Unit Kerja Dinas Pertanian Kab. Kediri Status : Januari 2009
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya
eqv(US$)
Metode
Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego
Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING
23,000,000
2,706
1 GD 1 Pengadaan Laptop & Camera 23,000,000 2,706 NS Post Review Mar-09 Mar-09 Apr-09 30 hari
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
Sub Total Keg Cat 3 (Loan + Pend) - -Sub Total Keg Selain Cat 3 (Loan) 23,000,000 2,705.88 TOTAL KEGIATAN I (Loan + Pend) 23,000,000 2,705.88 TOTAL KEGIATAN II (GOI-PF/APBD) - 0 Goods (Category 2)
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
Unit Kerja Dinas Pertanian, Peternakan & Perikanan Kab. Mojokerto Status : Januari 2009
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya
eqv(US$)
Metode
Pengadaan Post/ Prior Review
Pengumum an Pengadaan
Pemasukan
Penawaran Eval/ Nego
Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING
29,000,000
3,412
1 GD 1 Pengadaan Wireless 6,000,000 706 NS Post Review Apr-09 May-09 May-09 15 hari
2 GD 2 Pengadaan Alat Pengukur PH Tanah 16,000,000 1,882 NS Post Review Apr-09 May-09 May-09 15 hari
3 GD 3 Pengadaan GPS 7,000,000 824 NS Post Review Apr-09 May-09 May-09 15 hari
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
1 Pengadaan Wireless 6,110,000 PL Apr-09 May-09 May-09 15 hari
2 Pengadaan Alat Pengukur PH Tanah 8,000,000 PL Apr-09 May-09 May-09 15 hari
Sub Total Keg Cat 3 (Loan + Pend) -
-Sub Total Keg Selain Cat 3 (Loan) 29,000,000 3,412
TOTAL KEGIATAN I (Loan + Pend) 29,000,000 3,412
TOTAL KEGIATAN II (GOI-PF/APBD)
Unit Kerja Dinas Pertanian & Perkebunan Kab. Jombang Status : Januari 2009
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya
eqv(US$)
Metode
Pengadaan Post/ Prior Review
Pengumum an Pengadaan
Pemasukan
Penawaran Eval/ Nego
Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING
23,000,000
2,706
1 GD 1 Pengadaan Laptop 23,000,000 2,706 NS Post Review Apr-09 Apr-09 May-09 20 hari
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
1 Pengadaan Printer 1 Unit 4,000,000 PL Apr-09 May-09 May-09 9-Jun 30 hari
2 Pengadaan Kamera Digital 1 Unit 4,500,000 PL Apr-09 May-09 May-09 9-Jun 30 hari
Sub Total Keg Cat 3 (Loan + Pend) -
-Sub Total Keg Selain Cat 3 (Loan) 23,000,000 2,706
TOTAL KEGIATAN I (Loan + Pend) 23,000,000 2,706
TOTAL KEGIATAN II (GOI-PF/APBD) 8,500,000
Unit Kerja Dinas Pertanian, Perkebunan & Peternakan Kab. Sidoarjo Status : Januari 2009
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya
eqv(US$)
Metode
Pengadaan Post/ Prior Review
Pengumum an Pengadaan
Pemasukan
Penawaran Eval/ Nego
Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING
23,000,000
2,706
1 GD 1 Pengadaan Laptop & Printer 23,000,000 2,706 NS Post Review Mar-09 Apr-09 Apr-09 30 hari
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
Sub Total Keg Cat 3 (Loan + Pend) -
-Sub Total Keg Selain Cat 3 (Loan) 23,000,000 2,706
TOTAL KEGIATAN I (Loan + Pend) 23,000,000 2,706
TOTAL KEGIATAN II (GOI-PF/APBD)
Unit Kerja Dinas Pertanian Kabupaten Pasuruan Status : Januari 2009
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya
eqv(US$)
Metode
Pengadaan Post/ Prior Review
Pengumum an Pengadaan
Pemasukan
Penawaran Eval/ Nego
Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING
23,000,000
2,706
1 GD 1 Pengadaan Laptop & Camera 23,000,000 2,706 NS Post Review Mar-09 Mar-09 Apr-09 30 hari
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
Sub Total Keg Cat 3 (Loan + Pend) -
-Sub Total Keg Selain Cat 3 (Loan) 23,000,000 2,706
TOTAL KEGIATAN I (Loan + Pend) 23,000,000 2,706
TOTAL KEGIATAN II (GOI-PF/APBD) -
Unit Kerja Dinas Pertanian Kabupaten Jember Status : Januari 2009
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya
eqv(US$)
Metode
Pengadaan Post/ Prior Review
Pengumum an Pengadaan
Pemasukan
Penawaran Eval/ Nego
Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING
15,000,000
1,765
1 GD 1 ATK 15,000,000 1,765 NS Post Review Mar-09 Mar-09 Apr-09 30 hari
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
1 Penyusunan RTTG 35,000,000 PL Mar-09 Mar-09 Apr-09 3 bulan
2 Penyusunan RTTD 35,000,000 PL Mar-09 Mar-09 Apr-09 3 bulan
Sub Total Keg Cat 3 (Loan + Pend) -
-Sub Total Keg Selain Cat 3 (Loan) 15,000,000 1,765
TOTAL KEGIATAN I (Loan + Pend) 15,000,000 1,765
TOTAL KEGIATAN II (GOI-PF/APBD)
Unit Kerja Dinas Pertanian Tanaman Pangan & Holtikultura Kab. Banyuwangi Status : Januari 2009
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya
eqv(US$)
Metode
Pengadaan Post/ Prior Review
Pengumum an Pengadaan
Pemasukan
Penawaran Eval/ Nego
Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING
31,000,000
3,647
1 GD 1 Pengadaan Laptop, Handycam, & Camera Digital 31,000,000 3,647 NS Post Review Mar-09 Mar-09 Apr-09 30 hari
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
1 Pengadaan APPO 120,000,000 PU Mar-09 Mar-09 Mar-09 Apr-09 3 bulan
2 ATK 610,000 PL Mar-09 Mar-09 Mar-09 Apr-09 4 bulan
3 Pupuk Organik 12,000,000 PL Mar-09 Mar-09 Mar-09 Apr-09 5 bulan
4 Benih Padi 450,000 PL Mar-09 Mar-09 Mar-09 Apr-09 6 bulan
5 Pupuk Ponska 1,050,000 PL Mar-09 Mar-09 Mar-09 Apr-09 7 bulan
Sub Total Keg Cat 3 (Loan + Pend) -
-Sub Total Keg Selain Cat 3 (Loan) 31,000,000 3,647
TOTAL KEGIATAN I (Loan + Pend) 31,000,000 3,647
TOTAL KEGIATAN II (GOI-PF/APBD) 134,110,000
Unit Kerja Dinas Pertanian Tanaman Pangan & Holtikultura Kab. Bondowoso Status : Januari 2009
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya
eqv(US$)
Metode
Pengadaan Post/ Prior Review
Pengumum an Pengadaan
Pemasukan
Penawaran Eval/ Nego
Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING
23,000,000
2,706
1 GD 1 Pengadaan Laptop & Camera 23,000,000 2,706 NS Post Review Mar-09 Mar-09 Apr-09 30 hari
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
1 Alat Tulis Kantor (ATK) 6,697,500 PL Mar-09 Mar-09 Mar-09 Apr-09 3 Bulan
Sub Total Keg Cat 3 (Loan + Pend) -
-Sub Total Keg Selain Cat 3 (Loan) 23,000,000 2,706
TOTAL KEGIATAN I (Loan + Pend) 23,000,000 2,706
TOTAL KEGIATAN II (GOI-PF/APBD)
Unit Kerja Dinas Pertanian Kab. Situbondo Status Januari 2009
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya
eqv(US$)
Metode
Pengadaan Post/ Prior Review
Pengumum an Pengadaan
Pemasukan
Penawaran Eval/ Nego
Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan : Permasalah an/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING
27,000,000
3,176
1 GD 1 Belanja barang : NS Post Review Feb-09 Feb-09 Feb-09 Mar-09 30 hari
Pengadaan Laptop 20,000,000 2,353
Pengadaan Handycam 7,000,000 824
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
1 Belanja Modal : PL Feb-09 Feb-09 Feb-09 Mar-09 30 hari
Pengadaan Kamera Digital 4,500,000
Pengadaan Printer 4,000,000
Pengadaan Infokus/LCD 10,000,000
Sub Total Keg Cat 3 (Loan + Pend) -
-Sub Total Keg Selain Cat 3 (Loan) 27,000,000 3,176
TOTAL KEGIATAN I (Loan + Pend) 27,000,000 3,176
TOTAL KEGIATAN II (GOI-PF/APBD) 18,500,000
Unit Kerja Dinas Pertanian & Peternakan Kab. Bangkalan Status : Januari 2009
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya
eqv(US$)
Metode
Pengadaan Post/ Prior Review
Pengumum an Pengadaan
Pemasukan
Penawaran Eval/ Nego
Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING
23,000,000
2,706
1 GD 1 Pengadaan Laptop 23,000,000 2,706 NS Post Review Apr-09 Apr-09 May-09 30 hari
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
1 Pengadaan Printer 5,500,000 PL Apr-09 Apr-09 Apr-09 May-09 30 hari
2 Pengadaan Camera Digital 5,000,000 PL Apr-09 Apr-09 Apr-09 May-09 30 hari
3 Penyusunan RTTG 24,250,000 PL Apr-09 Apr-09 Apr-09 May-09 60 hari
4 Penyusunan RTTD 2,450,000 PL Apr-09 Apr-09 Apr-09 May-09 60 hari
Sub Total Keg Cat 3 (Loan + Pend) -
-Sub Total Keg Selain Cat 3 (Loan) 23,000,000 2,706
TOTAL KEGIATAN I (Loan + Pend) 23,000,000 2,706
TOTAL KEGIATAN II (GOI-PF/APBD) 37,200,000
Unit Kerja Dinas Pertanian Kabupaten Pamekasan Status : Januari 2009
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya
eqv(US$)
Metode
Pengadaan Post/ Prior Review
Pengumuma n Pengadaan
Pemasukan
Penawaran Eval/ Nego
Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING
23,000,000
2,706
1 GD 1 Pengadaan Laptop 23,000,000 2,706 NS Post Review 03-Jun-09 12-Jun-09 15-Jun-09 90 hari
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
1 Pengadaan Sarana & Prasarana Produksi : PL 03-Mar-09 10-Mar-09 12-Mar-09 13-Mar-09 45 hari
- Benih Padi 600,000
- Pupuk Organik 35,000,000
- Alat Semai 2,500,000
2 Kamera Digital 4,000,000 PL 06-Apr-09 09-Apr-04 13-Apr-08 14/16/09 30 hari
Sub Total Keg Cat 3 (Loan + Pend) -
-Sub Total Keg Selain Cat 3 (Loan) 23,000,000 2,706
TOTAL KEGIATAN I (Loan + Pend) 23,000,000 2,706
TOTAL KEGIATAN II (GOI-PF/APBD) 42,100,000
Unit Kerja Dinas Pertanian Kabupaten Sumenep Status Januari 2009 No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya
eqv(US$)
Metode
Pengadaan Post/ Prior Review
Pengumum an Pengadaan
Pemasukan
Penawaran Eval/ Nego
Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan : Permasala han/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING
23,000,000
2,706
1 GD 1 Pengadaan Laptop 23,000,000 2,706 NS Post Review Feb-09 Feb-09 Mar-09 Mar-09 30 hari
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
1 Bantuan Teknis Sistem Stimulan : Benih, Pupuk Pestisida, Saprodi, Modal Kerja Dll. 39,750,000 2 Perjalanan Dinas Dalam Daerah 7,800,000
Sub Total Keg Cat 3 (Loan + Pend) - -Sub Total Keg Selain Cat 3 (Loan) 23,000,000 2,706 TOTAL KEGIATAN I (Loan + Pend) 23,000,000 2,706 TOTAL KEGIATAN II (GOI-PF/APBD) 47,550,000 -Goods (Category 2)
Unit Kerja Dinas Pertanian Kabupaten Probolinggo Status : Januari 2009
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya
eqv(US$)
Metode
Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego
Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalaha n/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING
Tidak Ada Pengadaan
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
Sub Total Keg Cat 3 (Loan + Pend) -
-Sub Total Keg Selain Cat 3 (Loan) -
-TOTAL KEGIATAN I (Loan + Pend) -