DURASI PEKERJAAN (MINGGU)
1 PEKERJAAN PERSIAPAN Rp 36,294,095.50 2.33 1
2 PEKERJAAN TANAH Rp 21,104,386.67 1.35 3
3 PEKERJAAN PASANGAN Rp 138,975,869.03 8.92 15
4 PEKERJAAN PLESTERAN Rp 128,379,921.29 8.24 11
5 PEKERJAAN KUSEN PINTU DAN JENDELA Rp 512,992,722.79 32.91 12
6 PEKERJAAN BETON Rp 353,314,589.36 22.67 9
7 PEKERJAAN PASANGAN LANGIT-LANGIT Rp 34,455,000.00 2.21 2
8 PEKERJAAN PENGUNCI DAN KACA Rp 54,568,489.39 3.50 1
9 PEKERJAAN SANITASI DALAM GEDUNG Rp 36,323,516.08 2.33 4 10 PEKERJAAN PENUTUP LANTAI DAN DINDING Rp 162,319,237.29 10.41 10
11 PEKERJAAN PENGECATAN Rp 28,747,513.01 1.84 2
12 PEKERJAAN ELEKTRIKAL Rp 20,365,400.00 1.31 3
13 PEKERJAAN PENUTUP ATAP Rp 23,255,205.51 1.49 2
14 PEKERJAAN TANGGA Rp 7,754,481.00 0.50 4
1,558,850,427
Rp 100.00
RENCANA ANGGARAN DAN BIAYA
PEKERJAAN PEMBANGUNAN RUMAH MINIMALIS 3 LANTAI TIPE 12,150 X 15,150 m TAHUN 2019
TOTAL
NO URAIAN PEKERJAAN HARGA BOBOT (%)
PROGRES
1 2 3 4 5 6 7 8 9 10 11 12 13 2.328
0.451 0.451 0.451
0.594 0.594 0.594 0.594 0.594 0.594 0.594 0.594 0.594 0.594
0.749 0.749 0.749 0.749 0.749 0.749 0.749 0.749
2.742 2.742 2.742 2.742 2.742
2.518 2.518 2.518 2.518 2.518 2.518 2.518
0.583 0.583 0.583
1.041 1.041 1.041 1.041
0.435 0.435
0.124 0.124
2.780 1.046 3.564 3.113 4.879 1.926 6.009 7.175 4.502 5.127 2.820 4.444 6.604
2.780 3.825 7.389 10.502 15.381 17.307 23.316 30.491 34.994 40.120 42.940 47.384 53.988
RENCANA ANGGARAN DAN BIAYA
PEKERJAAN PEMBANGUNAN RUMAH MINIMALIS 3 LANTAI TIPE 12,150 X 15,150 m TAHUN 2019
BULAN 1 BULAN 2 BULAN 3 BULAN 4
14 15 16 17 18 19 20 21 22 23 24
0.594 0.594 0.594 0.594 0.594
0.749 0.749 0.749
2.742 2.742 2.742 2.742 2.742 2.742 2.742
2.518 2.518
1.105 1.105
3.501 0.583
1.041 1.041 1.041 1.041 1.041 1.041
0.922 0.922
0.435
0.746 0.746
0.124 0.124
6.302 6.426 4.502 2.820 2.967 5.127 3.337 3.488 4.593 5.528 0.922
60.290 66.716 71.218 74.038 77.005 82.132 85.468 88.957 93.550 99.078 100.000
RENCANA ANGGARAN DAN BIAYA
PEKERJAAN PEMBANGUNAN RUMAH MINIMALIS 3 LANTAI TIPE 12,150 X 15,150 m TAHUN 2019
BULAN 6
BULAN 4 BULAN 5