BAHAGIAN : 3.0 KOS ITEM-ITEM KERJA
SUB-BAHAGIAN : 3.2 DEMOLITION & SITE CLEARANCE
Kawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor
Kawasan B - Perak Kawasan E - Pahang
Kawasan C - WP. KL, Selangor Kawasan F - Terengganu
N. Sembilan & Melaka & Kelantan
BIL. KETERANGAN KERJA UNIT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA
(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)
Site Clearance
1 General clearance comprising trees and shrubs including Ha - - 500.00 - 667.00 - - - 500.00 - 1,135.00 500.00 - 901.00
uprooting all stumps of various diameters and cart away to 1,000.00 2,500.00 2,500.00
contractor's own site
2 Supply all tools, transport, labour and everything else Ha - - 650.00 - 708.00 - - - 650.00 - 708.00
necessary for clearing of site as specified of all 800.00 800.00
vegetation trees irrespective of girth including up roots etc structures and remove all from site
3 General clearance within the reserve including the demolition Ha - 200.00 - - - 300.00 - 1,433.00 200.00 - 816.50
and removal of all articles, objects and obstruction from site. 3,000.00 3,000.00
4 General clearance of areas including removal of all vegetative Ha - - 300.00 - 360.00 500.00 - 633.00 - - - 400.00 - - 300.00 - 464.33
growths, bushes, stump, fences and other similar obstruction 420.00 800.00 800.00
and disposal.
5 General clearance of the side along the alignment of the M2 - - - 0.30 - - - 0.30
drain including removal of vegetation, stumps, rubbish and other similar obstruction.
6 Allow for the approved removal including felling, uprooting No. - - - 50.00 - 50.00
and approved disposal of trees measuring 1.0 m to 1.5 m girth as measured 1.2m above ground level
7 Allow for the approved removal including felling, uprooting No. - - - 100.00 - 100.00
and approved disposal of trees measuring 1.0 m to 2.0 m girth as measured 1.2m above ground level
KAWASAN E KAWASAN F KESELURUHAN
KAWASAN A KAWASAN B KAWASAN C KAWASAN D
Page 1 of 2
BAHAGIAN : 3.0 KOS ITEM-ITEM KERJA
SUB-BAHAGIAN : 3.2 DEMOLITION & SITE CLEARANCE
Kawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor
Kawasan B - Perak Kawasan E - Pahang
Kawasan C - WP. KL, Selangor Kawasan F - Terengganu N. Sembilan & Melaka & Kelantan
BIL. KETERANGAN KERJA UNITJULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA
(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)
Demolition
1 Demolition of existing of existing RC concrete bridge with timber decking size:
a 3.6m x 14.4m length No. - - - 5,000.00 - 5,000.00
b 3.6m x 21.0m length No. - - - 7,000.00 - 7,000.00
2 Demolition of road sides drain size 300mm X 300mm and cart M - - - 35.00 - 35.00
away to contractor's own site.
3 Demolition of brickwork sump size 1300 x 1300mm cart No. - - - 1,200.00 - 1,200.00
away to contractor's own site.
4 Demolition of road culvert 600mm diameter x 6.0 m length No. - - - 200.00 - 200.00
including reinforced concrete bed, wingwall and disposed to contractor's own site.
KOS2001
KAWASAN A KAWASAN B KAWASAN C KAWASAN D KAWASAN E KAWASAN F KESELURUHAN
Page 2 of 2