PEKERJAAN : LANJUTAN PEMBANGUNAN KANTOR KELURAHAN REMPOA
HARGA SATUAN JUMLAH
Rp. Rp.
1 PEKERJAAN LANTAI 1 I. PEKERJAAN PERSIAPAN :
1 - 1.00 ls 10,000,000.00 10,000,000.00
2 - 1.00 ls 10,000,000.00 10,000,000.00
3 I. 009 189.00 m2 2,085.36 394,132.36
4 I. 011 111.50 m1 42,852.37 4,778,039.26
5 I. 002 1.00 unit 245,284.79 245,284.79
6 I. 020 189.00 m2 4,346.31 821,452.59
7 - 1.00 ls 5,000,000.00 5,000,000.00
8 I. 005 1.00 set 5,678,969.08 5,678,969.08
9 I. 017 24.00 m2 359,992.57 8,639,821.79
10 I. 012 56.00 m1 427,537.91 23,942,123.19
11 - 1.00 ls 13,000,000.00 13,000,000.00
82,499,823.07
II, PEKERJAAN TANAH :
-1 III. 003 98.70 m3 30,170.48 2,977,826.38
2 VI. 001 3.12 m3 238,660.42 744,620.51
3 VI. 001 20.25 m3 238,660.42 4,832,873.51
4 III. 015 71.15 m3 221,907.40 15,788,711.79
5 III. 013 59.68 m3 14,458.83 862,903.00
25,206,935.18
III. PEK. BETON BERTULANG :
-1 XIX. 003 1.64 m3 1,391,006.89 2,281,251.30
2 XIX. 163 9.83 m3 5,389,243.79 52,976,266.47
3 XIX. 163 0.39 m3 5,389,243.79 2,101,805.08
4 XIX. 163 0.25 m3 5,389,243.79 1,347,310.95
5 XIX. 166 6.69 m3 4,995,782.64 33,421,785.88
6 XIX. 164 1.11 m3 4,599,555.39 5,105,506.49
7 XIX. 005 24.03 m3 793,315.71 19,063,376.61
8 XIX. 182 8.88 m3 5,721,551.84 50,807,380.37
9 XIX. 183 1.72 m3 5,454,928.44 9,382,476.92
10 XIX. 183 0.86 m3 5,454,928.44 4,691,238.46
11 XIX. 170 1.58 m3 4,585,423.22 7,244,968.69
12 XIX. 170 0.88 m3 4,585,423.22 4,035,172.43
13 XIX. 172 3.76 m3 3,728,192.91 14,018,005.33
14 XIX. 172 0.14 m3 3,728,192.91 521,947.01
15 XIX. 001 62.00 m2 99,317.93 6,157,711.66
213,156,203.65
IV. PEKERJAAN PASANGAN :
-1 VII. 014 39.03 m3 733,302.47 28,620,795.45
2 VII. 006 7.81 m3 330,379.26 2,580,262.02
3 VIII. 005 314.96 m2 94,247.76 29,684,274.28
4 VIII. 004 8.00 m2 96,270.48 770,163.82
5 X. 006 569.52 m2 38,585.52 21,975,226.60
6 X. 017 60.40 m2 58,869.15 3,555,696.95
7 - 46.28 m2 240,950.00 11,151,166.00
8 XI. 012 191.29 m2 108,780.76 20,808,671.31
9 XI. 012 28.69 m2 108,780.76 3,120,919.96
10 XI. 017 18.30 m2 107,141.88 1,960,696.44
11 XI. 018 4.65 m2 83,613.26 388,801.67
12 XI. 018 1.40 m2 83,613.26 117,058.57
13 XVII. 001 2.00 bh 2,203,175.75 4,406,351.50
14 XVII. 002 2.00 bh 560,225.08 1,120,450.15
15 XVII. 006 1.00 bh 1,581,398.86 1,581,398.86
16 XVII. 007 2.00 bh 507,752.89 1,015,505.78
17 - 4.00 bh 100,000.00 400,000.00
133,257,439.35
V. PEK.KUSEN,PINTU & JENDELA+PLAFOND :
-1 - 6.00 Unit 2,783,966.29 16,703,797.76
2 - 1.00 Unit 4,298,332.59 4,298,332.59
3 - 4.00 Unit 609,880.54 2,439,522.14
4 - 9.00 Unit 1,773,657.21 15,962,914.88
5 - 1.00 Unit 2,297,371.87 2,297,371.87
6 - 2.00 Unit 3,683,911.10 7,367,822.21
7 - 1.00 Unit 8,327,266.90 8,327,266.90
8 - 11.00 Unit 957,710.21 10,534,812.36
9 XII. 027 4.65 m2 87,974.84 409,083.02
10 - 191.29 m2 121,488.28 23,239,493.73
11 - 205.60 m1 27,000.00 5,551,200.00
97,131,617.46
Pas. Penutup Plafond Gypsum=9 mm Rangka Hollow 20x40 Pas. List Profil Plafond Gypsum 7 CM
Kusen Pintu jendela J 1 Kusen Pintu jendela J 2 (loket) Kusen Pintu jendela J 3 Kusen Pintu jendela J 4 Kusen Pintu jendela BV
Pas. Penutup Plafond GRC t=5 mm Rangka Hollow 20x40 Pas. Bak Mandi Fiber Glass
Pas. Jet Washer
Kusen pintu P 1 Kusen pintu P 2 Kusen pintu P 3
Pas. Keramik Dinding 20/25 Corak/Warna setara Masterina KW II Pas. Keramik Lantai 20/20 Corak/Warna Setara Masterina KW I Pas. Keramik Meja Pantry 20/20 Corak/Warna Setara Masterina KW I Pas. Closet Duduk Setara HCG
Pas. Closet Jongkok Setara Toto Pas. Kitchen Zink lengkap Accessories Pas. Plesteran Biasa 1:5 + Acian t=15 cm Pas. Plesteran Biasa 1:5 + Acian t=25 cm Pas. Batu Alam Andesit
Pas. Lantai Keramik 40/40 warna setara Masterina KW I Pas. Plint Lantai 20/40 warna setara Masterina KW I Pek. Meja Pantry, Beton Ready Mix K-225, Besi = 88kg/m3 Pek. Rabat Beton t= 7cm
Pas. Pondasi Batu Belah 1:5 Pas. Batu Kosong Pas. Dinding Bata a.d 1:5 Pas. Bata Rolag
Pek. Kolom Utama 30/30, Beton Site Mix K-225, Besi = 195 Kg, (K1) Pek. Kolom Teras 20/100, Beton Site Mix K-225, Besi = 120kg, (K2) Pek. Kolom Teras 20/50, Beton Site Mix K-225, Besi = 120kg, (K3) Pek. Kolom Praktis 15/15, Beton Site Mix K-175, Besi = 153kg, (KP) Pek. Balok Lintel 12/15, Beton Site Mix K-175, Besi = 153kg, (BL) Pek. Plat Canopy, Beton Ready Mix K-225, Besi = 88kg/m3 Pek. Pondasi Plat Beton Setempat,besi 250 kg, K1 Pek. Pondasi Plat Beton Setempat,besi 250 kg, k2 Pek. Pondasi Plat Beton Setempat,besi 250 kg, k3
Pek. Sloof Beton , uk 20x30 Beton Site Mix K-175, Besi = 200 kg, Bekisting Papan 50% Pek. Sloof Beton , 15x20 Beton Site Mix K-175, Besi = 154 kg, Bekisting Papan 50% Pek. Beton Tumbuk Lantai Kerja 1:3:5
Urugan Pasir Bawah Pondasi t:10 cm. Urugan Pasir Bawah Lantai
Urugan Tanah Merah dipadatkan tiap 20 Cm Urugan Tanah Kembali Bekas galian
Pek. Lantai Kerja Pondasi 1:2:4 Pek. Direksikeet & Gudang Pek. Gudang Kerja Pek. Pagar Pengaman Proyek Pek.Bongkaran bangunan eksisting
Galian Tanah Pondasi
Mobilisasi dan Demobilisasi Alat Bantu Pek. Pengukuran kembali / Pematokan Pekerjaan Bouwplank
Papan Nama Proyek Uk. 60x90 cm Pembersihan Lokasi/Perataan Tanah Pengadaan Air Kerja dan Listrik Kerja
NO. URAIAN PEKERJAAN ANA- VOLUME
LISA
Biaya Pengurusan IMB
DAFTAR KUANTITAS DAN HARGA
PEMERINTAH KOTA TANGERANG SELATAN DINAS TATA KOTA, BANGUNAN DAN PEMUKIMAN
VI. TANGGA :
-1 XIX. 171 2.51 m3 4,331,560.21 10,872,216.12
2 XIX. 167 0.35 m3 3,907,079.01 1,367,477.65
3 XIX. 167 0.19 m3 3,907,079.01 742,345.01
4 XI. 012 19.68 m2 108,780.76 2,140,805.33
5 18.30 m1 450,000.00 8,235,000.00
23,357,844.11
VII. PEKERJAAN INSTALASI LISTRIK & AIR :
-1 - 1.00 Bh 14,000,000.00 14,000,000.00
2 1.00 ls 12,000,000.00 12,000,000.00
3 XXVII. 004 25.00 ttk 348,459.72 8,711,493.06
4 XXVII. 003 11.00 ttk 282,594.91 3,108,544.01
5 XXVII. 004 4.00 ttk 348,459.72 1,393,838.89
6 - 14.00 bh 100,000.00 1,400,000.00
7 - 12.00 bh 200,000.00 2,400,000.00
8 - 5.00 bh 100,000.00 500,000.00
9
-XVII. 016 6.00 m1 17,691.10 106,146.62 XVII. 017 10.00 m1 22,172.08 221,720.84 XVII. 015 29.50 m1 15,201.67 448,449.25
10
-XVII. 021 25.00 m1 77,152.24 1,928,805.96 XVII. 020 45.50 m1 44,608.61 2,029,691.62
11 XVII. 023 8.00 bh 48,652.95 389,223.58
12 XVII. 025 5.00 bh 37,922.95 189,614.76
13 XVII. 029 1.00 unit 3,441,253.50 3,441,253.50
14 - 1.00 ttk 8,500,000.00 8,500,000.00
15 - 1.00 bh 3,000,000.00 3,000,000.00
63,768,782.09
VIII. PEKERJAAN LAIN - LAIN
-1 XVIII. 012 629.92 m2 28,959.02 18,241,868.40
2 XVIII. 034 195.94 m2 29,904.43 5,859,473.98
3 XVIII. 034 14.39 m2 29,904.43 430,324.74
4 - 46.28 m2 42,000.00 1,943,760.00
5 - 28.10 m2 45,000.00 1,264,500.00
6 - 126.00 m1 60,000.00 7,560,000.00
7 - 32.50 m1 60,000.00 1,950,000.00
8 - 1.00 bh 3,000,000.00 3,000,000.00
9 - 30.00 hrf 150,000.00 4,500,000.00
10 - 20.00 hrf 225,000.00 4,500,000.00
49,249,927.12
Huruf Stainless Steel t=20 cm Huruf Stainless Steel t=30 cm Pengecatan List Plafon Setara Metrolith Pengecatan Batu Alam Dengan Vernis Water Profing Atap dan Canopy Plin Ban-Banan t= 10 Cm Tali Air Profil t= 3 cm
Lambang Daerah Tangerang Selatan Pas. Floor Drain Ø 3" Lokal Pek. Septictank uk 2x1.5x1.5
Pek. Pengeboran Sumur + Pompa Listrik Pek. Water Torn 1000 L+ Instalasi
Pengecatan Dinding setara ICI/Dulux Warna Biasa Pengecatan Plafon Setara Metrolith
Pipa PVC 1" Pipa PVC 1/2"
Instalasi Air Kotor & Air Hujan Pipa PVC 3"
Pipa PVC 2 1/2" Pas. Kran Air
Pek. Instalasi Stop Kontak AC 3x2.5 mm Eterna Pas. Lampu Neon Phillips TL 40 Watt Pas. Lampu Down Light PL 20 Watt Pas. Lampu Neon Phillips PL 20 Watt Instalasi Air Bersih
Pipa PVC 3/4"
Pas. Keramik 40/40 Setara Masterina Warna KWI Pas.Hand Railling Tangga Pipa Stainless Steel Ø 2.5"
Box Panel Groub
Biaya Sambung Listrik PLN 10000 Watt Pek. Instalasi Titik Lampu 3x2.5 mm Eterna Pek. Instalasi Stop Kontak 2x2.5 mm Eterna Pek. Plat Tangga Beton Ready Mix K 225 Besi 160 kg
HARGA SATUAN JUMLAH
Rp. Rp.
2 PEKERJAAN LANTAI 2
I. PEK. BETON BERTULANG :
1 XIX. 171 22.62 m3 4,331,560.21 97,979,891.88
2 XIX. 182 6.62 m3 5,721,551.84 37,876,673.20
3 XIX. 180 0.53 m3 5,454,928.44 2,891,112.07
4 XIX. 169 1.18 m3 4,585,423.22 5,410,799.40
5 XIX. 169 0.71 m3 4,585,423.22 3,255,650.49
6 XIX. 172 1.20 m3 3,728,192.91 4,473,831.49
7 XIX. 172 0.14 m3 3,728,192.91 521,947.01
8 XIX. 176 12.80 m3 4,642,826.08 59,428,173.88
9 XIX. 176 2.43 m3 4,393,766.31 10,676,852.13
10 XIX. 167 1.46 m3 3,907,079.01 5,704,335.35
11 XIX. 178 5.04 m3 5,582,446.25 28,135,529.12
256,354,796.03
II. PEKERJAAN PASANGAN :
-1 VIII. 005 415.47 m2 94,247.76 39,157,116.57
2 X. 006 770.54 m2 38,585.52 29,731,688.28
3 X. 017 60.40 m2 58,869.15 3,555,696.95
4 XI. 012 191.29 m2 108,780.76 20,808,671.31
5 XI. 012 28.69 m2 108,780.76 3,120,919.96
6 XI. 017 4.65 m2 107,141.88 498,209.75
7 XI. 018 5.85 m2 83,613.26 489,137.58
8 XI. 018 1.40 m2 83,613.26 117,058.57
9 XVII. 001 3.00 bh 2,203,175.75 6,609,527.25
10 XVII. 002 1.00 bh 560,225.08 560,225.08
11 XVII. 006 1.00 bh 1,581,398.86 1,581,398.86
12 XVII. 007 2.00 bh 507,752.89 1,015,505.78
13 - 4.00 bh 100,000.00 400,000.00
107,645,155.93
III. PEK.KUSEN,PINTU & JENDELA+PLAFOND :
-1 - 3.00 Unit 2,783,966.29 8,351,898.88
2 - 1.00 Unit 4,298,332.59 4,298,332.59
3 - 4.00 Unit 609,880.54 2,439,522.14
4 - 18.00 Unit 1,773,657.21 31,925,829.76
5 - 12.00 Unit 957,710.21 11,492,522.57
6 XII. 027 5.85 m2 87,974.84 514,652.83
7 - 191.29 m2 121,488.28 23,239,493.73
8 - 186.95 m1 27,000.00 5,047,650.00
87,309,902.51
IV. PEKERJAAN INSTALASI LISTRIK & AIR :
-1 XXVII. 004 25.00 ttk 348,459.72 8,711,493.06
2 XXVII. 003 13.00 ttk 282,594.91 3,673,733.83
3 XXVII. 004 7.00 ttk 348,459.72 2,439,218.06
4 - 20.00 bh 100,000.00 2,000,000.00
5 - 11.00 bh 200,000.00 2,200,000.00
6 - 4.00 bh 100,000.00 400,000.00
7
-XVII. 016 6.00 m1 17,691.10 106,146.62 XVII. 017 10.00 m1 22,172.08 221,720.84 XVII. 015 15.00 m1 15,201.67 228,025.04
8
-XVII. 021 13.00 m1 77,152.24 1,002,979.10 XVII. 020 45.50 m1 44,608.61 2,029,691.62
9 XVII. 023 6.00 bh 48,652.95 291,917.68
10 XVII. 025 4.00 bh 37,922.95 151,691.81
23,456,617.66
V. PEKERJAAN ATAP
-1 XIV. 087 290.40 m2 249,618.84 72,489,312.47
2 - 290.40 m2 95,888.16 27,845,921.66
3 - 290.40 m2 45,000.00 13,068,000.00
4 - 47.00 m1 85,000.00 3,995,000.00
5 XIII. 044 15.00 m1 133,970.23 2,009,553.49
6 - 36.80 m2 86,000.00 3,164,800.00
7 XIV. 058 70.00 m1 52,872.05 3,701,043.65
8 XIX. 171 0.12 m3 4,331,560.21 519,787.22
9 - 34.00 m1 52,000.00 1,768,000.00
128,561,418.50
VI PEKERJAAN LAIN - LAIN
-1 XVIII. 012 830.94 m2 28,959.02 24,063,211.40
2 XVIII. 028 21.00 m2 44,959.79 944,155.66
3 XVIII. 034 197.14 m2 29,904.43 5,895,359.29
4 XVIII. 034 13.09 m2 29,904.43 391,448.99
5 - 1.00 ls 2,500,000.00 2,500,000.00
6 - 1.00 ls 5,000,000.00 5,000,000.00
7 - 1.00 ls 15,000,000.00 15,000,000.00
8 Instalasi Penangkal Petir + Grounding - 1.00 ls 14,500,000.00 14,500,000.00
68,294,175.34
Pengecatan List Plafon Setara Metrolith Pelaporan , As-Build Drawing dan Dokumentasi Pek. Perapihan & Pembersihan.
Profil Ornamen Betawi
Pas. Lisplank GRC, Superplank, lebar 30 cm, tebal 5 mm Pek. Dak Atap Beton Beton Ready Mix K 225 Besi 160 kg Pas. Talang Air PVC Kotak 6"
Pengecatan Dinding setara ICI/Dulux Warna Biasa Pengecatan Listplank Setara Glotek
Pengecatan Plafon Setara Metrolith
Pas. Rangka Baja Atap Baja Ringan Berikut Gording, Kaso & Reng Pas. Genteng Model Metal Type butiran
Pas. Alumunium Foil
Pas. Nok Genteng Model Metal Type butiran Pas. Talang Patahan Atap Pakai Karpet Water Profing Atap dan Canopy Pipa PVC 1/2"
Instalasi Air Kotor & Air Hujan Pipa PVC 3"
Pipa PVC 2 1/2" Pas. Kran Air
Pas. Floor Drain Ø 3" Lokal Pas. Lampu Neon Phillips TL 40 Watt Pas. Lampu Down Light PL 20 Watt Pas. Lampu Neon Phillips PL 20 Watt Instalasi Air Bersih
Pipa PVC 3/4" Pipa PVC 1"
Pas. Penutup Plafond GRC t=5 mm Rangka Hollow 20x40 Pas. Penutup Plafond Gypsum=9 mm Rangka Hollow 20x40 Pas. List Profil Plafond Gypsum 7 CM
Pek. Instalasi Titik Lampu 3x2.5 mm Eterna Pek. Instalasi Stop Kontak 2x2.5 mm Eterna Pek. Instalasi Stop Kontak AC 3x2.5 mm Eterna Kusen pintu P 1
Kusen pintu P 2 Kusen pintu P 3 Kusen Pintu jendela J 1 Kusen Pintu jendela BV
Pas. Keramik Meja Pantry 20/20 Corak/Warna Setara Masterina KW I Pas. Closet Duduk Setara HCG
Pas. Closet Jongkok Setara Toto Pas. Kitchen Zink lengkap Accessories Pas. Bak Mandi Fiber Glass
Pas. Jet Washer
Pas. Plesteran Biasa 1:5 + Acian t=15 cm Pas. Plesteran Biasa 1:5 + Acian t=25 cm
Pas. Lantai Keramik 40/40 warna setara Masterina KW I Pas. Plint Lantai 20/40 warna setara Masterina KW I
Pas. Keramik Dinding 20/25 Corak/Warna setara Masterina KW II Pas. Keramik Lantai 20/20 Corak/Warna Setara Masterina KW I
Pek. Meja Pantry, Beton Ready Mix K-225, Besi = 88kg/m3, Bekisting Multiplex 12 mm Pek. Balok Induk Struktur25/40, Beton Ready Mix K-225, Besi = 150 kg/m3, (BI) Pek. Balok Anak Struktur20/30, Beton Ready Mix K-225, Besi = 150 kg/m3, (BA) Pek. Ring Balok 15/20, Beton Ready Mix K-225, Besi = 175 Kg, (RB1) Pek. Ring Balok 20/40, Beton Ready Mix K-225, Besi =212 Kg, (RB2)
Pas. Dinding Bata a.d 1:5
Pek. Dak Lantai Beton Ready Mix K 225 Besi 160 kg Pek. Kolom Utama 30/30, Beton Site Mix K-225, (K1)
Pek. Kolom Teras 15/50, Beton Site Mix K-225, Besi = 153kg, (k2) Pek. Kolom Praktis 15/15, Beton Site Mix K-175, (kp)
Pek. Balok Lintel 15/15, Beton Site Mix K-175, (bl)
Pek. Plat Canopy, Beton Ready Mix K-225, Besi = 88kg/m3, Bekisting Multiplex 12 mm
NO. URAIAN PEKERJAAN ANA- VOLUME
REKAPITULASI TOTAL : LANTAI 1
I. PEKERJAAN PERSIAPAN Rp. 82,499,823.07
II. PEKERJAAN TANAH Rp. 25,206,935.18
III. PEKERJAAN BETON Rp. 213,156,203.65
IV. PEKERJAAN PASANGAN Rp. 133,257,439.35
V. PEK.KUSEN,PINTU & JENDELA + PLAFOND Rp. 97,131,617.46
VI. PEKERJAAN TANGGA Rp. 23,357,844.11
VII. PEKERJAAN INSTALASI LISTRIK Rp. 63,768,782.09
VIII. PEKERJAAN LAIN-LAIN : Rp. 49,249,927.12
JUMLAH. Rp. 687,628,572.03
LANTAI 2
I. PEK. BETON BERTULANG Rp. 256,354,796.03
II. PEKERJAAN PASANGAN Rp. 107,645,155.93
III. PEKERJAAN KUSEN,PINTU & JENDELA+PLAFOND : Rp. 87,309,902.51
IV. PEKERJAAN INSTALASI LISTRIK & AIR : Rp. 23,456,617.66
V PEKERJAAN ATAP : Rp. 128,561,418.50
VI. PEKERJAAN LAIN-LAIN : Rp. 68,294,175.34
JUMLAH. Rp. 671,622,065.96
REKAPITULASI : LANTAI 1 + LANTAI 2
REKAPITULASI LANTAI 1 Rp. 687,628,572.03
REKAPITULASI LANTAI 2 Rp. 671,622,065.96
JUMLAH TOTAL Rp. 1,359,250,637.99
PPN 10 % Rp. 135,925,063.80
JUMLAH TOTAL Rp. 1,495,175,701.79 1,500,000,000.00
DIBULATKAN. Rp. 1,495,175,000.00 4,825,000.00