PAKET : II
PEKERJAAN : BENDUNG TAWANGSARI VOLUME : 1 Unit
PROYEK/BAGIAN PROYEK : PIKITRING JBN/PLTA AMPELGADING
TAHUN ANGGARAN : 2009
HARGA JUMLAH
No. SATUAN VOLUME SATUAN HARGA
(Rp) (Rp)
A Mobilisasi dan Demobilisasi
00 Mobilisasi ls 1.00 18,900,000.00 18,900,000.00
01 Demobilisasi ls 1.00 18,900,000.00 18,900,000.00
Sub. Total A 37,800,000.00
B Saluran Pengelak
1 10 Pembersihan Lokasi m2 100.00 2,563 256,250.00
2 20 Galian Tanah dengan Alat Berat m3 300.00 28,442 8,532,675.00
3 30 Timbunan tanah dipadatkan m3 751.00 35,301 26,511,051.00
4 40 Timbunan Karung Pasir m3 517.00 93,588 48,384,737.50
Sub. Total B 83,684,713.50
C Bendung Tawangsari
1 61 Pembersihan Lokasi m2 100.00 2,563 256,250.00
2 70 Galian Tanah dengan Alat Berat m3 500.00 28,442 14,221,125.00 3 80 Timbunan Kembali m3 351.00 11,688 4,102,312.50
4 90 Pasangan batu kali 1pc:3ps m3 2,390.00 398,294 951,922,062.50
5 100 Beton K.175 (termasuk bikisting) m3 3.40 1,258,197 4,277,868.10
6 110 Penulangan kg 374.00 15,910 5,950,461.55
7 130 Plesteran m2 27.00 21,065 568,755.00
8 140 Bronjong (2 x 1 x 0,5) m3 24.00 235,680 5,656,310.00 9 150 Siaran 1pc:3ps m2 560.00 12,730 7,128,800.00
Sub. Total C 993,827,694.65
D Saluran Pengarah dan Kantong Lumpur
1 170 Pembersihan Lokasi m2 154.00 2,563 394,625.00 2 180 Galian Tanah dengan Alat Berat m3 3,410.00 28,442 96,988,072.50
3 190 Pasangan batu kali 1pc:3ps m3 594.00 398,294 236,586,487.50
4 200 Plesteran m2 58.00 21,065 1,221,770.00
5 210 Siaran 1pc:3ps m2 139.18 12,730 1,771,760.33
6 220 Beton K.175 (termasuk bikisting) m3 6.85 1,258,197 8,618,646.03
7 230 Penulangan kg 753.50 15,910 11,988,429.89
Sub. Total D 357,569,791.25
Total ( A + B +C + D ) 1,472,882,199.40
PPn 10% 147,288,219.94
JUMLAH BIAYA KESELURUHAN 1,620,170,419.34
PEMBULATAN 1,620,170,000.00
RENCANA ANGGARAN BIAYA
No. MACAM ALAT / KAPASITAS SATUAN SEWA (Rp)
1 2 3 4
1 Back Hoe,7 ton Jam 160,000.00
2 Bulldozer Jam 143,000.00
3 Concrete Mixer Jam 60,000.00
4 Concrete Vibrator Jam 21,450.00
5 Dump Truck , 4 ton Jam 78,650.00
6 Water Tank Jam 65,780.00
DAFTAR HARGA SATUAN DASAR SEWA ALAT PEKERJAAN KONSTRUKSI TAHUN ANGGARAN 2004
DAFTAR HARGA SATUAN DASAR MATERIAL PEKERJAAN KONSTRUKSI
HARGA
NO. URAIAN SATUAN SATUAN
(Rp)
1 2 3 4
1 Batu Pecah 15/20 M3 90,000
2 Besi Beton Ulir Kg 6,375
3 Gravel 2/3 M3 90,000
4 Karung pasir bh 1,500
5 Kawat Beton Kg 7,000
6 Kawat Galvano 4 mm Kg 7,000
7 Kayu Meranti Balok/Papan M3 1,100,000
8 Paku kayu kg 8,000 9 Pasir Cor M3 85,000 10 Pasir Pasang m3 85,000 11 Pasir Urug m3 63,000 12 Semen PC @ 50 kg zak 28,500 13 Solar Ltr 1,650
UPAH (Rp.)
1 2 3 4
1 Mandor org/hr 37,500.00
2 Kepala Tukang Kayu org/hr 33,000.00
3 Kepala Tukang Batu org/hr 33,000.00
4 Kepala Tukang Besi org/hr 33,000.00
5 Tukang Kayu org/hr 28,600.00
6 Tukang Batu org/hr 27,500.00
7 Tukang Besi org/hr 26,400.00
8 Tukang Cat org/hr 25,000.00
9 Tukang Pipa org/hr 26,400.00
10 Tukang Anyam org/hr 26,400.00
11 Tk.bongkar bekisting org/hr 21,875.00
12 Pekerja org/hr 21,875.00
13 Pengemudi org/hr 31,250.00
14 Operator org/hr 35,000.00
NOMOR URAIAN SATUAN
DAFTAR HARGA SATUAN DASAR UPAH TENAGA PEKERJAAN KONSTRUKSI TAHUN ANGGARAN 2003
PAKET : II
PEKERJAAN : BENDUNG TAWANGSARI VOLUME : 1 Unit
TAHUN ANGGARAN : 2009
No. SATUAN VOLUME Tenaga Durasi Durasi Dibulatkan
(kelompok/hari) (hari) (hari)
A Mobilisasi dan Demobilisasi
00 Mobilisasi ls 1.00 1.00 5.00 5.00 01 Demobilisasi ls 1.00 1.00 5.00 5.00 B Saluran Pengelak
10 Pembersihan Lokasi m2 100.00 10.00 1.00 1.00 20 Galian Tanah dengan Alat Berat m3 300.00 1.00 3.00 3.00 30 Timbunan Tanah dipadatkan m3 751.00 1.00 3.76 4.00 40 Timbunan Karung Pasir m3 517.00 35.00 10.34 11.00 C Bendung Tawangsari
61 Pembersihan Lokasi m2 125.00 10.00 1.25 2.00 70 Galian Tanah dengan Alat Berat m3 500.00 1.00 5.00 5.00 80 Timbunan Kembali m3 351.00 15.00 11.70 12.00 90 Pasangan batu kali 1pc:3ps m3 2,390.00 20.00 158.94 159.00 100 Beton K.175 (termasuk bikisting) m3 3.40 6.00 3.40 4.00 110 Penulangan kg 374.00 6.00 3.74 4.00 130 Plesteran m2 27.00 3.00 3.60 4.00 140 Bronjong (2 x 1 x 0,5) m3 24.00 5.00 10.40 11.00 150 Siaran m2 560.00 15.00 13.44 14.00 D Saluran Pengarah dan Kantong Lumpur
170 Pembersihan Lokasi m2 154.00 10.00 1.54 2.00 180 Galian Tanah dengan Alat Berat m3 3,410.00 1.00 34.10 35.00 190 Pasangan batu kali 1pc:3ps m3 594.00 20.00 39.50 40.00 200 Plesteran m2 58.00 3.00 7.73 8.00 210 Siaran 1pc:3ps m2 139.18 3.00 16.70 17.00 220 Beton K.175 (termasuk bikisting) m3 6.85 6.00 6.85 7.00 230 Penulangan kg 753.50 7.00 6.46 7.00
JENIS PEKERJAAN
PROYEK/BAGIAN PROYEK : PIKITRING JBN/PLTA AMPELGADING
No. Item Pekerjaan Satuan Harga Satuan
1 Alat bantu dan pengamanan ls 11,496,500
2 Besi Siku (100 x 75 x 7) kg 9,500
3 Beton K 125/Lantai Kerja m3 465,350
4 Beton K.175 (termasuk bikisting) m3 1,258,197 5 Beton K.225 (termasuk bikisting) m3 1,357,120 6 Shootcrete lindungan tebing m3 465,350
7 Bronjong (2 x 1 x 0,5) m3 235,680
8 Clearing dan Stripping m2 15,434
9 Galian tanah m3 23,000
10 Galian Tanah dengan Alat Berat m3 28,442
11 Jacking Boring m 6,211,000
12 Kanopy Atap seng gelombang ls 400,000
13 Lapisan pasir m3 82,538
14 Pasangan batu kali 1pc:3ps m3 398,294
15 Peil Scale bh 150,000
16 Pembersihan Lokasi m2 2,563
17 Pembongkaran ls 3,000,000
18 Pengadaan Pipa steel kg 15,000
19 Pengeringan/dewatering lks 2,000,000
20 Penulangan kg 15,910
21 Penutup Man Hole kg 16,598
22 Plesteran m2 21,065
23 Pompa grouting lks 2,000,000
24 Sambungan Las bh 1,065,000
25 Siaran 1pc:3ps unit 12,730
26 Support Block bh 516,208
27 Tangga Besi Beton D32 kg 15,910
28 Temporary Sheet Pile, Panjang 6 meter m 150,000 29 Timbunan tanah dipadatkan m3 35,301
30 Timbunan Karung Pasir m3 93,588
31 Timbunan Kembali m3 11,688
Nomor analisa :
Jenis Pekerjaan : Pembersihan
Satuan : m2
Harga satuan ( Rp. ) : 2,562.50
Dasar analisa : Referensi
HARGA SAT. JML.HARGA
Rp. Rp. 1. BAHAN Sub Total 1 -2. TENAGA Pekerja org/hr 0.1000 21,875 2,187.50 Mandor org/hr 0.0100 37,500 375.00 Sub Total 2 2,562.50 3. ALAT Sub Total 3 -2,562.50 2,562.50 TOTAL
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa :
Jenis Pekerjaan : Galian tanah ( dg.alat)
Satuan : m3
Harga satuan ( Rp.) : 28,442
Dasar analisa : Taksiran
HARGA SAT. JML.HARGA
(Rp) (Rp) 1. BAHAN Solar ltr 3.5400 1,650 5,841 Sub Total 1 5,841 2. TENAGA Mandor org/hr 0.0100 37,500 375 Operator org/hr 0.0400 35,000 1,400 Pekerja org/hr 0.1300 21,875 2,844 Pengemudi org/hr 0.0400 31,250 1,250 Sub Total 2 5,869 3. ALAT
Back Hoe,7 ton jam 0.0800 160,000 12,800 Dump Truck , 4 ton jam 0.0500 78,650 3,933
Sub Total 3 16,733
28,442 TOTAL
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa :
Jenis Pekerjaan : Timbunan Karung Pasir
Satuan : m3
Harga satuan ( Rp.) : 93,588
Dasar analisa : DD.Cost.Es.no.39
HARGA SAT. JML.HARGA
Rp. Rp. 1. BAHAN Pasir urug m3 1.0000 63,000 63,000.0 Karung Pasir bh 10.0000 1,500 15,000.0 Sub Total 1 78,000.0 2. TENAGA
Tukang batu org/hr 0.0100 27,500 275.0 Pekerja org/hr 0.7000 21,875 15,312.5 Sub Total 2 15,587.5 3. ALAT Sub Total 3 -93,587.5 TOTAL
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa :
Jenis Pekerjaan : Timbunan kembali
Satuan : m3
Harga satuan ( Rp.) : 11,688
Dasar analisa : BOW
HARGA SAT. JML.HARGA
Rp. Rp. 1. BAHAN Sub Total 1 -2. TENAGA Mandor org/hr 0.0200 37,500 750 Pekerja org/hr 0.5000 21,875 10,938 Sub Total 2 3. ALAT Sub Total 3 -11,688 TOTAL
ANALISA HARGA SATUAN PEKERJAAN
0.5000 Pekerja 0.0200 Mandor = 1 m3/hari 175.5000 Pekerja 7.0200 Mandor = 351 m3/hari 1
Nomor analisa :
Jenis Pekerjaan : Pasangan batu kali 1pc:3ps
Satuan : m3
Harga satuan ( Rp.) : 398,294
Dasar analisa : DD.Cost.Es.no11
HARGA SAT. JML.HARGA
Rp. Rp. 1. BAHAN Batu Pecah 15/20 m3 1.2000 90,000 108,000 Semen PC @ 50 kg zak 5.0000 28,500 142,500 Pasir pasang m3 0.4800 85,000 40,800 Sub Total 1 291,300 2. TENAGA Mandor org/hr 0.1300 37,500 4,875 Kepala tukang besi org/hr 0.2000 33,000 6,600 Tukang batu org/hr 0.6700 27,500 18,425 Pekerja org/hr 1.3300 21,875 29,094
Sub Total 2 58,994
3. ALAT
Concrete Mixer jam 0.8000 60,000 48,000
Sub Total 3 48,000
398,294 TOTAL
Nomor analisa :
Jenis Pekerjaan : Beton K.175 (termasuk bikisting)
Satuan : m3
Harga satuan ( Rp.) : 1,258,197
Dasar analisa : Cost.E no.8
HARGA SAT. JML.HARGA
Rp. Rp. A Beton 1. BAHAN Gravel 2/3 m3 0.8200 90,000 73,800 Pasir Cor m3 0.5400 85,000 45,900 Semen PC @ 50 kg zak 6.5800 28,500 187,530 Sub Total 1 307,230 2. TENAGA Mandor org/hr 0.3000 37,500 11,250 Kepala tukang batu org/hr 0.1000 33,000 3,300 Tukang Batu org/hr 1.0000 27,500 27,500 Pekerja org/hr 6.0000 21,875 131,250
Sub Total 2 173,300
3. ALAT
Concrete mixer Jam 0.6400 60,000 38,400 Concrete vibrator Jam 0.7700 21,450 16,517
Sub Total 3 54,917
B Bekisting
1 Bahan
Kayu meranti balok/papan m3 0.4000 1,100,000 440,000 Paku kayu kg 4.0000 8,000 32,000
Sub Total 4 472,000
2 Tenaga
Mandor org/hr 0.1000 37,500 3,750 Kepala tukang kayu org/hr 0.5000 33,000 16,500 Tukang kayu org/hr 5.0000 28,600 143,000 TK.bongkar bekisting org/hr 2.0000 21,875 43,750 Pekerja org/hr 2.0000 21,875 43,750
Sub Total 5 250,750
1,258,197
TOTAL
Nomor analisa :
Jenis Pekerjaan : Penulangan
Satuan : kg
Harga satuan ( Rp.) : 15,910
Dasar analisa : DD.Cost.Es.no7
HARGA SAT. JML.HARGA
Rp. Rp.
1. BAHAN
Besi Beton Ulir kg 110 6,375 701,250
Kawat beton kg 2 7,000 14,000
Sub Total 1 715,250
2. TENAGA
Mandor org/hr 0.4500 37,500 16,875 Kepala tukang besi org/hr 2.2500 33,000 74,250 Tukang besi org/hr 6.0000 26,400 158,400 Pekerja org/hr 6.0000 21,875 131,250
Sub Total 2 380,775
3. ALAT
Alat bantu 15% Tenaga 57,116
Sub Total 3 57,116
1,591,033
15,910 Jumlah Biaya per 100 kg
Harga Satuan per 1 kg
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa :
Jenis Pekerjaan : Plesteran t=1,5 cm , 1pc:4ps
Satuan : m2
Harga satuan ( Rp.) : 21,065
Dasar analisa : BOW.G50.p
HARGA SAT. JML.HARGA
Rp. Rp. 1. BAHAN Semen PC @ 50 kg zak 0.1300 28,500 3,705 Pasir Pasang m3 0.02 85,000 1,700 Sub Total 1 5,405 2. TENAGA Mandor org/hr 0.0200 37,500 750 Kepala tukang batu org/hr 0.0200 33,000 660 Tukang batu org/hr 0.2000 27,500 5,500 Pekerja org/hr 0.4000 21,875 8,750 Sub Total 2 15,660 3. ALAT Sub Total 3 -21,065 TOTAL
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa :
Jenis Pekerjaan : Siaran 1pc:2ps
Satuan : m2
Harga satuan ( Rp.) : 12,730
Dasar analisa : BOW. G.51c
HARGA SAT. JML.HARGA
Rp. Rp. 1. BAHAN Pasir Pasang m3 0.0100 85,000 850 Semen PC @ 50 kg zak 0.1100 28,500 3,135 Sub Total 1 850 2. TENAGA Mandor org/hr 0.0100 37,500 375 Kepala tukang batu org/hr 0.0100 33,000 330 Tukang batu org/hr 0.1200 27,500 3,300 Pekerja org/hr 0.3600 21,875 7,875 Sub Total 2 11,880 3. ALAT Sub Total 3 -12,730 TOTAL
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa :
Jenis Pekerjaan : Pasang Bronjong 0,5x1,0x2,0
Satuan : 3 m3
Harga satuan ( Rp.)/m3 : 235,680
Dasar analisa : DD.Cost.Es.no.14
HARGA SAT. JML.HARGA
Rp. Rp. 1. BAHAN Kawat Galvano 4 mm Kg 30.0000 7,000 210,000 Batu Pecah 15/20 m3 3.0000 90,000 270,000 Sub Total 1 480,000 2. TENAGA Mandor org/hr 0.1600 37,500 6,000 Tukang Anyam org/hr 2.5000 26,400 66,000 Pekerja org/hr 6.5000 21,875 142,188
Sub Total 2 214,188
3. ALAT
Alat Bantu 6% dari Tenaga jam 0.0600 214,188 12,851
Sub Total 3 12,851
707,039
Per m3 235,680
TOTAL per 3 m3
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa :
Jenis Pekerjaan Timbunan tanah dengan alat
Satuan : m3
Harga satuan ( Rp.) : 35,301
Dasar analisa : Detail design ( Cost estimate ) no.4
HARGA SAT. JML.HARGA
Rp. Rp. volume
50
1. BAHAN Okt Nop
Solar ltr 2.1600 1,650 3,564 108.00 Sub Total 1 3,564 2. TENAGA Mandor org/hr 0.0100 37,500 375 0.50 Operator org/hr 0.0800 35,000 2,800 4.00 Pekerja org/hr 0.0800 21,875 1,750 4.00 Pengemudi org/hr 0.0400 31,250 1,250 2.00 Sub Total 2 6,175 3. ALAT Bulldozer jam 0.0200 143,000 2,860 1.00 Back Hoe,7 ton jam 0.0400 160,000 6,400 2.00 Dump Truck , 4 ton jam 0.0400 78,650 3,146 2.00 Water Tank jam 0.2000 65,780 13,156 10.00
Sub Total 3 25,562
35,301 TOTAL
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa :
Jenis Pekerjaan : Beton K.225 (termasuk bikisting)
Satuan : m3
Harga satuan ( Rp.) : 1,357,120
Dasar analisa : DD.Cost.Es.no.9
HARGA SAT. JML.HARGA
Rp. Rp. A Beton 1. BAHAN Gravel 2/3 m3 0.8200 90,000 73,800 Pasir Cor m3 0.5400 85,000 45,900 Semen PC @ 50 kg zak 8.2000 28,500 233,700 Sub Total 1 353,400 2. TENAGA Mandor org/hr 0.3000 37,500 11,250 Kepala tukang batu org/hr 0.1000 33,000 3,300 Tukang Batu org/hr 1.0000 27,500 27,500 Pekerja org/hr 6.0000 21,875 131,250
Sub Total 2 173,300
3. ALAT
Concrete mixer jam 0.7400 60,000 44,400 Concrete vibrator jam 0.9100 21,450 19,520
Sub Total 3 63,920
B Bekisting
1 Bahan
Kayu meranti balok/papan m3 0.4000 1,100,000 440,000 Paku kayu kg 4.0000 8,000 32,000
Sub Total 4 472,000
2 Tenaga
Mandor org/hr 0.1000 37,500 3,750 Kepala tukang kayu org/hr 0.5000 33,000 16,500 Tukang kayu org/hr 5.0000 28,600 143,000 Tk.bongkar bekisting org/hr 4.0000 21,875 87,500 Pekerja org/hr 2.0000 21,875 43,750
Sub Total 5 294,500
1,357,120
TOTAL
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa :
Jenis Pekerjaan : Beton K 125/Lantai Kerja
Satuan : m3
Harga satuan ( Rp.) : 465,350
Dasar analisa : BOW.G44
HARGA SAT. JML.HARGA
Rp. Rp. 1. BAHAN Gravel 2/3 m3 0.8200 90,000 73,800 Pasir Cor m3 0.5400 85,000 45,900 Semen PC @ 50 kg zak 4.7000 28,500 133,950 Sub Total 1 253,650 2. TENAGA Mandor org/hr 0.3000 37,500 11,250 Kepala tukang batu org/hr 0.1000 33,000 3,300 Tukang Batu org/hr 1.0000 27,500 27,500 Pekerja org/hr 6.0000 21,875 131,250
Sub Total 2 173,300
3. ALAT
Concrete mixer Jam 0.6400 60,000 38,400
Sub Total 3 38,400
465,350 TOTAL
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa :
Jenis Pekerjaan : Galian Batu dengan Alat Berat
Satuan : m3
Harga satuan ( Rp.) : #VALUE!
Dasar analisa : Cost.E.no3
HARGA SAT. JML.HARGA
Rp. Rp. 1. BAHAN Solar ltr 3.9400 1,650 6,501 Sub Total 1 6,501 2. TENAGA Mandor org/hr 0.0100 37,500 375 Operator org/hr 0.0400 35,000 1,400 Pekerja org/hr 0.1300 21,875 2,844 Pengemudi org/hr 0.0400 31,250 1,250 Sub Total 2 5,869 3. ALAT
Back Hoe,7 ton jam 0.0800 160,000 12,800 Dump Truck , 4 ton jam 0.0500 78,650 3,933
Hard Rock Breaker jam 0.0400 x #VALUE!
Sub Total 3 #VALUE!
#VALUE! TOTAL
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa :
Jenis Pekerjaan : Lapisan pasir
Satuan : m3
Harga satuan ( Rp.) : 82,538
Dasar analisa : BOW. A 18
HARGA SAT. JML.HARGA
Rp. Rp. 1. BAHAN Pasir urug m3 1.2000 63,000 75,600 Sub Total 1 75,600 2. TENAGA Mandor org/hr 0.0100 37,500 375 Pekerja org/hr 0.3000 21,875 6,563 Sub Total 2 6,938 3. ALAT Sub Total 3 82,538 TOTAL
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa :
Jenis Pekerjaan : Base Course
Satuan : m3
Harga satuan ( Rp.) : #VALUE!
Dasar analisa : DD.Cost.Es.no25
HARGA SAT. JML.HARGA
Rp. Rp.
1. BAHAN
Batu Pecah 5/7 Kg 0.5100 x #VALUE!
Batu Pecah 15/20 m3 0.6800 90,000 61,200
Sub Total 1 #VALUE!
2. TENAGA Mandor org/hr 0.9300 37,500 34,875 Operator org/hr 0.0200 35,000 700 Pekerja org/hr 0.9500 21,875 20,781 Sub Total 2 56,356 3. ALAT
Road Roller 10 Ton jam 0.010 x #VALUE!
Dump Truck , 4 ton jam 0.051 78,650 4,011
Sub Total 3 #VALUE!
#VALUE! TOTAL
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa :
Jenis Pekerjaan : Sub Base Course
Satuan : m3
Harga satuan ( Rp.) : #VALUE!
Dasar analisa : DD.Cost.Es.no25
HARGA SAT. JML.HARGA
Rp. Rp.
1. BAHAN
Sirtu M3 1.2000 x #VALUE!
Sub Total 1 #VALUE!
2. TENAGA Mandor org/hr 0.0200 37,500 750.00 Operator org/hr 0.1800 35,000 6,300.00 Pengemudi org/hr 0.0200 31,250 625.00 Pekerja org/hr 0.1800 21,875 3,937.50 Sub Total 2 11,612.50 3. ALAT
Back Hoe,7 ton jam 0.0200 160,000 3,200.00 Bulldozer jam 0.0400 143,000 5,720.00 Dump Truck , 4 ton jam 0.1200 78,650 9,438.00 Water Tank jam 0.0200 65,780 1,315.60
Sub Total 3 19,673.60
#VALUE! TOTAL
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa :
Jenis Pekerjaan : Clearing dan Stripping
Satuan : 4 m2
Harga satuan ( Rp.)/m2 : 15,434
Dasar analisa : DD.Cost.Es.no.18
HARGA SAT. JML.HARGA
Rp. Rp. 1. BAHAN Sub Total 1 2. TENAGA Mandor org/hr 0.0100 37,500 375 Operator org/hr 0.0200 35,000 700 Pekerja org/hr 0.4000 21,875 8,750 Sub Total 2 9,825 3. ALAT Bulldozer jam 0.0030 143,000 429
Road roller 10 ton jam 0.0800 x #VALUE!
Dump Truck , 4 ton jam 0.6600 78,650 51,909
Sub Total 3 51,909
61,734
15,434 Harga satuan per m2
Harga satuan per 4 m2
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa : 24
Jenis Pekerjaan : Hand Rail dia. 2 "
Satuan : m
Harga satuan ( Rp.) : #VALUE!
Dasar analisa : DD.Cost.Es.no25
HARGA SAT. JML.HARGA
Rp. Rp.
1. BAHAN
Pipa besi GIP 2' btg 0.9000 x #VALUE!
Sambungan Pipa M3 0.3000 x #VALUE!
Sub Total 1 #VALUE!
2. TENAGA
Mandor org/hr 0.0900 37,500 3,375 Kepala tukang besi org/hr 0.3800 33,000 12,540 Tukang besi org/hr 1.5000 26,400 39,600 Pekerja org/hr 0.9000 21,875 19,688
Sub Total 2 75,203
3. ALAT
Alat bantu= 6% x upah jam 0.2100 4,512 948
Sub Total 3 948
#VALUE! TOTAL
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa :
Jenis Pekerjaan : Bahu Jalan
Satuan : m3
Harga satuan ( Rp.) : #VALUE!
Dasar analisa : DD.Cost.Es.no23
HARGA SAT. JML.HARGA
Rp. Rp.
1. BAHAN
Tanah Pilihan M3 1.2000 x #VALUE!
Sub Total 1 #VALUE!
2. TENAGA Mandor org/hr 0.0200 37,500 750 Operator org/hr 0.1800 35,000 6,300 Pengemudi org/hr 0.0200 31,250 625 Pekerja org/hr 0.1800 21,875 3,938 Sub Total 2 11,613 3. ALAT
Back Hoe,7 ton jam 0.0200 160,000 3,200 Bulldozer jam 0.0400 143,000 5,720 Dump Truck , 4 ton jam 0.1200 78,650 9,438 Water Tank jam 0.0200 65,780 1,316
Sub Total 3 19,674
#VALUE! TOTAL
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa : 30
Jenis Pekerjaan : Peil Scale
Satuan : bh
Harga satuan ( Rp.) : #VALUE!
Dasar analisa : DD.Cost.Es.no.25
HARGA SAT. JML.HARGA
Rp. Rp.
1. BAHAN
Semen PC @ 50 kg zak 0.3000 28,500 8,550
Pasir Pasang m3 0.0200 85,000 1,700
Plamir tembok kg 0.6500 x #VALUE!
Cat Emco kg 0.0400 x #VALUE!
Minyak Cat liter 0.4700 x #VALUE!
Sub Total 1 #VALUE!
2. TENAGA
Mandor org/hr 0.0100 37,500 375 Kepala tukang batu org/hr 0.0200 33,000 660 Tukang batu org/hr 0.2000 27,500 5,500 Pekerja org/hr 0.4000 21,875 8,750
Sub Total 2 15,285
3. ALAT
Alat bantu= 6% x upah jam 0.2100 917 193
Sub Total 3 193
#VALUE! TOTAL
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa :
Jenis Pekerjaan : Penetrasi
Satuan : m3
Harga satuan ( Rp.) : #VALUE!
Dasar analisa : DD.Cost.Es.no24
HARGA SAT. JML.HARGA
Rp. Rp.
1. BAHAN
Batu Kerikil M3 0.2100 x #VALUE!
Pasir Cor M3 0.2100 85,000 17,850
Aspal Curah Kg 90.0000 x #VALUE!
Sub Total 1 #VALUE!
2. TENAGA Mandor org/hr 0.9300 37,500 34,875 Operator org/hr 0.0200 35,000 700 Pekerja org/hr 0.3000 21,875 6,563 Sub Total 2 42,138 3. ALAT
Road Roller 10 Ton jam 0.2100 x #VALUE!
Sub Total 3 #VALUE!
#VALUE! TOTAL
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa : 11
Jenis Pekerjaan : Pasang bouwplank
Satuan : m
Harga satuan ( Rp.) : 18,680
Dasar analisa : Taksiran
HARGA SAT. JML.HARGA
Rp. Rp.
1. BAHAN
Kayu meranti Balok/Papan m3 0.0070 1,409,700 9,867.90
Paku kayu kg 0.1540 8,570 1,319.78
Sub Total 1 11,187.68
2. TENAGA
Mandor org/hr 0.0150 37,500 562.50
Tukang Kayu org/hr 0.0550 28,600 1,573.00
Pekerja org/hr 0.1500 21,875 3,281.25
Sub Total 2 5,416.75
3. ALAT
- Alat bantu = 6% x upah kerja 325.01
Sub Total 3 0.00
16,604.43
12.50% 2,075.55
TOTAL
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa :
Jenis Pekerjaan : Galian tanah biasa
Satuan : m3
Harga satuan ( Rp.) : 23,000
Dasar analisa : DD.Cost.Es.no.1
HARGA SAT. JML.HARGA
Rp. Rp. 1. BAHAN Sub Total 1 -2. TENAGA Mandor org/hr 0.0300 37,500 1,125 Pekerja org/hr 1.0000 21,875 21,875 Sub Total 2 23,000 3. ALAT Sub Total 3 23,000 TOTAL
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa :
Jenis Pekerjaan : Gorong-gorong dia.1,5 m
Satuan : m
Harga satuan ( Rp.) : #VALUE!
Dasar analisa : DD.Cost.Es.no22
HARGA SAT. JML.HARGA
Rp. Rp. 1. BAHAN Beton K.125 m3 0.5500 465,350 255,943 Sub Total 1 255,943 2. TENAGA Mandor org/hr 0.0200 37,500 750 Operator org/hr 0.8200 35,000 28,700 Pekerja org/hr 2.7400 21,875 59,938 Sub Total 2 89,388 3. ALAT
Stamper jam 0.1800 x #VALUE!
Dump truck , 4 ton jam 0.5160 78,650 40,583
Sub Total 3 #VALUE!
#VALUE!
D/2004/analis-04xls
Biaya per m
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa : 3
Jenis Pekerjaan : Gorong-gorong dia.1 m
Satuan : m
Harga satuan ( Rp.) : #VALUE!
Dasar analisa : DD.Cost.Es.no22
HARGA SAT. JML.HARGA
Rp. Rp. 1. BAHAN Beton K.125 m3 0.3800 465,350 176,833 Sub Total 1 176,833 2. TENAGA Mandor org/hr 0.0100 37,500 375 Operator org/hr 0.5700 35,000 19,950 Pekerja org/hr 2.2900 21,875 50,094 Sub Total 2 70,419 3. ALAT
Stamper jam 0.1500 x #VALUE!
Dump truck , 4 ton jam 0.4300 78,650 33,820
Sub Total 3 #VALUE!
#VALUE! Biaya per m
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa :
Jenis Pekerjaan : Gorong-gorong dia.0,2 m
Satuan : m
Harga satuan ( Rp.) : #VALUE!
Dasar analisa : DD.Cost.Es.no.19
HARGA SAT. JML.HARGA
Rp. Rp.
1. BAHAN
Buis beton dia.0,20m-1m m 1.0000 x #VALUE!
Pasir urug m3 0.0200 63,000 1,260
Sub Total 1 #VALUE!
2. TENAGA
Mandor org/hr 0.0100 37,500 375 Tukang batu org/hr 0.2500 27,500 6,875 Pekerja org/hr 0.5700 21,875 12,469
Sub Total 2 19,719
3. ALAT
Stamper jam 0.1500 x #VALUE!
Sub Total 3 #VALUE!
#VALUE! Biaya per m
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa : 21
Jenis Pekerjaan : Screen Gravel
Satuan : m3
Harga satuan ( Rp.) : 114,938
Dasar analisa : BOW.A18B
HARGA SAT. JML.HARGA
Rp. Rp. 1. BAHAN Gravel 2/3 m3 1.2000 90,000 108,000 Sub Total 1 108,000 2. TENAGA Mandor org/hr 0.0100 37,500 375 Pekerja org/hr 0.3000 21,875 6,563 Sub Total 2 6,938 3. ALAT Sub Total 3 -114,938 TOTAL
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa : 20
Jenis Pekerjaan : Drain hole dia.2"-0,6 m
Satuan : bh
Harga satuan ( Rp.) : #VALUE!
Dasar analisa : Taksiran
HARGA SAT. JML.HARGA
Rp. Rp.
1. BAHAN
Pipa PVC 2' x 4 m m 0.1500 x #VALUE!
Ijuk kg 0.5000 x #VALUE!
Sub Total 1 #VALUE!
2. TENAGA
Mandor org/hr 0.0100 37,500 375 Pekerja org/hr 0.1500 21,875 3,281
Sub Total 2 3,656
3. ALAT
Alat bantu 6% tenaga hr 0.0600 3,656 219
Sub Total 3 219
#VALUE! TOTAL
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa :
Jenis Pekerjaan : Drai hole dia 2"- 3 m
Satuan : bh
Harga satuan ( Rp.) : #VALUE!
Dasar analisa : Taksiran
HARGA SAT. JML.HARGA
Rp. Rp.
1. BAHAN
Pipa PVC 2' x 4 m m 1.0000 x #VALUE!
Ijuk kg 0.5000 x #VALUE!
Sub Total 1 #VALUE!
2. TENAGA
Mandor org/hr 0.0100 37,500 375 Pekerja org/hr 0.1500 21,875 3,281
Sub Total 2 3,656
3. ALAT
Alat bantu 6% tenaga hr 0.0600 3,656 219.375
Sub Total 3 219.375
#VALUE! TOTAL
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa :
Jenis Pekerjaan : Gebalan rumput
Satuan : m2
Harga satuan ( Rp.) : #VALUE!
Dasar analisa : DD.Cost.Es.no5
HARGA SAT. JML.HARGA
Rp. Rp.
1. BAHAN
Rumput m2 1 x #VALUE!
Bambu buah 0.05 x #VALUE!
Sub Total 1 #VALUE!
2. TENAGA
Mandor org/hr 0.0100 37,500 375 Pekerja org/hr 0.1500 21,875 3,281
Sub Total 2 3,656
3. ALAT
Alat bantu 6% tenaga hr 0.0600 3,656 219 Sub Total 3
#VALUE! TOTAL
ANALISA HARGA SATUAN PEKERJAAN
PAKET : III
PEK. : BENDUNG GROJOGAN DAN SALURAN HANTAR II
NO. URAIAN SATUAN JUMLAH JARAK H. SAT. JML. HARGA
Km Rp./Km
A PERALATAN
1 Back hoe 0,40 m3 + Trailer ( 2bh) Unit 4 75 25,000 7,500,000 2 Bulldozer 6 t + Trailer ( 2 bh ) Unit 4 75 25,000 7,500,000
3 Dump Truck Unit 2 75 10,000 1,500,000
4 Road Roller Unit 2 75 15,000 2,250,000
5 Water Tank 4000 ltr Unit 2 75 10,000 1,500,000
6 Concrete Vibrator + Truck Unit 2 75 10,000 1,500,000 7 Concrete Mixer + Truck Unit 2 75 10,000 1,500,000 23,250,000 B FASILITAS 1 Direksi keet m2 20 300,000 6,000,000 2 Gudang m2 24 275,000 6,600,000 12,600,000 C TENAGA
1 Site Manager orang 1 x 400,000 400,000
2 Pelaksana orang 4 x 300,000 1,200,000 3 Mandor orang 16 x 250,000 4,000,000 3 Mekanik orang 2 x 250,000 500,000 4 Tukang orang 25 x 225,000 5,625,000 5 Administrasi orang 4 x 225,000 900,000 6 Logistik orang 4 x 225,000 900,000 7 Pekerja orang 75 x 200,000 15,000,000 28,525,000 TOTAL ( A + B + C ) 64,375,000
PAKET : V. KOLAM PENAMPUNG
NO. URAIAN SATUAN JUMLAH JARAK H. SAT. JML. HARGA
Km Rp./Km
A PERALATAN
1 Back hoe 0,40 m3 + Trailer Unit 2 75 25,000 3,750,000 2 Bulldozer 6 t + Trailer Unit 2 75 25,000 3,750,000
3 Dump Truck Unit 2 75 10,000 1,500,000
4 Road Roller Unit 2 75 15,000 2,250,000
5 Water Tank 4000 ltr Unit 2 75 10,000 1,500,000
6 Concrete Vibrator + Truck Unit 2 75 10,000 1,500,000 7 Concrete Mixer + Truck Unit 2 75 -
-8 Hard rock breaker Unit 2 75 10,000 1,500,000
9 Stamper Unit 2 75 10,000 1,500,000 17,250,000 B FASILITAS 1 Direksi keet m2 20 300,000 6,000,000 2 Gudang m2 24 275,000 6,600,000 Total 12,600,000 C TENAGA 1 Pelaksana orang 2 x 300,000 600,000 2 Mandor orang 3 x 250,000 750,000 3 Mekanik orang 1 x 250,000 250,000 4 Tukang orang 3 x 225,000 675,000 5 Administrasi orang 1 x 225,000 225,000 6 Logistik orang 1 x 225,000 225,000 7 Pekerja orang 20 x 200,000 4,000,000 6,725,000 TOTAL ( A + B + C ) 36,575,000
D.Analis-04 dup.04 revisi
PAKET : I
PEK. : BASE CAMP
NO. URAIAN SATUAN JUMLAH JARAK H. SAT. JML. HARGA
Km Rp./Km
A PERALATAN
1 Back hoe 0,40 m3 + Trailer Unit 2 75 25,000 3,750,000 2 Bulldozer 6 t + Trailer Unit 2 75 25,000 3,750,000
3 Dump Truck Unit 2 75 10,000 1,500,000
4 Vibration Roller Unit 2 75 15,000 2,250,000
5 Water Tank 4000 ltr Unit 2 75 10,000 1,500,000
7 Concrete Mixer + Truck Unit 2 75 10,000 1,500,000 14,250,000 B FASILITAS 1 Direksi keet m2 20 300,000 6,000,000 2 Gudang m2 24 275,000 6,600,000 12,600,000 C TENAGA
1 Site Manager orang 1 x 350,000 350,000
1 Pelaksana orang 2 x 300,000 600,000 2 Mandor orang 3 x 250,000 750,000 3 Mekanik orang 1 x 250,000 250,000 4 Tukang orang 3 x 225,000 675,000 5 Administrasi orang 2 x 225,000 450,000 6 Logistik orang 2 x 225,000 450,000 7 Pekerja orang 20 x 200,000 4,000,000 7,525,000 TOTAL ( A + B + C ) 34,375,000
PAKET : V
PEK. : Terowong 930 M
NO. URAIAN SATUAN JUMLAH JARAK H. SAT. JML. HARGA
2trip(km) Rp./Km A PERALATAN ( untuk 2 trip )
1 Excavator (2bh) +Trailler Unit 2 150 25,000 7,500,000
2 Crane (2bh) Unit 2 150 20,000 6,000,000
3 Concrete vibrator Unit 4 150 5,000 3,000,000
4 Tone Boring Machine (1bh)+Trailler. Unit 1 300 30,000 9,000,000 5 Jacking Pipe App.(2)+Trailler Unit 2 300 30,000 18,000,000
6 Ordinary Truck (1bh) Unit 2 150 10,000 3,000,000
7 Concrete Mixer (2bh)+ Truck crane Unit 2 150 10,000 3,000,000
8 Pompa grouting Unit 1 150 15,000 2,250,000
9 Generator (1bh) +truck Unit 2 150 15,000 4,500,000
10 mesin las Unit 1 150 15,000 2,250,000
11 Dump Truck Unit 4 150 10,000 6,000,000
64,500,000
B FASILITAS
1 Direksi keet 1 buah m2 20 x 300,000 6,000,000
(termasuk Meja tulis,Meja gambar, Meja kursi tamu,PPPK.).
2 Gudang & Bengkel m2 40 x 100,000 4,000,000
3 Asrama Unit 1 x 3,000,000 3,000,000
13,000,000
C TENAGA
1 Pimpinan Pelaksana orang 1 x 300,000 300,000
2 Teknik Konstruksi orang 1 x 300,000 300,000
3 Peralatan orang 4 x 200,000 800,000
3 Geologi orang 4 x 200,000 800,000
4 Supertend / Quality orang 4 x 200,000 800,000
5 Geodesi orang 4 x 200,000 800,000
6 Sipil Kosntruksi orang 3 x 200,000 600,000
7 Mechanical orang 3 x 150,000 450,000
8 Pengukuran orang 3 x 150,000 450,000
9 Administrasi orang 1 x 150,000 150,000
10 Bidang Teknik orang 1 x 150,000 150,000
5,600,000
TOTAL ( A + B + C ) 83,100,000
PAKET : II
PEK. : BENDUNG TAWANGSARI
NO. URAIAN SATUAN JUMLAH JARAK H. SAT. JML. HARGA
2trip(km) Rp./Km A PERALATAN ( untuk 2 trip )
1 Excavator ( 1bh ) +Trailler Unit 1 150 25,000 3,750,000 2 Bulldozer (1bh)+ Trailler Unit 1 150 25,000 3,750,000
3 Ordinary Truck (2bh) Unit 2 150 10,000 3,000,000
4 Concrete Mixer (2bh)+ Truck crane Unit 2 150 10,000 3,000,000
5 Vibrator concrete Unit 2 150 5,000 1,500,000
6 Submersible Pump(1bh) Unit 1 150 6,000 900,000 7 Generator (1bh) +truck Unit 1 150 15,000 2,250,000
8 Dump Truck Unit 3 150 10,000 4,500,000
22,650,000
B FASILITAS
1 Direksi keet 1 buah m2 20 x 300,000 6,000,000
(termasuk Meja tulis,Meja gambar, Meja kursi tamu,PPPK.).
2 Gudang & Bengkel m2 40 x 100,000 4,000,000
3 Asrama Unit 1 x 3,000,000 3,000,000
13,000,000
C TENAGA
1 Pimpinan Pelaksana (1org) orang 1 x 300,000 300,000 2 Teknik Konstruksi (1org) orang 1 x 300,000 300,000 4 Supertend / Quality (1org) orang 1 x 200,000 200,000 6 Sipil Kosntruksi (1 org) orang 3 x 200,000 600,000
7 Pengukuran ( 2 org) orang 3 x 150,000 450,000
9 Administrasi (2 org) orang 1 x 150,000 150,000
10 Bidang Teknik (2 org) orang 1 x 150,000 150,000
2,150,000
TOTAL ( A + B + C ) 37,800,000
PAKET : IV
PEK. : BENDUNG GROJOGAN
NO. URAIAN SATUAN JUMLAH JARAK H. SAT. JML. HARGA
2trip(km) Rp./Km A PERALATAN ( untuk 2 trip )
1 Excavator ( 1bh ) +Trailler Unit 1 150 25,000 3,750,000 2 Bulldozer (1bh)+ Trailler Unit 1 150 25,000 3,750,000
3 Ordinary Truck (1bh) Unit 1 150 10,000 1,500,000
4 Concrete Mixer (2bh)+ Truck crane Unit 2 150 10,000 3,000,000 5 Submersible Pump(1bh) Unit 1 150 6,000 900,000 6 Generator (1bh) +truck Unit 1 150 15,000 2,250,000
7 Vibrator concrete Unit 2 150 5,000 1,500,000
8 Road Roller Unit 1 150 25,000 3,750,000
9 Water Tanker Unit 1 150 10,000 1,500,000
10 Dump Truck Unit 2 150 10,000 3,000,000
24,900,000
B FASILITAS
1 Direksi keet 1 buah m2 20 300,000 6,000,000
(termasuk Meja tulis,Meja gambar, Meja kursi tamu,PPPK.).
2 Gudang & Bengkel m2 40 100,000 4,000,000
3 Asrama Unit 1 3,000,000 3,000,000
13,000,000
C TENAGA
1 Pimpinan Pelaksana (1org) orang 1 x 300,000 300,000 6 Sipil Kosntruksi (2 org) orang 3 x 200,000 600,000
7 Pengukuran ( 1 org) orang 3 x 150,000 450,000
9 Administrasi (1 org) orang 1 x 150,000 150,000
10 Bidang Teknik (1 org) orang 1 x 150,000 150,000
1,650,000
TOTAL ( A + B + C ) 39,550,000
PAKET : III
PEK. : SALURAN HANTAR I+II
NO. URAIAN SATUAN JUMLAH JARAK H. SAT. JML. HARGA
2trip(km) Rp./Km A PERALATAN ( untuk 2 trip )
1 Excavator (2bh) +Trailler Unit 2 150 25,000 7,500,000
2 Ordinary Truck (1bh) Unit 2 150 10,000 3,000,000
3 Concrete Mixer (2bh)+ Truck crane Unit 3 150 10,000 4,500,000
4 Submersible Pump(3) Unit 3 150 6,000 2,700,000
5 Generator (1bh) +truck Unit 1 150 15,000 2,250,000
6 Concrete Vibrator Unit 3 150 5,000 2,250,000
7 Dump Truck Unit 2 150 10,000 3,000,000
25,200,000
B FASILITAS
1 Direksi keet 1 buah m2 20 x 300,000 6,000,000
(termasuk Meja tulis,Meja gambar, Meja kursi tamu,PPPK.).
2 Gudang & Bengkel m2 40 x 100,000 4,000,000
3 Asrama Unit 1 x 3,000,000 3,000,000
13,000,000
C TENAGA
1 Pimpinan Pelaksana orang 1 x 300,000 300,000
2 Teknik Konstruksi orang 1 x 300,000 300,000
3 Peralatan orang 4 x 200,000 800,000
3 Geologi orang 4 x 200,000 800,000
4 Supertend / Quality orang 4 x 200,000 800,000
5 Geodesi orang 4 x 200,000 800,000
6 Sipil Kosntruksi orang 3 x 200,000 600,000
7 Mechanical orang 3 x 150,000 450,000
8 Pengukuran orang 3 x 150,000 450,000
9 Administrasi orang 1 x 150,000 150,000
10 Bidang Teknik orang 1 x 150,000 150,000
5,600,000
TOTAL ( A + B + C ) 43,800,000
PAKET : VI
PEK. : KOLAM PENAMPUNG
NO. URAIAN SATUAN JUMLAH JARAK H. SAT. JML. HARGA
2trip(km) Rp./Km A PERALATAN ( untuk 2 trip )
1 Excavator ( 1bh ) +Trailler Unit 1 150 25,000 3,750,000 2 Bulldozer (1bh)+ Trailler Unit 1 150 25,000 3,750,000
3 Ordinary Truck (2bh) Unit 1 150 10,000 1,500,000
4 Concrete Mixer (2bh)+ Truck crane Unit 2 150 10,000 3,000,000 5 Submersible Pump(1bh) Unit 1 150 6,000 900,000 6 Generator (1bh) +truck Unit 1 150 15,000 2,250,000
7 Water tanker Unit 1 150 10,000 1,500,000
8 Dump Truck Unit 1 150 10,000 1,500,000
9 Concrete Vibrator Unit 2 150 5,000 1,500,000
19,650,000
B FASILITAS
1 Direksi keet 1 buah m2 20 x 300,000 6,000,000
(termasuk Meja tulis,Meja gambar, Meja kursi tamu,PPPK.).
2 Gudang & Bengkel m2 40 x 100,000 4,000,000
3 Asrama m2 1 x 3,000,000 3,000,000
13,000,000
C TENAGA
1 Pimpinan Pelaksana (1org) orang 1 x 300,000 300,000 2 Teknik Konstruksi (1org) orang 1 x 300,000 300,000 4 Supertend / Quality (1org) orang 1 x 200,000 200,000 6 Sipil Kosntruksi (1 org) orang 3 x 200,000 600,000
7 Pengukuran ( 2 org) orang 3 x 150,000 450,000
9 Administrasi (2 org) orang 1 x 150,000 150,000
10 Bidang Teknik (2 org) orang 1 x 150,000 150,000
2,150,000
TOTAL ( A + B + C ) 34,800,000
PAKET : I
PEK. : BASE CAMP
NO. URAIAN SATUAN JUMLAH JARAK H. SAT. JML. HARGA
2trip(km) Rp./Km A PERALATAN ( untuk 2 trip )
1 Bulldozer (1bh)+ Trailler Unit 1 300 25,000 7,500,000
2 Ordinary Truck (1bh) Unit 2 150 10,000 3,000,000
3 Concrete Mixer (2bh)+ Truck crane Unit 2 150 10,000 3,000,000
4 Pompa air Unit 1 150 500 75,000
5 Tone Boring Machine (1bh)+Truck crane. Unit 1 150 20,000 3,000,000
6 Dump Truck Unit 1 150 10,000 1,500,000
18,075,000
B FASILITAS
1 Direksi keet 1 buah m2 20 350,000 7,000,000
(termasuk Meja tulis,Meja gambar, Meja kursi tamu,PPPK.).
2 Gudang & Bengkel m2 40 100,000 4,000,000
3 Asrama Unit 1 3,000,000 3,000,000
14,000,000
C TENAGA
1 Pimpinan Pelaksana (1org) orang 1 x 300,000 300,000 6 Sipil Kosntruksi (2 org) orang 3 x 200,000 600,000
7 Pengukuran ( 1 org) orang 3 x 150,000 450,000
9 Administrasi (1 org) orang 1 x 150,000 150,000
10 Bidang Teknik (1 org) orang 1 x 150,000 150,000
1,650,000
TOTAL ( A + B + C ) 33,725,000
Nomor analisa : 22
Jenis Pekerjaan : Coffering
Satuan : Ls
Harga satuan ( Rp.) : 27,610
Dasar analisa : DD.Cost.Es.no20
HARGA SAT. JML.HARGA
Rp. Rp. 1. BAHAN Gedeg lbr 0.0800 17,000 1,360 Bambu bh 0.0300 6,000 180 Kawat kg 0.0400 7,000 280 Sub Total 1 1,540 2. TENAGA Mandor org/hr 0.0380 37,500 1,425 Kepala tukang kayu org/hr 0.0050 33,000 165
Tukang Kayu org/hr 0.0460 28,600 1,316 Pekerja org/hr 1.0370 21,875 22,684 Sub Total 2 25,590 3. ALAT Alat Pelancip bh 0.0800 6,000 480 Bodem bh 0.0300 5,000 150 Keranjang bh 0.0400 3,000 120 Sub Total 3 480 27,610 Total 3,313,197 Dibulatkan 3,313,000 TOTAL
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa : 22
Jenis Pekerjaan : Pengadaan Pipa steel, ID 1400mm,t=15 mm
Kuantitas Pekerjaan 3139.05 kg
Satuan : kg
Harga satuan ( Rp.) : #VALUE!
Dasar analisa : DD.Cost.Es.no.48
HARGA SAT. JML.HARGA
Rp. Rp.
1. BAHAN
Pipa steel (6m) bt 3,139.0500 x #VALUE!
Sub Total 1 #VALUE!
2. TENAGA
Mandor org/hr 0.1400 37,500 5,250
Tukang besi org/hr 0.2900 26,400 7,656
Pekerja org/hr 0.8600 21,875 18,813 Sub Total 2 31,719 3. ALAT Trailler Pengangkut bh 1.0000 3,000,000 3,000,000 Crane Pengangkat bh 1.0000 250,000 250,000 Sub Total 3 3,000,000 #VALUE! TOTAL
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa :
Jenis Pekerjaan : Pipe Jacking
Satuan : m
Harga satuan ( Rp.) : Rp. 6,211,000
HARGA SAT. JML.HARGA
Rp. Rp. 1 TENAGA Mandor org/hr 0.2000 37,500 7,500 Pekerja org/hr 1.6500 21,875 36,094 Mekanik org/hr 0.5000 37,500 18,750 Operator org/hr 0.5000 35,000 17,500 Sub Total 2 79,844 2 PERALATAN
Jacking Machine' jam 2.15 2,300,000 4,945,000
Compressor jam 2.15 190,000 408,500
Pompa submersible jam 2.15 62,000 133,300
Genset jam 2.15 100,000 215,000
Crane 10 ton jam 2.15 200,000 430,000
6,131,800
Total 6,211,644
Dibulatkan 6,211,000 ANALISA HARGA SATUAN PEKERJAAN
NO. URAIAN SAT. VOLUME
Nomor analisa :
Jenis Pekerjaan : Dewatering/Pengeringan
Satuan : Jam
Harga satuan ( Rp.) : Rp. 100,000
HARGA SAT. JML.HARGA
Rp. Rp. 1 TENAGA Mekanik org/hr 0.0500 37,500 1,875 Operator org/hr 0.0500 35,000 1,750 Sub Total 2 3,625 2 PERALATAN
Pompa submersible jam 1 23,200 23,200
Genset jam 1 65,000 65,000 88,200 3 BAHAN Solar lt 5 1,650 8,250 Total 100,075 Dibulatkan 100,000 ANALISA HARGA SATUAN PEKERJAAN
NO. URAIAN SAT. VOLUME