Plan today, Monday June 02, 2025 (E) MCC#2

Supervisor : Reno, Manpower Total : 20 Cable room

- install arm bracket - install cable tray dll - install sambungan support MCC room

- Continue fullweld base frame - Cleaning, Painting base frame

- Continue Fabrikasi base frame stand alone - Repair base frame line 20

Trafo room

- install trafo / install accessories trafo TR26, TR27 ( tunggu info) Actual

Cable room

- instal breacket arm ; 57 pcs

- instal pabrikasi offside 2,25 horizontal tray 600 mm : 4 btg - instal straight ladder tray 600 mm : 7 btg/ 42m

- instal tray 400 mm favorite : 6 btg - instal equal tee 600 mm : 1 pcs

- instal pabrikasi reduser 600 mm to 400 mm p : 1500 mm : 1 pcs - instal connection plat : 8 ea

- instal Square neck bolt : 48 ea Mcc room

- continue base frame stand alone Unp 75 x 40 p : 6000 mm : 6 btg Unp 75x40 p : 645 mm : 8 btg Total unp 75x 40 terpakai : 7 btg/ 42m Trafo room

- loading trafo 025 - open cash trafo 025 - instal trafo 025 ( trafo on posisi)

Trafo Room MCC4

Supervisor : Nelson Purba, Manpower Total : 15 Panel Room

- Cutting, install, welding UNP for base frame panel Transformer Room

- Install cable Tray incoming to Transformer Cable Room

- Install support tray incoming from conveyor Conveyor 4015

- Lifting manual tray Actual :

Trafo Room

- Install Support Tray 600mm, Install Offset tray 600mm TR047 Room, full Weld and Cleaning Plan today, Monday June 02, 2025 (IA)

Chipping Line 20; Screening Line 20; Panel Room MCC4; Panel Room MCC2, Conveyor 4013

(2)

Supervisor : Ishak , Manpower Total : 23 Conveyor 4013 (I), 6 manpower

- Continue Instal field device - Fabrikasi support 2nd tray Screening line 20 (I), 4 manpower - Fabrikasi frame Digital JB - Instal support, cable tray - Instal DJB

Line 20 (I), 7 manpower - Fabrikasi Support tray - Fabrikasi frame JB - Install 2nd tray

Automation Panel Room MCC4,MCC4 (A) , 5 manpower - Manual lifting frame automation panel MCC4

- Continue welding frame automation panel MCC2 - Finishing, touch up painting

Referensi

Dokumen terkait

7) Persiapan Program Pengembangan KUPS Eduforestry melalui kemitraan multistakeholder. 8) Implementasi KUPS Eduforestry melalui program pengelolaan lingkungan berbasis

6 Education and training No specific education and training on code of conduct and ethics on ecotourism is available in Malaysia except for the training for nature

[r]

Melukis Bilangan Kompleks Bilangan-bilangan riil dilukis sebagai titik dalam sebuah garis yang disebut garis bilangan Bilangan kompleks dilukiskan pada bidang datar dimana

Laporan rencana bisnis dan kegiatan expo bazar 2025 untuk tugas akhir jurusan perbankan syariah di UIN Maulana Malik Ibrahim