Plan today, Monday June 02, 2025 (E) MCC#2
Supervisor : Reno, Manpower Total : 20 Cable room
- install arm bracket - install cable tray dll - install sambungan support MCC room
- Continue fullweld base frame - Cleaning, Painting base frame
- Continue Fabrikasi base frame stand alone - Repair base frame line 20
Trafo room
- install trafo / install accessories trafo TR26, TR27 ( tunggu info) Actual
Cable room
- instal breacket arm ; 57 pcs
- instal pabrikasi offside 2,25 horizontal tray 600 mm : 4 btg - instal straight ladder tray 600 mm : 7 btg/ 42m
- instal tray 400 mm favorite : 6 btg - instal equal tee 600 mm : 1 pcs
- instal pabrikasi reduser 600 mm to 400 mm p : 1500 mm : 1 pcs - instal connection plat : 8 ea
- instal Square neck bolt : 48 ea Mcc room
- continue base frame stand alone Unp 75 x 40 p : 6000 mm : 6 btg Unp 75x40 p : 645 mm : 8 btg Total unp 75x 40 terpakai : 7 btg/ 42m Trafo room
- loading trafo 025 - open cash trafo 025 - instal trafo 025 ( trafo on posisi)
Trafo Room MCC4
Supervisor : Nelson Purba, Manpower Total : 15 Panel Room
- Cutting, install, welding UNP for base frame panel Transformer Room
- Install cable Tray incoming to Transformer Cable Room
- Install support tray incoming from conveyor Conveyor 4015
- Lifting manual tray Actual :
Trafo Room
- Install Support Tray 600mm, Install Offset tray 600mm TR047 Room, full Weld and Cleaning Plan today, Monday June 02, 2025 (IA)
Chipping Line 20; Screening Line 20; Panel Room MCC4; Panel Room MCC2, Conveyor 4013
Supervisor : Ishak , Manpower Total : 23 Conveyor 4013 (I), 6 manpower
- Continue Instal field device - Fabrikasi support 2nd tray Screening line 20 (I), 4 manpower - Fabrikasi frame Digital JB - Instal support, cable tray - Instal DJB
Line 20 (I), 7 manpower - Fabrikasi Support tray - Fabrikasi frame JB - Install 2nd tray
Automation Panel Room MCC4,MCC4 (A) , 5 manpower - Manual lifting frame automation panel MCC4
- Continue welding frame automation panel MCC2 - Finishing, touch up painting