

B 1 1 M3 GALIAN TANAH MAX 1 M

Pekerja 0.4000 Org 46,000.00 18,400.00 Tukang Gali 0.0200 Org 50,000.00 1,000.00 Mandor 0.0400 Org 85,000.00 3,400.00 22,800.00 0.10 2,280.00 25,080.00

B 2 1 M3 PEKERJAAN URUGAN TANAH KEMBALI

Pekerja 0.1920 Org 46,000.00 8,832.00 Tukang Gali 0.0200 Org 50,000.00 1,000.00 Mandor 0.0190 Org 85,000.00 1,615.00 11,447.00 0.10 1,144.70 12,591.70 B 3 1 M3 PEMADATAN TANAH Pekerja 0.3000 Org 46,000.00 13,800.00 Mandor 0.0300 Org 85,000.00 2,550.00 B. PEKERJAAN GALIAN TANAH

Jumlah Keuntungan MAX. 10% Jumlah Keuntungan MAX. 10% Jumlah Jumlah Jumlah Jumlah Keuntungan MAX. 10% Jumlah Jumlah Keuntungan MAX. 10%

(26)

16,350.00 0.10 1,635.00 17,985.00 C 1 1 M3 URUGAN PASIR Pasir Urug 1.2000 M2 140,000.00 168,000.00 Pekerja 0.1500 Org 46,000.00 6,900.00 Mandor 0.0500 Org 85,000.00 4,250.00 179,150.00 0.10 17,915.00 197,065.00

C 2 1 M3 PASANG PONDASI BATU KOSONG (AANSTAMPING)

Batu Belah 1.2000 M3 170,000.00 204,000.00 Pasir Urug 0.4000 M3 140,000.00 56,000.00 Pekerja 1.5000 Org 46,000.00 69,000.00 Tukang Batu 1/2 Terampil 0.7500 Org 57,500.00 43,125.00 Kepala Tukang 0.0100 Org 75,000.00 750.00 Mandor 0.0800 Org 85,000.00 6,800.00 379,675.00 0.10 37,967.50 417,642.50

C 3 1 M3 PONDASI BATU KALI 1 Pc : 2 Ps

Batu Belah 1.2000 M3 170,000.00 204,000.00 Semen PC ( abu - abu ) 2.1600 Zak 70,000.00 151,200.00 Pasir Pasang 0.4270 M3 210,000.00 89,670.00 Pekerja 3.0000 Org 46,000.00 138,000.00 Tukang Batu Terampil 1.5000 Org 63,250.00 94,875.00 Kepala Tukang Batu 0.1500 Org 75,000.00 11,250.00 Mandor 0.0500 Org 85,000.00 4,250.00 693,245.00 0.10 69,324.50 762,569.50

C 4 1 M3 MEMBUAT PONDASI PLAT BETON (PENULANGAN 150 Kg + BEKISTING) Jumlah Keuntungan MAX. 10% Jumlah Jumlah Keuntungan MAX. 10% Jumlah Jumlah Keuntungan MAX. 10% Jumlah

C. PEKERJAAN PONDASI

Jumlah Keuntungan MAX. 10% Jumlah

(27)

Papan Kayu Terentang 0.0200 M3 1,400,000.00 28,000.00 Paku 5 - 7 cm 0.4000 Kg 18,000.00 7,200.00 Besi Beton Polos - Polos 150.0000 Kg 10,000.00 1,500,000.00 Kawat Beton 2.2500 Kg 30,000.00 67,500.00 Semen PC ( abu - abu ) 7.9000 Zak 70,000.00 553,000.00 Pasir Beton 0.4900 M3 220,000.00 107,800.00 Split (Batu Pecah) 0.8100 M3 165,000.00 133,650.00 Pekerja 3.9000 Org 46,000.00 179,400.00 Tukang Batu 1/2 Terampil 0.3500 Org 57,500.00 20,125.00 Tukang Kayu 1/2 Terampil 1.0400 Org 57,500.00 59,800.00 Tukang Besi 1/2 Terampil 1.0500 Org 57,500.00 60,375.00 Kepala Tukang 0.2450 Org 80,000.00 19,600.00 Mandor 0.1650 Org 85,000.00 14,025.00 2,750,475.00 0.10 275,047.50 3,025,522.50

C 5 1 M3 MEMBUAT PONDASI BETON BORPILE (PENULANGAN 150 Kg + BEKISTING)

Papan Kayu Terentang 0.2000 M3 1,400,000.00 280,000.00 Paku 5 - 7 cm 1.5000 Kg 21,000.00 31,500.00 Besi Beton Polos - Polos 150.0000 Kg 10,000.00 1,500,000.00 Kawat Beton 2.2500 Kg 30,000.00 67,500.00 Semen PC ( abu - abu ) 6.4600 Zak 70,000.00 452,200.00 Pasir Beton 0.5200 M3 220,000.00 114,400.00 Split (Batu Pecah) 0.7800 M3 165,000.00 128,700.00 Pekerja 4.0000 Org 46,000.00 184,000.00 Tukang Batu 1/2 Terampil 0.4000 Org 57,500.00 23,000.00 Tukang Kayu 1/2 Terampil 1.0000 Org 57,500.00 57,500.00 Tukang Besi 1/2 Terampil 1.0000 Org 57,500.00 57,500.00 Kepala Tukang 0.2450 Org 80,000.00 19,600.00 Mandor 0.1650 Org 85,000.00 14,025.00 2,929,925.00 0.10 292,992.50 3,222,917.50 Jumlah Keuntungan MAX. 10% Jumlah Jumlah Keuntungan MAX. 10% Jumlah

(28)

D 1 1 M3 MEMBUAT SLOOF 15/25 BETON BERTULANG ( 200 Kg BESI + BEKISTING )

Bekesteng Albasiah 0.2900 M3 1,400,000.00 406,000.00 Paku 5 - 7 cm 1.5000 Kg 18,000.00 27,000.00 Besi Beton Polos 200.0000 Kg 10,000.00 2,000,000.00 Kawat Beton 2.2500 Kg 30,000.00 67,500.00 Semen PC ( abu - abu ) 6.4600 Zak 70,000.00 452,200.00 Pasir Beton 0.5200 M3 220,000.00 114,400.00 Split (Batu Pecah 2/3) 0.7800 M3 165,000.00 128,700.00 Pekerja 3.0000 Org 46,000.00 138,000.00 Tukang Batu 1/2 Terampil 0.3500 Org 57,500.00 20,125.00 Tukang Kayu 1/2 Terampil 1.0400 Org 57,500.00 59,800.00 Tukang Besi 1/2 Terampil 1.0500 Org 57,500.00 60,375.00 Kepala Tukang 0.2450 Org 80,000.00 19,600.00 Mandor 0.1225 Org 85,000.00 10,412.50 3,504,112.50 0.10 350,411.25 3,854,523.75

D 2 1 M3 MEMBUAT KOLOM BETON BERTULANG 15/40 ( 99.6267 Kg BESI + BEKISTING )

Bekisting Albasiah 0.3500 M3 1,400,000.00 490,000.00 Paku 5 - 7cm 1.5000 Kg 18,000.00 27,000.00 Besi Beton Polos 99.6267 Kg 10,000.00 996,267.00 Kawat Beton 2.2500 Kg 30,000.00 67,500.00 Semen PC ( abu - abu ) 6.4600 Zak 70,000.00 452,200.00 Pasir Beton 0.5200 M3 220,000.00 114,400.00 Split (Batu Pecah) 0.7800 M3 165,000.00 128,700.00 Pekerja 3.0000 Org 46,000.00 138,000.00 Tukang Batu 1/2 Terampil 0.3500 Org 1 orang / Hari / 8 Jam #VALUE! Tukang Kayu 1/2 Terampil 1.0400 Org 57,500.00 59,800.00 Tukang Besi 1/2 Terampil 1.0500 Org 57,500.00 60,375.00 Kepala Tukang 0.2450 Org 80,000.00 19,600.00 Mandor 0.1225 Org 85,000.00 10,412.50 #VALUE! Jumlah D. PEKERJAAN STRUKTUR Jumlah Keuntungan MAX. 10% Jumlah

(29)

0.10

#VALUE! #VALUE! D 3 1 M3 MEMBUAT KOLOM BETON BERTULANG 15/25 ( 91.334 Kg BESI + BEKISTING )

Bekisting Albasiah 0.4400 M3 1,400,000.00 616,000.00 Paku 5 - 7cm 1.5000 Kg 18,000.00 27,000.00 Besi Beton Polos 91.3340 Kg 10,000.00 913,340.00 Kawat Beton 2.2500 Kg 30,000.00 67,500.00 Semen PC ( abu - abu ) 6.4600 Zak 70,000.00 452,200.00 Pasir Beton 0.5200 M3 220,000.00 114,400.00 Split (Batu Pecah) 0.7800 M3 165,000.00 128,700.00 Pekerja 3.0000 Org 46,000.00 138,000.00 Tukang Batu 1/2 Terampil 0.3500 Org 57,500.00 20,125.00 Tukang Kayu 1/2 Terampil 1.0400 Org 57,500.00 59,800.00 Tukang Besi 1/2 Terampil 1.0500 Org 57,500.00 60,375.00 Kepala Tukang 0.2450 Org 80,000.00 19,600.00 Mandor 0.1225 Org 85,000.00 10,412.50 2,627,452.50 0.10 262,745.25 2,890,197.75

D 4 1 M3 MEMBUAT KOLOM BETON BERTULANG 15/15 ( 211.5556 Kg BESI + BEKISTING )

Bekisting Albasiah 0.4400 M3 1,400,000.00 616,000.00 Paku 5 - 7cm 1.5000 Kg 18,000.00 27,000.00 Besi Beton Polos 211.5556 Kg 10,000.00 2,115,556.00 Kawat Beton 2.2500 Kg 30,000.00 67,500.00 Semen PC ( abu - abu ) 6.4600 Zak 70,000.00 452,200.00 Pasir Beton 0.5200 M3 220,000.00 114,400.00 Split (Batu Pecah) 0.7800 M3 165,000.00 128,700.00 Pekerja 3.0000 Org 46,000.00 138,000.00 Tukang Batu 1/2 Terampil 0.3500 Org 57,500.00 20,125.00 Tukang Kayu 1/2 Terampil 1.0400 Org 57,500.00 59,800.00 Tukang Besi 1/2 Terampil 1.0500 Org 57,500.00 60,375.00 Kepala Tukang 0.2450 Org 80,000.00 19,600.00 Mandor 0.1225 Org 85,000.00 10,412.50 Keuntungan MAX. 10% Jumlah Keuntungan MAX. 10% Jumlah Jumlah

(30)

3,829,668.50 0.10 382,966.85 4,212,635.35

D 5 1 M3 MEMBUAT BALOK BETON BERTULANG 30/50 ( 250 Kg BESI + BEKISTING )

Bekisting Albasiah 0.5600 M3 1,400,000.00 784,000.00 Paku 5 - 7cm 1.5000 Kg 18,000.00 27,000.00 Besi Beton Polos 250.0000 Kg 10,000.00 2,500,000.00 Kawat Beton 2.2500 Kg 30,000.00 67,500.00 Semen PC ( abu - abu ) 6.4500 Zak 70,000.00 451,500.00 Pasir Beton 0.5200 M3 220,000.00 114,400.00 Split (Batu Pecah) 0.7800 M3 165,000.00 128,700.00 Pekerja 3.0000 Org 46,000.00 138,000.00 Tukang Batu 1/2 Terampil 0.3500 Org 57,500.00 20,125.00 Tukang Kayu 1/2 Terampil 1.0400 Org 57,500.00 59,800.00 Tukang Besi 1/2 Terampil 1.0500 Org 57,500.00 60,375.00 Kepala Tukang 0.2450 Org 80,000.00 19,600.00 Mandor 0.1225 Org 85,000.00 10,412.50 4,381,412.50 0.10 438,141.25 4,819,553.75

D 6 1 M3 MEMBUAT BALOK BETON BERTULANG 18/10 ( 217 Kg BESI + BEKISTING )

Bekisting Albasiah 0.5600 M3 1,400,000.00 784,000.00 Paku 5 - 7cm 1.5000 Kg 18,000.00 27,000.00 Pelumas Begisting (oli/minyak) 0.4000 Ltr 18,000.00 7,200.00 Besi Beton Polos 217.0000 Kg 10,000.00 2,170,000.00 Kawat Beton 2.2500 Kg 30,000.00 67,500.00 Semen PC ( abu - abu ) 6.4500 Zak 70,000.00 451,500.00 Pasir Beton 0.5200 M3 220,000.00 114,400.00 Split (Batu Pecah) 0.7800 M3 165,000.00 128,700.00 Pekerja 3.0000 Org 46,000.00 138,000.00 Tukang Batu 1/2 Terampil 0.3500 Org 57,500.00 20,125.00 Tukang Kayu 1/2 Terampil 1.0400 Org 57,500.00 59,800.00 Tukang Besi 1/2 Terampil 1.0500 Org 57,500.00 60,375.00

Jumlah Jumlah Keuntungan MAX. 10% Jumlah Keuntungan MAX. 10% Jumlah

(31)

Kepala Tukang 0.2450 Org 80,000.00 19,600.00 Mandor 0.1225 Org 85,000.00 10,412.50 4,058,612.50 0.10 405,861.25 4,464,473.75

D 7 1 M3 MEMBUAT PLAT LANTAI Tb.12 cm BETON BERTULANG

Semen Portland 232.0000 M3 70,000.00 16,240,000.00 Pasir Beton 0.5200 Kg 220,000.00 114,400.00 Batu Pecah Mesin 2/3 0.7800 Ltr 165,000.00 128,700.00 Besi Beton Polos 164.1262 Kg 10,000.00 1,641,262.00 Kawat Beton 2.3447 Kg 30,000.00 70,341.00 Kayu Terentang Albasiah, Papan 0.2450 Zak 1,400,000.00 343,000.00 Paku 2" - 5" 0.1500 M3 21,000.00 3,150.00 Kayu Balok Albasiah 0.0700 M3 1,400,000.00 98,000.00 Pekerja 6.4697 Org 46,000.00 297,606.20 Tukang Batu 1/2 Terampil 0.2500 Org 57,500.00 14,375.00 Tukang Kayu 1/2 Terampil 4.0260 Org 57,500.00 231,495.00 Tukang Besi 1/2 Terampil 1.0073 Org 57,500.00 57,919.75 Kepala Tukang 0.5192 Org 80,000.00 41,536.00 Mandor 0.1924 Org 85,000.00 16,354.00 19,298,138.95 0.10 1,929,813.90 21,227,952.85

D 8 1 M3 MEMBUAT PLAT LANTAI Tb.10 cm BETON BERTULANG

Semen Portland 232.0000 M3 70,000.00 16,240,000.00 Pasir Beton 0.5200 Kg 220,000.00 114,400.00 Batu Pecah Mesin 2/3 0.7800 Ltr 165,000.00 128,700.00 Besi Beton Polos 197.1795 Kg 10,000.00 1,971,795.00 Kawat Beton 2.8169 Kg 30,000.00 84,507.00 Kayu Terentang Albasiah, Papan 0.2450 Zak 1,400,000.00 343,000.00 Paku 5 - 12 cm 0.1500 M3 17,500.00 2,625.00 Kayu Balok Albasiah 0.0700 M3 1,400,000.00 98,000.00 Pekerja 6.4697 Org 46,000.00 297,606.20 Jumlah Keuntungan MAX. 10% Jumlah Jumlah Keuntungan MAX. 10% Jumlah

(32)

Tukang Batu 1/2 Terampil 0.2500 Org 57,500.00 14,375.00 Tukang Kayu 1/2 Terampil 4.0260 Org 57,500.00 231,495.00 Tukang Besi 1/2 Terampil 1.0073 Org 57,500.00 57,919.75 Kepala Tukang 0.5192 Org 80,000.00 41,536.00 Mandor 0.1924 Org 85,000.00 16,354.00 19,642,312.95 0.10 1,964,231.30 21,606,544.25

D 9 1 M3 MEMBUAT RING BALK BETON BERTULANG ( 175 Kg BESI + BEKISTING )

Papan Kayu Terentang 0.2700 M3 1,400,000.00 378,000.00 Paku 5 - 12 cm 2.0000 Kg 17,500.00 35,000.00 Besi Beton Polos 175.0000 Kg 10,000.00 1,750,000.00 Kawat Beton 3.0000 Kg 30,000.00 90,000.00 Semen PC ( abu - abu ) 8.0000 Zak 70,000.00 560,000.00 Pasir Beton 0.5200 M3 220,000.00 114,400.00 Split (Batu Pecah) 0.7800 M3 170,000.00 132,600.00 Pekerja 3.0000 Org 46,000.00 138,000.00 Tukang Batu 1/2 Terampil 0.3500 Org 57,500.00 20,125.00 Tukang Kayu 1/2 Terampil 1.0400 Org 57,500.00 59,800.00 Tukang Besi 1/2 Terampil 1.0500 Org 57,500.00 60,375.00 Kepala Tukang 0.2450 Org 80,000.00 19,600.00 Mandor 0.1225 Org 85,000.00 10,412.50 3,368,312.50 0.10 336,831.25 3,705,143.75

D 9 1 M3 MEMBUAT BALOK AMPIG BETON BERTULANG ( 175 Kg BESI + BEKISTING )

Papan Kayu Terentang 0.2700 M3 35,000.00 9,450.00 Paku 5 - 12 cm 2.0000 Kg 17,500.00 35,000.00 Besi Beton Polos 175.0000 Kg 10,000.00 1,750,000.00 Kawat Beton 3.0000 Kg 52,000.00 156,000.00 Semen PC ( abu - abu ) 8.0000 Zak 48,000.00 384,000.00 Pasir Beton 0.5200 M3 61,000.00 31,720.00 Split (Batu Pecah) 0.7800 M3 15,000.00 11,700.00

Jumlah Keuntungan MAX. 10% Jumlah Jumlah Keuntungan MAX. 10% Jumlah

(33)

Pekerja 3.0000 Org 46,000.00 138,000.00 Tukang Batu 1/2 Terampil 0.3500 Org 57,500.00 20,125.00 Tukang Kayu 1/2 Terampil 1.0400 Org 57,500.00 59,800.00 Tukang Besi 1/2 Terampil 1.0500 Org 57,500.00 60,375.00 Kepala Tukang 0.2450 Org 80,000.00 19,600.00 Mandor 0.1225 Org 85,000.00 10,412.50 2,686,182.50 0.10 268,618.25 2,954,800.75

E 1 1 M2 PASANG BATA MERAH 1/2 BATA, CAMPURAN 1 PC : 2 PS

Bata Merah 5 x 11 x 22 80.0000 Bh 800.00 64,000.00 Semen PC ( abu - abu ) 0.5180 Zak 70,000.00 36,260.00 Pasir Pasang 0.0580 M3 210,000.00 12,180.00 Pekerja Terampil 0.3500 Org 63,250.00 22,137.50 Tukang Batu Terampil 0.2140 Org 63,250.00 13,535.50 Kepala Tukang 0.0210 Org 75,000.00 1,575.00 Mandor 0.0110 Org 85,000.00 935.00 150,623.00 0.10 15,062.30 165,685.30

E 2 1 M2 PASANGAN PLESTERAN CAMPURAN 1 PC : 2 PS Tebal 2 cm + ACIAN

Semen PC ( abu - abu ) 0.0320 Zak 70,000.00 2,240.00 Pasir Pasang 0.0060 M3 210,000.00 1,260.00 Pekerja Terampil 0.3500 Org 46,000.00 16,100.00 Tukang Batu Terampil 0.2400 Org 63,250.00 15,180.00 Kepala Tukang 0.0210 Org 75,000.00 1,575.00 Mandor 0.0100 Org 85,000.00 850.00 37,205.00 0.10 3,720.50 40,925.50

E 3 1 M2 PASANG DINDING KERAMIK UKURAN 20 X 20 cm 1.0100 Bh 54,000.00 54,540.00 Jumlah Keuntungan MAX. 10% Jumlah Keuntungan MAX. 10% Jumlah Keramik 20 x 20 E. PEKERJAAN DINDING Jumlah Jumlah Keuntungan MAX. 10% Jumlah

(34)

0.1600

Zak 70,000.00 11,200.00 Pasir Pasang 0.0300 M3 210,000.00 6,300.00 Semen Warna 0.0130 Kg 80,000.00 1,040.00 Pekerja Terampil 0.1880 Org 63,250.00 11,891.00 Tukang Batu Terampil 0.1000 Org 63,250.00 6,325.00 Kepala Tukang 0.3750 Org 75,000.00 28,125.00 Mandor 0.0190 Org 85,000.00 1,615.00 121,036.00 0.10 12,103.60 133,139.60

F 1 1 M2 PASANG KUSEN PINTU DAN JENDELA KAYU JATI

Kayu Kamper Samarinda 1.1000 M3 9,400,000.00 10,340,000.00 Paku Semua Ukuran 1.2500 Kg 56,500.00 70,625.00 Lem Putih (Fox) 1.0000 Kg 14,800.00 14,800.00 Pekerja Terampil 4.0000 Org 63,250.00 253,000.00 Tukang Kayu Terampil 15.0000 Org 65,000.00 975,000.00 Kepala Tukang 2.7000 Org 80,000.00 216,000.00 Mandor 0.5000 Org 85,000.00 42,500.00 11,911,925.00 0.10 1,191,192.50 13,103,117.50

F 2 1 UNIT PASANG DAUN PINTU

Rangka + Panil Kayu Kamper Samarinda 0.0500 M3 10,400,000.00 520,000.00 Paku 1.2500 Kg 56,500.00 70,625.00 Lem Putih (Fox) 0.7500 Kg 14,800.00 11,100.00 List Kayu Profil 4.0000 M1 9,795.00 39,180.00 Pekerja Terampil 0.6000 Org 63,250.00 37,950.00 Tukang Kayu Terampil 2.6000 Org 65,000.00 169,000.00 Kepala Tukang 0.2600 Org 80,000.00 20,800.00 Mandor 0.0260 Org 85,000.00 2,210.00 870,865.00

0.10

87,086.50 Semen PC ( abu - abu )

Jumlah Keuntungan MAX. 10% F. PEKERJAAN KUSEN Jumlah Keuntungan MAX. 10% Jumlah Jumlah Keuntungan MAX. 10% Jumlah

(35)

957,951.50

F 3 1 UNIT PASANG KUSEN PINTU TOILET

Fiber Glass 1.0000 Unit 240,000.00 240,000.00 Pekerja 1.0000 Org 46,000.00 46,000.00 Tukang Kayu 2.5000 Org 65,000.00 162,500.00 Kepala Tukang 0.2500 Org 80,000.00 20,000.00 Mandor 0.0500 Org 85,000.00 4,250.00 472,750.00 0.10 47,275.00 520,025.00

F 4 1 UNIT PASANG DAUN PINTU TOILET

Fiber Glass 1.0000 Unit 240,000.00 240,000.00 Pekerja 1.0000 Org 46,000.00 46,000.00 Tukang Kayu 2.5000 Org 65,000.00 162,500.00 Kepala Tukang 0.2500 Org 80,000.00 20,000.00 Mandor 0.0500 Org 85,000.00 4,250.00 472,750.00 0.10 47,275.00 520,025.00

F 5 1 UNIT DAUN JENDELA KACA

Rangka + Panil Kayu Kamper Samarinda 0.0500 M3 165,000.00 8,250.00 Paku 1.2500 Kg 22,000.00 27,500.00 Lem Putih (Fox) 0.7500 Kg 25,000.00 18,750.00 List Kayu Profil 4.0000 M1 60,000.00 240,000.00 Pekerja Terampil 0.6000 M3 63,250.00 37,950.00 Tukang Kayu Terampil 2.6000 Org 65,000.00 169,000.00 Kepala Tukang 0.2600 Org 80,000.00 20,800.00 Mandor 0.0260 Org 85,000.00 2,210.00 524,460.00 0.10 52,446.00 576,906.00

F 6 1 BUAH PASANG KAIT ANGIN

Kait Angin 1.0000 Ps 40,000.00 40,000.00 Jumlah Jumlah Keuntungan MAX. 10% Jumlah Jumlah Keuntungan MAX. 10% Jumlah Keuntungan MAX. 10% Jumlah Jumlah

(36)

Pekerja 0.0150 M3 46,000.00 690.00 Tukang Kayu 0.1500 Org 65,000.00 9,750.00 Kepala Tukang 0.0150 Org 80,000.00 1,200.00 Mandor 0.00075 Org 85,000.00 63.75 51,703.75 0.10 5,170.38 56,874.13

F 7 1 M2 PASANG KACA, TEBAL 5 MM

Kaca Polos 5 mm 1.0000 M2 97,000.00 97,000.00 Paku 0.1000 Kg 18,000.00 1,800.00 List Kayu 4.0000 M1 9,795.00 39,180.00 Pekerja 1/2 Terampil 0.1500 Org 57,500.00 8,625.00 Tukang Kayu 1/2 Terampil 0.1000 Org 57,500.00 5,750.00 Kepala Tukang 0.0150 Org 80,000.00 1,200.00 Mandor 0.01000 Org 85,000.00 850.00 154,405.00 0.10 15,440.50 169,845.50

F 8 1 M2 PASANG KACA, TEBAL 3 MM

Kaca Polos 3 mm 1.0000 M2 52,000.00 52,000.00 Paku 0.1000 Kg 18,000.00

List Kayu 0.1000 M1 9,795.00

Pekerja 1/2 Terampil 0.1500 Org 57,500.00 8,625.00 Tukang Kayu 1/2 Terampil 0.1000 Org 57,500.00 5,750.00 Kepala Tukang 0.0150 Org 80,000.00 1,200.00 Mandor 0.01000 Org 85,000.00 850.00 68,425.00 0.10 6,842.50 75,267.50

F 9 1 BUAH PASANG KUNCI TANAM STANDAR

Kunci Tanam Standar 1.0000 Bh 165,000.00 165,000.00 Pekerja 0.0100 Org 46,000.00 460.00 Tukang Kayu 0.5000 Org 65,000.00 32,500.00

Jumlah Keuntungan MAX. 10% Jumlah Jumlah Keuntungan MAX. 10% Jumlah Jumlah Keuntungan MAX. 10% Jumlah

(37)

Kepala Tukang 0.0100 Org 80,000.00 800.00 Mandor 0.0050 Org 85,000.00 425.00 199,185.00 0.10 19,918.50 219,103.50

F 10 1 BUAH PASANG KUNCI TANAM KAMAR MANDI

Kunci Tanam Kamar Mandi 1.0000 Bh 165,000.00 165,000.00 Pekerja 0.0050 Org 46,000.00 230.00 Tukang Kayu 0.5000 Org 65,000.00 32,500.00 Kepala Tukang 0.0050 Org 80,000.00 400.00 Mandor 0.0025 Org 85,000.00 212.50 198,342.50 0.10 19,834.25 218,176.75

F 11 1 BUAH PASANG ENGSEL PINTU

Kunci Tanam Standar 1.0000 Bh 165,000.00 165,000.00 Pekerja 0.0150 Org 46,000.00 690.00 Tukang Kayu 0.1000 Org 65,000.00 6,500.00 Kepala Tukang 0.0150 Org 80,000.00 1,200.00 Mandor 0.00075 Org 85,000.00 63.75 173,453.75 0.10 17,345.38 190,799.13

F 12 1 BUAH PASANG ENGSEL JENDELA KUPU - KUPU

Engsel Jendela 1.0000 Bh 7,400.00 7,400.00 Pekerja 0.0100 Org 46,000.00 460.00 Tukang Kayu 0.1000 Org 65,000.00 6,500.00 Kepala Tukang 0.0100 Org 80,000.00 800.00 Mandor 0.00050 Org 85,000.00 42.50 15,202.50 0.10 1,520.25 16,722.75

F 13 1 UNIT PASANG KUNCI SELOT PINTU

Jumlah Jumlah Keuntungan MAX. 10% Jumlah Jumlah Jumlah Keuntungan MAX. 10% Jumlah Jumlah Jumlah Keuntungan MAX. 10% Keuntungan MAX. 10%

(38)

Kunci Selot 1.0000 Bh 60,000.00 60,000.00 Pekerja 0.0200 Org 46,000.00 920.00 Tukang Kayu 0.2000 Org 65,000.00 13,000.00 Kepala Tukang 0.0200 Org 80,000.00 1,600.00 Mandor 0.00100 Org 85,000.00 85.00 75,605.00 0.10 7,560.50 83,165.50

F 14 1 UNIT PASANG KUNCI SELOT JENDELA

Kunci Selot 1.0000 Bh 25,000.00 25,000.00 Pekerja 0.0200 Org 46,000.00 920.00 Tukang Kayu 0.2000 Org 65,000.00 13,000.00 Kepala Tukang 0.0200 Org 80,000.00 1,600.00 Mandor 0.00100 Org 85,000.00 85.00 40,605.00 0.10 4,060.50 44,665.50

F 15 1 BUAH PASANG HAK ANGIN JENDELA

Kait Angin 1.0000 M3 40,000.00 40,000.00 Pekerja 0.2000 M3 46,000.00 9,200.00 Tukang Kayu 0.2000 Org 65,000.00 13,000.00 Kepala Tukang 0.0200 Org 80,000.00 1,600.00 Mandor 0.00100 Org 85,000.00 85.00 63,885.00 0.10 6,388.50 70,273.50

G 1 1 M2 PASANG RANGKA PLAFOND BESI HOLLOW

2.2000

M1 25,000.00 55,000.00 3.0750

M1 22,500.00 69,187.50 Pekerja 1/2 Terampil 0.1500 Org 57,500.00 8,625.00 Tukang Kayu Terampil 0.2500 Org 65,000.00 16,250.00 Kepala Tukang 0.0250 Org 80,000.00 2,000.00 Hollow 4/4 Zincromate Hollow 2/4 Zincromate Keuntungan MAX. 10% Jumlah Jumlah Jumlah Keuntungan MAX. 10% Jumlah Jumlah Keuntungan MAX. 10% Jumlah G. PEKERJAAN PLAFOND

(39)

Mandor 0.0750 Org 85,000.00 6,375.00 157,437.50 0.10 15,743.75 173,181.25

G 2 1 M2 PASANG PLAFOND GYPSUM BOARD, TEBAL 9 MM + RANGKA BESI HOLLOW

Gypsum Board (120 x 240 x 9) mm 0.3640 Lbr 61,000.00 22,204.00 Paku 1/2 " - 1 " 0.2000 Kg 21,000.00 4,200.00 Pekerja 0.1000 Org 46,000.00 4,600.00 Tukang Kayu Terampil 0.2000 Org 65,000.00 13,000.00 Kepala Tukang 0.0200 Org 80,000.00 1,600.00 Mandor 0.0070 Org 85,000.00 595.00 46,199.00 0.10 4,619.90 50,818.90

G 3 1 M2 PASANG PLAFOND GRC ( 60 X 1,2 ) M, TEBAL 6 MM

GRC tebal 6 mm 0.3640 Lbr 48,000.00 17,472.00 Paku 1 /2" - 1" 0.2000 Kg 21,000.00 4,200.00 Pekerja 0.1000 Org 46,000.00 4,600.00 Tukang Kayu Terampil 0.2000 Org 65,000.00 13,000.00 Kepala Tukang 0.0200 Org 80,000.00 1,600.00 Mandor 0.0070 Org 85,000.00 595.00 41,467.00 0.10 4,146.70 45,613.70

G 4 1 M1 PASANG LIST PLAFOND PROFIL GYPSUM

List Gypsum Profil 1.0000 M1 15,000.00 15,000.00 Paku 1 /2" - 1" 0.2100 Kg 21,000.00 4,410.00 Tepung Gypsum 0.1500 Kg 1,000.00 150.00 Pekerja 0.0700 Org 46,000.00 3,220.00 Tukang Kayu 1/2 Terampil 0.0210 Org 57,500.00 1,207.50 Kepala Tukang 0.0020 Org 80,000.00 160.00 Mandor 0.0040 Org 85,000.00 340.00 24,487.50 Jumlah Keuntungan MAX. 10% Jumlah Jumlah Keuntungan MAX. 10% Jumlah Jumlah Jumlah Keuntungan MAX. 10% Jumlah

(40)

0.10

2,448.75 26,936.25

H 1 1 M2 PASANG LANTAI KERAMIK UKURAN 40 X 40 cm

1.0100 Bh 94,000.00 94,940.00 0.1600 Zak 70,000.00 11,200.00 Pasir Pasang 0.0300 M3 210,000.00 6,300.00 Semen Warna 0.0130 Kg 80,000.00 1,040.00 Pekerja Terampil 0.2500 Org 63,250.00 15,812.50 Tukang Batu Terampil 0.4000 Org 63,250.00 25,300.00 Kepala Tukang 0.0120 Org 75,000.00 900.00 Mandor 0.00125 Org 85,000.00 106.25 155,598.75 0.10 15,559.88 171,158.63

H 2 1 M2 PASANG LANTAI KERAMIK UKURAN 20 X 20 cm

1.0100 Dus 2,000.00 2,020.00 0.1600 Zak 70,000.00 11,200.00 Pasir Pasang 0.0300 M3 210,000.00 6,300.00 Semen Warna 0.0130 Kg 80,000.00 1,040.00 Pekerja Terampil 0.2500 Org 63,250.00 15,812.50 Tukang Batu Terampil 0.4000 Org 63,250.00 25,300.00 Kepala Tukang 0.0500 Org 75,000.00 3,750.00 Mandor 0.02500 Org 85,000.00 2,125.00 67,547.50 0.10 6,754.75 74,302.25

H 3 1 M2 PASANG KERAMIK UKURAN 30 X 30

1.0100 Bh 84,000.00 84,840.00 0.1600 Zak 70,000.00 11,200.00 Pasir Pasang 0.0300 M3 210,000.00 6,300.00 Semen Warna 0.0130 Kg 80,000.00 1,040.00 Pekerja Terampil 0.2500 Org 63,250.00 15,812.50 Keramik ukuran 30 x 30

Semen PC ( abu - abu )

Jumlah Ubin Keramik 20 x 20

Semen PC ( abu - abu )

Jumlah Keuntungan MAX. 10% Jumlah Keuntungan MAX. 10% Jumlah Jumlah H. PEKERJAAN LANTAI Keuntungan MAX. 10% Keramik 40 x 40 cm

(41)

Tukang Batu Terampil 0.4000 Org 63,250.00 25,300.00 Kepala Tukang 0.0500 Org 75,000.00 3,750.00 Mandor 0.02500 Org 85,000.00 2,125.00 150,367.50 0.10 15,036.75 165,404.25

H 4 1 M2 PASANG PLIN KERAMIK UKURAN 10 X 40

0.2000 Bh 2,500.00 500.00 0.1600 Zak 70,000.00 11,200.00 Pasir Pasang 0.0300 M3 210,000.00 6,300.00 Semen Warna 0.0130 Kg 80,000.00 1,040.00 Pekerja Terampil 0.2500 Org 63,250.00 15,812.50 Tukang Batu Terampil 0.4000 Org 63,250.00 25,300.00 Kepala Tukang 0.0500 Org 75,000.00 3,750.00 Mandor 0.0250 Org 85,000.00 2,125.00 66,027.50 0.10 6,602.75 72,630.25

I 1 1 M3 PASANG RANGKA ATAP BAJA RINGAN

1.0000

M2 32,000.00 32,000.00 Accessories 1.0000 Ls 5,000.00 5,000.00 Pekerja 1/2 Terampil 0.5000 Org 57,500.00 28,750.00 Tukang Besi Terampil 0.2500 Org 60,000.00 15,000.00 Kepala Tukang 0.0250 Org 75,000.00 1,875.00 Mandor 0.0250 Org 85,000.00 2,125.00 84,750.00 0.10 8,475.00 93,225.00

I 2 1 M2 PEKERJAAN PENUTUP ATAP GENTENG BETON

11.0000

Bh 55,000.00 605,000.00 0.0300

Bh 21,000.00 630.00 Pekerja 0.2000 Org 46,000.00 9,200.00 Plint Keramik ukuran 10 x 40

Semen PC ( abu - abu )

Jumlah Keuntungan MAX. 10% Jumlah Jumlah Genteng Beton Paku Biasa 2" - 5" Jumlah Keuntungan MAX. 10% Jumlah Keuntungan MAX. 10% Jumlah I. PEKERJAAN ATAP

(42)

Tukang Batu 0.1000 Org 63,250.00 6,325.00 Kepala Tukang 0.0100 Org 75,000.00 750.00 Mandor 0.0010 Org 85,000.00 85.00 621,990.00 0.10 62,199.00 684,189.00

I 3 1 M2 PEKERJAAN BUBUNGAN ATAP GENTENG BETON

3.0000 Bh 6,500.00 19,500.00 0.1304 Zak 70,000.00 9,128.00 Pasir Pasang 0.0210 M3 210,000.00 4,410.00 Pekerja 0.1500 Org 46,000.00 6,900.00 Tukang Batu Terampil 0.2000 Org 63,250.00 12,650.00 Kepala Tukang 0.0100 Org 75,000.00 750.00 Mandor 0.0050 Org 85,000.00 425.00 53,763.00 0.10 5,376.30 59,139.30

I 4 1 M2 PASANG LIST PLANG UKURAN ( 3 x 20 ) cm, Kayu Jati 0.0040

M3 4,700,000.00 18,800.00 Paku 1.2800 Kg 18,000.00 23,040.00 Pekerja 0.1000 Org 46,000.00 4,600.00 Tukang Kayu Terampil 0.2000 Org 65,000.00 13,000.00 Kepala Tukang 0.0250 Org 80,000.00 2,000.00 Mandor 0.0050 Org 85,000.00 425.00 61,865.00 0.10 6,186.50 68,051.50

I 5 1 M2 PASANG TALANG DATAR

0.5000

Lbr 20,000.00 10,000.00 0.0150

Kg 21,000.00 315.00 Kayu Lokal Kls II, Papan 0.0096 M3 1,500,000.00 14,400.00 Flincote/Meni Besi 0.2500 Kg 22,000.00 5,500.00 Pekerja 0.1500 Org 46,000.00 6,900.00 Genteng Bubungan Beton

Jumlah Jumlah Keuntungan MAX. 10% Jumlah Semen PC Jumlah

Kayu Borneo, Papan

Jumlah Keuntungan MAX. 10% Jumlah Seng Plat 3 x 6 bjls 20 Paku Biasa 1/2" - 1" Keuntungan MAX. 10%

(43)

Tukang Kayu 0.4000 Org 65,000.00 26,000.00 Kepala Tukang 0.0250 Org 80,000.00 2,000.00 Mandor 0.00125 Org 85,000.00 106.25 65,221.25 0.10 6,522.13 71,743.38

J 1 1 M2 PENGECATAN DINDING SEKELAS VINILEX (3 x )

Cat Tembok Vinilex / Sekelas Vinilex (3x) 0.1000 Kg 152,000.00 15,200.00 0.1600 Kg 19,000.00 3,040.00 0.0100 Kg 27,500.00 275.00 Ampelas 0.1500 Bh 10,600.00 1,590.00 Pekerja 0.0280 Lbr 46,000.00 1,288.00 Tukang Cat 0.0630 Org 60,000.00 3,780.00 Kepala Tukang Cat 0.0060 Org 75,000.00 450.00 Mandor 0.0030 Org 85,000.00 255.00 10,678.00 0.10 1,067.80 11,745.80

J 2 1 M2 PENGECATAN BIDANG KAYU (3X) BERIKUT MENI 0.2000 Kg 22,000.00 4,400.00 0.1500 Kg 25,350.00 3,802.50 0.3500 Kg 40,000.00 14,000.00 Ampelas Kayu 0.1500 Lbr 10,600.00 1,590.00 Minyak Cat Terpentin 0.1500 Ltr 26,500.00 3,975.00 Kwas 3 " 0.0500 Bh 10,000.00 500.00 Pekerja 0.0700 Org 46,000.00 3,220.00 Tukang Cat 0.1050 Org 60,000.00 6,300.00 Kepala Tukang 0.0040 Org 75,000.00 300.00 Mandor 0.0030 Org 85,000.00 255.00 38,342.50 0.10 3,834.25 42,176.75 Jumlah Keuntungan MAX. 10% Jumlah J. PEKERJAAN PENGECATAN Plamir Tembok Rol Cat Jumlah Keuntungan MAX. 10% Jumlah

Cat Kayu Sekelas SEIV Meni Kayu

Plamir Kayu

Jumlah Keuntungan MAX. 10% Jumlah

(44)

J 3 1 M2 PENGECATAN PLAFOND SEKELAS VINILEX (3X) LUAR 0.1000 Kg 152,000.00 15,200.00 0.1000 Kg 19,000.00 1,900.00 0.0100 Bh 27,500.00 275.00 Ampelas 0.1500 Lbr 10,600.00 1,590.00 Pekerja 0.0300 Org 46,000.00 1,380.00 Tukang Cat 0.0750 Org 60,000.00 4,500.00 Kepala Tukang 0.0080 Org 75,000.00 600.00 Mandor 0.0030 Org 85,000.00 255.00 25,700.00 0.10 2,570.00 28,270.00 J 4 1 M2 PENGECATAN BESI (3X) 0.1670 Kg 22,000.00 3,674.00 0.2000 Kg 40,000.00 8,000.00 Ampelas 0.4000 Lbr 10,600.00 4,240.00 Minyak Cat / Thiner B 0.1500 Ltr 26,500.00 3,975.00 Kwas 3 " 0.0500 Bh 10,000.00 500.00 Pekerja 0.2000 Org 46,000.00 9,200.00 Tukang Cat 0.0600 Org 60,000.00 3,600.00 Kepala Tukang 0.0300 Org 75,000.00 2,250.00 Mandor 0.0100 Org 85,000.00 850.00 36,289.00 0.10 3,628.90 39,917.90 J 4 1 M2 PENGECATAN GENTENG (3X) 0.2000 Kg 683,000.00 136,600.00 Ampelas 0.4000 Lbr 10,600.00 4,240.00 Minyak Cat / Thiner B 0.1500 Ltr 26,500.00 3,975.00 Kwas 3 " 0.0500 Bh 10,000.00 500.00 Pekerja 0.2000 Org 46,000.00 9,200.00 Tukang Cat 0.0600 Org 60,000.00 3,600.00 Kepala Tukang 0.0300 Org 75,000.00 2,250.00 Cat Tembok Vinilex / Sekelas Vinilex (3x)

Plamir Tembok

Jumlah Keuntungan MAX. 10%

Keuntungan MAX. 10% Jumlah Cat Genteng Supralux

Cat Besi Sekelas SEIV

Jumlah Meni Besi

Jumlah Rol Cat

(45)

Mandor 0.0100 Org 85,000.00 850.00 161,215.00 0.10 16,121.50 177,336.50

K 1 1 M2 PASANG BEKISTING UNTUK TANGGA

0.0030

M2 1,400,000.00 4,200.00 0.4000

Kg 21,000.00 8,400.00 Kayu Balok Albasiah 0.0015 M3 1,400,000.00 2,100.00 Polywood Tebal 9 mm 0.3500 Lbr 240,000.00 84,000.00 Dolken Kayu Galam 8 - 10/14 m 2.0000 Btg 24,000.00 48,000.00 Pekerja 0.3200 Org 46,000.00 14,720.00 Tukang Kayu 0.3300 Org 65,000.00 21,450.00 Kepala Tukang 0.0330 Org 80,000.00 2,640.00 Mandor 0.0060 Org 85,000.00 510.00 186,020.00 0.10 18,602.00 204,622.00

K 2 1 M3 MEMBUAT BETON BERTULANG DENGAN MUTU K 275 6.4600

Zak 70,000.00 452,200.00 0.5200

M3 220,000.00 114,400.00 Batu Pecah 0.7800 M3 165,000.00 128,700.00 Besi Beton Polos 275.0000 Kg 10,000.00 2,750,000.00 Kawat Beton 2.2500 Kg 30,000.00 67,500.00 Pekerja 6.0000 Org 46,000.00 276,000.00 Tukang Batu 1.0000 Org 63,250.00 63,250.00 Kepala Tukang 0.1000 Org 75,000.00 7,500.00 Mandor 0.3000 Org 85,000.00 25,500.00 3,885,050.00 0.10 388,505.00 4,273,555.00

K 3 1 M2 PASANG LANTAI KERAMIK TANGGA UKURAN 40 X 40 cm 1.0100

Bh 94,000.00 94,940.00 Jumlah

K. PEKERJAAN TANGGA

Kayu Terentang Albasiah, Papan Paku Biasa 2 - 5 cm Jumlah Keuntungan MAX. 10% Jumlah Jumlah Keuntungan MAX. 10% Semen PC Pasir Beton Jumlah Keuntungan MAX. 10% Jumlah Granito 40 x 40 cm

(46)

0.1600

Zak 70,000.00 11,200.00 Pasir Pasang 0.0300 M3 210,000.00 6,300.00 Semen Warna 0.0130 Kg 80,000.00 1,040.00 Pekerja 0.2500 Org 46,000.00 11,500.00 Tukang Batu 0.4000 Org 63,250.00 25,300.00 Kepala Tukang 0.0120 Org 75,000.00 900.00 Mandor 0.00125 Org 85,000.00 106.25 151,286.25 0.10 15,128.63 166,414.88

K 4 1 M1 PASANG HANDRAILING TANGGA

0.3100 Btg 25,000.00 7,750.00 0.1750 Btg 25,000.00 4,375.00 Angkur Baut 8.0000 Kg 5,000.00 40,000.00 Pekerja 1.0000 Org 46,000.00 46,000.00 Tukang Besi Terampil 1.0000 Org 60,000.00 60,000.00 Kepala Tukang 0.1000 Org 75,000.00 7,500.00 Mandor 0.0500 Org 85,000.00 4,250.00 169,875.00 0.10 16,987.50 186,862.50 K 5 1 M1 PASANG STAIRNOSING 1.0100 M1 13,500.00 0.1600 Zak 70,000.00 Pasir Pasang 0.0300 M3 210,000.00 6,300.00 Semen Warna 0.0130 Kg 80,000.00 1,040.00 Pekerja 0.2500 Org 46,000.00 11,500.00 Tukang Besi 0.4000 Org 60,000.00 24,000.00 Kepala Tukang 0.0120 Org 75,000.00 900.00 Mandor 0.00125 Org 85,000.00 106.25 43,846.25 0.10 4,384.63 48,230.88

Tiang Besi Hollow 4 x 4 cm Handrail Besi Hollow

Jumlah Keuntungan MAX. 10% Jumlah Stairnosing Fiber

Semen PC ( abu - abu )

Jumlah Semen PC ( abu - abu )

Jumlah Keuntungan MAX. 10% Jumlah

Keuntungan MAX. 10% Jumlah

Referensi

Dokumen terkait

Berdasarkan mean pada item (x2.4)tentang Merupakan cara yang sangat efektif berinteraksi dengan berbagai user dalam forum Kaskus sehingga dapat digambarkan user

Expression of p53, bcl-2 and Ki-67 in cervical intraepithelial neoplasia and invasive squamous cell carcinoma of the uterine cervix.. Cancer of the cervix - from

- OTONOMI DAERAH, PEMERINTAHAN UMUM, ADMINISTRASI KEUANGAN DAERAH, PERANGKAT DAERAH, KEPEGAWAI. Ringkasan Anggaran Pendapatan

Pemeriksaan laboratorium yang paling penting pada bayi dengan ikterus yang lebih dari dua minggu ialah bilirubin direk.. Jika bilirubin direk meningkat, maka harus dilakukan

Kegiatan pemilihan bahan adalah pemilihan bahan yang akan digunakan untuk pembuatan sistem pengereman agar dapat dikembangkan masih menggunakan sistem gesek

Dampak umum jangka pendek pengelolaan program Abdimas-Bansos UT Th 2011-2013 cukup positif terhadap anggota komunitas masyarakat penerima manfaat, baik fisiologis

Skripsi yang berjudul "PENJATUHAN SANKSI PIDANA TERHADAP TINDAK PIDANA DI BIDANG LALU LINTAS (STUDI KASUS DI WILAYAH HUKUM PENGADILAN NEGERI DEMAK)" ini secara

Berdasarkan hasil analisa terhadap penilaian penerapan SMK3 di proyek pembangunan Gedung Living World Pekanbaru, untuk hasil penilaian kuisioner yang ditujukan kepada