• Tidak ada hasil yang ditemukan

Results

Dalam dokumen UBUDIYAH - UNDARIS Repository (Halaman 78-85)

4 Research Findings

4.2 The Challenges in Adopting Standard Forms of Construction Contract in Indonesia

4.3.3 Results

After conducting the analysis as mentioned above, then a proposed model of standard form of construction contract can be made. This proposed model is not made in form of a contract document, but rather be made in form of a set similar with body of knowledge. This proposed model consists of 2

Proceeding of The 1st International Joint Conference Indonesia-Malaysia-Bangladesh-Ireland 2015 Universitas Ubudiyah Indonesia, 27-28 April 2015, Banda Aceh, Indonesia

70

(two) parts. The first part is about the anatomical structure of the construction contract which has been adopted from international standards and adapted to the Indonesian construction industry context, while the second part is about the embodiment of the various aspects in construction contract.

The anatomy of construction contract below is adopted from FIDIC and has been adapted to Indonesian context. FIDIC is selected because it is the most widely used international standard form of contract in Indonesia. Thus, it is expected that Indonesia can publish its own version of standard form of construction contract with international standard and it can be easily socialised and accepted by the industry.

Table 4 The Proposed Anatomy of Construction Contract

No Anatomy Sub-Anatomy

1 General Provisions Definitions Interpretation Communications

Governing Law and Language Priority of Documents

Contract Agreement Assignment

Care and Supply of Documents Delayed Drawings or Instructions

Employer’s Use of Contractor’s Documents Contractor’s Use of Employer’s Documents Confidentiality

Compliance with Laws Joint and Several Liability Rights and Obligations of Parties 2 The Employer Right of Access to the Site

Permits, Licenses or Approvals Employer’s Personnel

Employer’s Financial Arrangements Employer’s Claims

3 The Engineer/CA/

Superintendent

Engineer’s Duties and Authority Delegation by the Engineer Instructions of the Engineer Replacement of the Engineer Determinations

4 The Contractor Contractor’s General Obligations Performance Security

Contractor’s Representative Subcontractors

Assignment of Benefit of Subcontract Co-operation

Setting Out Safety Procedures Quality Assurance Site Data

Sufficiency of the Accepted Contract Amount Unforesseable Physical Conditions

Rights of Way and Facilities Avoidance of Interference Access Route

Transport of Goods Contractor’s Equipment Protection of the Environment Electricity, Water and Gas

Employer’s Equipment and Free-Issue Material Progress Reports

Security of the Site

Proceeding of The 1st International Joint Conference Indonesia-Malaysia-Bangladesh-Ireland 2015 Universitas Ubudiyah Indonesia, 27-28 April 2015, Banda Aceh, Indonesia

71

Contractor’s Operations on Site Fossils

5 Nominated

Subcontractors and Nominated Suppliers

Definition of NSC and NS Objection to Nomination Payments to NSC and NS Evidence of Payments

6 Staff and Labour Engagement of Staff and Labour

Rates of Wages and Conditions of Labour Persons in the Service of Employer Labour Laws

Working Hours

Facilities for Staff and Labour Health and Safety

Contractor’s Personnel

Records of Contractor’s Personnel and Equipment Disorderly Conduct

7 Plant, Materials and Workmanship

Manner of Execution Samples

Inspection Testing Rejection Remedial Work

Ownership of Plant and Materials Royalties

8 Commencement, Delays and Suspension

Commencement of Works Time for Completion Programmes

Extension of Time for Completion Delay caused by Authorities Rate of Progress

Delay Damages Suspension of Work

Consequences of Suspension

Payment for Plant and Materials in Event of Suspension Prolonged Suspension

Resumption of Work 9 Tests on Completion Contractor’s Obligations

Delayed Tests Retesting

Failure to Pass Tests on Completion 10 Employer’s Taking Over Acceptance of the Work

Taking Over of the Works and Sections Taking Over of Parts of the Works Interference with Tests on Completion Surfaces Requiring Reinstatement

11 Defects Liability Completion of Outstanding Work and Remedying Defects Cost of Remedying Defects

Defects Liability Period

Extension of Defects Notification Period Failure to Remedy Defects

Removal of Defective Work Further Tests

Right of Access Contractor to Search Performance Certificate Unfulfilled Obligations Clearance of Site 12 Measurement and

Evaluation

Works to be Measured Method of Measurement Evaluation

Proceeding of The 1st International Joint Conference Indonesia-Malaysia-Bangladesh-Ireland 2015 Universitas Ubudiyah Indonesia, 27-28 April 2015, Banda Aceh, Indonesia

72 Omissions 13 Variations and

Adjustments

Right to Vary Value Engineering Variation Procedure

Payment in Applicable Currencies Provisional Sums

Daywork

Adjustments for Changes in Legislation Adjustments for Changes in Cost 14 Contract Price and

Payment

The Contract Price Procedure of Payments Advance Payment

Application for Interim Payment Certificates Schedule of Payments

Plant and Materials intended for the Works Issue of Interim Payment Certificates Payment

Performance Bond Advance Payment Bond Retention

Delayed Payment

Payment of Retention Money Statement at Completion

Application for Final Payment Certificate Discharge

Issue of Final Payment Certificate Cessation of Employer’s Liability Currencies of Payment

15 Termination by Employer

Notice to Correct

Termination by Employer Valuation at Date of Termination Payment after Termination

Employer’s Entitlement to Termination 16 Suspension and

Termination by Contractor

Contractor’s Entitlement to Suspend Work Termination by Contractor

Cessation of Work and Removal of Contractor’s Equipment Payment on Termination

17 Risk and Responsibility Indemnities

Contractor’s Care of the Works Employer’s Risks

Consequences of Employer’s Risks Intellectual and Industrial Property Rights Limitation of Liability

18 Insurance General Requirements for Insurance

Insurance for Works and Contractor’s Equipment

Insurance against Injury to Persons and Damage to Property Insurance for Contractor’s Personnel

19 Force Majeure Definition of Force Majeure Notice of Force Majeure Duty to Minimise Delay

Consequences of Force Majeure Force Majeure Affecting Subcontractor Optional Termination, Payment and Release Release from Performance under the Law 20 Claims and Disputes

Settlement

Contractor’s Claims Amicable Settlement Arbitration

21 Addendum and Amendment

Addendum and Amendment

Proceeding of The 1st International Joint Conference Indonesia-Malaysia-Bangladesh-Ireland 2015 Universitas Ubudiyah Indonesia, 27-28 April 2015, Banda Aceh, Indonesia

73

Because the construction contract serves as the main guideline in implementing construction projects, all aspects of the construction business should be incorporated into the contract in simple form and language. The embodiment of various aspects of construction contract can be seen in the following table.

Table 5 The Embodiment of Various Aspects in Construction Contract

No Aspects Commentaries

Legal Aspect

1 Preamble 1. There should be a contract title

2. Contract should have a contract number

3. Ensure that there shall be stated date and place of contract signing

2 Type of contract 1. Ensure whether the project is a government project or private project

2. Ensure what type of contract procurement does the project have (traditional, design-build, EPC or else) 3. Ensure what type of contract pricing does the project have

(lumpsum, unit price, or else)

3 Validity 1. Ensure that the both parties have legality in doing business process in Indonesia (notarial act, identity card, etc)

4 Contract background 1. There is a procedure from the tendering period up to awarding period

2. All parties agreed to sign the contract pursuant to the terms and conditions of the contract

3. There is basis of the agreement

5 Hierarchy of documents 1. There is a clause which stipulate the hierarchy of documents

6 Object of the agreement 1. Scope of work must be stated clearly and firmly

2. Clear time-related condition (commencement date, construction period, defect liability period, contract period, extension of time)

7 Rights and obligations 1. All rights and obligations of the parties involved should be clearly written down and balanced

8 Governing law and language 1. There should be clauses which state the governing law and language of the project

2. All work carried out in Indonesia are subject to the Indonesian Law

3. The contract should be written in Bahasa Indonesia 9 Dispute settlement 1. There should be clauses which describe how to settle any

disputes between the parties involved

2. Amicable settlement between parties must be prioritize 3. Arbitration as a higher level of alternative dispute

resolution should be enforced if no amicable settlement reached

10 Addendum and amendment 1. There should be a provision which provide a necessary way for both parties to make an addendum and/or amendment to the contract

Business Aspect

11 Contract Value 1. The amount of contract price should be clearly stated and written (both in numbers and spellings)

12 Completion time 1. The date of completion must be clearly stated 2. The duration of work must be clearly stated

13 Extension of time 1. Commitment to complete the works by any stipulated time must be subject to extension of time

2. Conditions which are subject to extension of time must be clearly stated in the contract (force majeure, variations, suspensions not cause by the contractor’s faults, change of law, etc)

Proceeding of The 1st International Joint Conference Indonesia-Malaysia-Bangladesh-Ireland 2015 Universitas Ubudiyah Indonesia, 27-28 April 2015, Banda Aceh, Indonesia

74

14 Working hour 1. Examine the local regulations and practices in respect of working hours (shift work, night work, daylight work, rest days, public holidays, etc)

2. The contract price and duration must be estimated accordingly

15 Variations and claims 1. The contract scope of work must be clearly defined without ambiguity

2. The contract must have a definitive procedure on variations

3. There must be rules of valuation for variations

4. The contract should provide reasonable time bar to notify and quantify a claim or variation

16 Cost of delay 1. The contract should provide for conditions where one party must compensate for the cost of delay

17 Acceptance of work 1. The contract must have definitive acceptance procedure 2. There should be clauses which describe the acceptance

procedure and the result of the acceptance (release of retention money)

18 Liquidated damages 1. There should be a clause which imposes an obligation upon one party to pay a fixed sum of money in the event of one party’s breach

19 Defect liabilities 1. The period of defect liability should be stated in the contract

20 Warranties 1. Warranties must be limited to express warranties set forth in the contract and to the extent permissible under applicable law

2. Clear definitions of performance test procedures, tolerances, and acceptance criteria

21 Nominated subcontractors and suppliers

1. There should be clauses which describe the procedure of nominated subcontractors and suppliers appoinments 2. The contract should give a chance for the main contractor

to object the nomination (giving reasonable refusal) 22 Subcontracting 1. There should be a provision which states the contractor’s

right and limitation to appoint subcontractors

2. The main contractor is responsible for the subcontractors’

work

23 Insurance 1. There should be a clause which provides the general requirements for insurance

2. At least three types of insurance should be provided:

- Insurance for Works and Contractor’s Equipment - Insurance against Injury to Persons and Damage to

Property

- Insurance for Contractor’s Personnel 24 Progress evaluation and

payment terms

1. There should be clauses which provide the procedures to evaluate work progress

2. There should be clauses which provide the payment procedures

25 Adjustments 1. There should be a clause in adjusting the contract value or work for changes in legislation and cost (escalation) 26 Bonds 1. There should be clauses which describe the various bonds

required for the work:

- Performance bond - Advance payment bond - Other bonds

27 Correspondence 1. The contract should provide a clear representative’s correspondence address

28 Contract Documents 1. All contract documents should be stated clearly

2. The priority of documents should be stipulated in a clause 29 Unforeseeable physical 1. There should be a clause which describes the definition of

Proceeding of The 1st International Joint Conference Indonesia-Malaysia-Bangladesh-Ireland 2015 Universitas Ubudiyah Indonesia, 27-28 April 2015, Banda Aceh, Indonesia

75

conditions unforeseeable physical conditions

2. There should be a clause which describes the procedure in case the contractor faces unforeseeable physical conditions

30 Reports and Instructions 1. Reports should be made by the contractor and be submitted to the engineer

2. Contractor should comply with the engineer’s instructions 3. Instructions should be made in written form

31 Liquidated damages 1. There should be clauses which describe the rules and procedures for liquidated damages

32 Suspension and termination 1. There should be clauses which state the procedures and conditions for:

- Suspension of work - Termination of the contract

33 Force Majeure 1. There should be clauses which explain what constitutes force majeure conditions, the procedures and settlement of obligations between parties involved

34 Termination 1. There should be a clause which defines the termination for both parties

2. There should be a clause which describes the procedure of termination

35 Taking Over 1. There should be clauses which describe the handing over procedure from contractor to the employer

2. Partial hand over procedure and requirements must be stated clearly if both parties agrees to have partial hand over in the contract

36 Taxation 1. Taxation should be stated whether it has already been included in the contract sum or not

37 Resource Utilization 1. The contractor is encouraged to use local materials, equipments and manpower

38 Environmental 1. Contractor in doing his work should comply with the applicable environmental laws and regulations

5 Conclusion

The focus of this research is the importance of standard form of construction contract which is expected to be introduced and be used in Indonesia. This is started with the definition of standard form of construction contract viz. an attempt to equalize perceptions, terms and conditions which is manifested in the form of construction contract, and is made based on the correct principles of contract, and serves as the guidance in negotiating and drafting a construction contract.

The findings show that there are at least 17 (seventeen) advantages of using standard form of construction contract against 8 (eight) disadvantages. The main benefit of the implementation of standard form is to provide education and good understanding on the principles of construction contract to the public. Currently there are still many people who do not understand how to make a correct contract and how to distribute the rights, obligations and risks appropriately. Since preparing and negotiating construction contract is part of the principle of freedom of contract, this standard form may at least serve as a guideline for people when they are starting a contract negotiation.

Meanwhile, this research has also identified 11 (eleven) challenges in adopting standard form of construction contract in Indonesia. Some of these challenges are lack of awareness and socialization, and the reluctant to change the current practices. Solution is given for each challenge which essentially tries to promote the usage and benefits of standard form of construction contract in Indonesia.

In addition, this research also examines various aspects of construction industry which will be stipulated in the form of construction contracts. There are 2 (two) main aspects i.e. legal aspect and business aspect. Business aspect consists of technical aspect, administrative aspect, financial aspect, taxation aspect, insurance aspect, socio-economic aspect, and environmental aspect. By

Proceeding of The 1st International Joint Conference Indonesia-Malaysia-Bangladesh-Ireland 2015 Universitas Ubudiyah Indonesia, 27-28 April 2015, Banda Aceh, Indonesia

76

understanding the various aspects of construction contract, then a proposed model of standard form of construction contract can be made.

Since standard form of construction contract is a new thing to be implemented in Indonesia, further researches can be made and developed. Two of them are the various types of standard form of construction contract in Indonesia and the impacts of the implementation of construction contract standard forms in Indonesia.

Dalam dokumen UBUDIYAH - UNDARIS Repository (Halaman 78-85)