B ILL OF Q UANTITIES

Dalam dokumen Procurement of INFRASTRUCTURE PROJECTS (Halaman 77-85)

BILL OF QUANTITIES

LOT A: IMPROVEMENT OF KSU MUSHROOM BUILDING:

ITEM NO. DESCRIPTION QTY UNIT Unit Price

(in Pesos)

Total Cost (in Pesos)

803(1)a STRUCTURE EXCAVATION (common soil) 6.86 cu.m.

804 EMBANKMENT 15.05 cu.m

902 REINFORCING STEEL BAR 457.39 kgs

901(1)c1 CONCRETE WORKS 6.08 cu.m

903(2) FORMS & FALSEWORK 60.80 sq.m.

1046 MASONRY WORKS 22.62 sq. m

1010(2)b DOOR (WOOD PANEL DOOR) 2.80 sq. m

1027 CEMENT PLASTER FINISH 351.32 sq. m

1018(3) GRANITE TILE 11.30 sq. m

1003(1)e1 CARPENTRY AND JOINERY WORKS (ceiling) 43.88 sq. m

1032(1)a PAINTING WORKS (Masonry/Concrete) 351.32 sq. m

1032(1) PAINTING WORKS (ceiling & interior walling) 108.46 sq. m

1003(1)e2 SPANDRELL CEILING 427.70 ln.m.

1001(8) SEWER LINE WORKS 1.00 ls

1001(6)b SEPTIC TANK 1.00 unit

1021(3)a FLOOR TOPPING 154.65 sq.m.

1003(2)a1 CARPENTRY AND JOINERY WORKS (INTERIOR

WALL) 64.58 sq.m.

B.7 OCCUPATIONAL SAFETY AND HEALTH PROGRAM 1.00 LS

TOTAL BID AMOUNT (in figures): Php TOTAL BID AMOUNT (in words): Pesos

Note: The Bill of Quantities (BOQ) contains the following parts:

a. BOQ for each Part of the Contract.

b. Summary of Bid Prices for all Parts of the Contract.

Project Duration: 57 calendar days Submitted by:

Name and Signature of Bidder’s Representative:_________________________________

Position :________________________________

Name of Bidder: ______________________________

Date: ________________

LOT B: COMPLETION OF THE REHABILITATION OF OLD TECH-VOC BUILDING:

ITEM NO. DESCRIPTION QTY UNIT UNIT PRICE

including Tax (in Pesos)

TOTAL COST

including Tax (in Pesos)

1008(1)a ALUMINUM GLASS (FIXED TYPE) 13.11 sq.m.

101(1) REMOVAL OF STRUCTURE AND

OBSTRUCTION 1.00 lumpsum

1007(1)b ALUMINUM GLASS DOOR (SWING

TYPE) 1.98 sq.m.

1010(2)b DOORS WOOD PANEL 1.89 sq.m.

1010(1) FRAMES (DOOR JAMBS) 1.00 set

SPL-1 MISCELLANEOUS 1.00 lumpsum

1200 AIRCONDITIONING AND

VENTILATING UNITS 1.00 lumpsum 1008(1)a ALUMINUM GLASS WINDOW

(SLIDING TYPE) 18.00 sq.m.

1046(2)a1 MASONRY WORKS 2.40 sq.m.

1027 CEMENT PLASTER FINISH 13.20 sq.m.

1032(1)a PAINTING WORKS (MASONRY/CONCRETE) 13.20 sq.m.

TOTAL BID AMOUNT (in figures): Php TOTAL BID AMOUNT (in words): Pesos

Note: The Bill of Quantities (BOQ) contains the following parts:

a. BOQ for each Part of the Contract.

b. Summary of Bid Prices for all Parts of the Contract.

Project Duration: 19 calendar days

Submitted by:

Name and Signature of Bidder’s Representative: _________________________________

Position: ________________________________

Name of Bidder: ______________________________

Date: ________________

LOT C: COMPUTER LABORATORIES IMPROVEMENT:

A. Summary of BOQ for the Computer Laboratories Improvement:

ITEM

NO. DESCRIPTION QTY UNIT Unit Price

(in Pesos) Total Cost (in Pesos)

Lot C1 CEIT Computer Laboratory Improvement 1.00 lot Lot C2 CCJE Computer Laboratory Improvement 1.00 lot Lot C3 CTE Computer Laboratory Improvement 1.00 lot Lot C4 Rizal Computer Laboratory Improvement 1.00 lot

TOTAL BID AMOUNT (in figures): Php TOTAL BID AMOUNT (in words): Pesos

Note: The Bill of Quantities (BOQ) contains the following parts:

a. BOQ for each Part of the Contract.

b. Summary of Bid Prices for all Parts of the Contract.

Project Duration: 74 calendar days

Submitted by:

Name and Signature of Bidder’s Representative: _________________________________

Position: ________________________________

Name of Bidder: ______________________________

Date: ________________

B. Details of per Lot BOQ for the Package Contract for KSU Computer Laboratories Improvement:

LOT C1: CEIT COMPUTER LABORATORY IMPROVEMENT:

ITEM NO. DESCRIPTION QTY UNIT Unit Price

(in Pesos) Total Cost (in Pesos)

801 REMOVAL OF STRUCTURES AND

OBSTRUCTIONS (WALL) 0.54 sq.m

1047 METAL STRUCTURES (WIRE WAYS) 74.70 sq.m

1032(1)a2 PAINTING (STEEL) 74.70 sq.m

1027 CEMENT PLASTER FINISH 1.08 sq.m

1032(1)a1 PAINTING (MASONRY/CONCRETE) 1.08 sq.m

1100 ELECTRICAL 1.00 ls

B.7 OCCUPATIONAL SAFETY AND HEALTH

PROGRAM 1.00 ls

B.5 PROJECT BILLBOARD 1.00 piece

TOTAL BID AMOUNT (in figures): Php TOTAL BID AMOUNT (in words): Pesos

Note: The Bill of Quantities (BOQ) contains the following parts:

a. BOQ for each Part of the Contract.

b. Summary of Bid Prices for all Parts of the Contract.

Project Duration: 27 calendar days

Submitted by:

Name and Signature of Bidder’s Representative: _________________________________

Position: ________________________________

Name of Bidder: ______________________________

Date: ________________

LOT C2: CCJE COMPUTER LABORATORY IMPROVEMENT:

ITEM NO. DESCRIPTION QTY UNIT Unit Price

(in Pesos) Total Cost (in Pesos)

801 REMOVAL OF STRUCTURES AND

OBSTRUCTIONS (WALL) 0.09 sq.m

1047 METAL STRUCTURES (WIRE WAYS) 9.90 sq.m

1032(1)a2 PAINTING (STEEL) 9.90 sq.m

1027 CEMENT PLASTER FINISH 0.18 sq.m

1032(1)a1 PAINTING (MASONRY/CONCRETE) 0.18 sq.m

1100 ELECTRICAL 1.00 ls

B.7 OCCUPATIONAL SAFETY AND HEALTH

PROGRAM 1.00 ls

TOTAL BID AMOUNT (in figures): Php TOTAL BID AMOUNT (in words): Pesos

Note: The Bill of Quantities (BOQ) contains the following parts:

a. BOQ for each Part of the Contract.

b. Summary of Bid Prices for all Parts of the Contract.

Project Duration: 27 calendar days

Submitted by:

Name and Signature of Bidder’s Representative:_________________________________

Position :________________________________

Name of Bidder: ______________________________

Date: ________________

LOT C3: CTE COMPUTER LABORATORY IMPROVEMENT:

ITEM NO. DESCRIPTION QTY UNIT Unit Price

(in Pesos) Total Cost (in Pesos)

801 REMOVAL OF STRUCTURES AND

OBSTRUCTIONS (WALL) 0.27 sq.m

1047 METAL STRUCTURES (WIRE WAYS) 14.40 sq.m

1032(1)a2 PAINTING (STEEL) 14.40 sq.m

1027 CEMENT PLASTER FINISH 0.72 sq.m

1032(1)a1 PAINTING (MASONRY/CONCRETE) 0.72 sq.m

1100 ELECTRICAL 1.00 ls

B.7 OCCUPATIONAL SAFETY AND HEALTH

PROGRAM 1.00 ls

TOTAL BID AMOUNT (in figures): Php TOTAL BID AMOUNT (in words): Pesos

Note: The Bill of Quantities (BOQ) contains the following parts:

a. BOQ for each Part of the Contract.

b. Summary of Bid Prices for all Parts of the Contract.

Project Duration: 27 calendar days

Submitted by:

Name and Signature of Bidder’s Representative: _________________________________

Position: ________________________________

Name of Bidder: ______________________________

Date: ________________

LOT C4: RIZAL COMPUTER LABORATORY IMPROVEMENT

:

ITEM NO. DESCRIPTION QTY UNIT Unit Price

(in Pesos) Total Cost (in Pesos)

801 REMOVAL OF STRUCTURES AND

OBSTRUCTIONS (WALL) 0.18 sq.m

1047 METAL STRUCTURES (WIRE WAYS) 27.90 sq.m

1032(1)a2 PAINTING(STEEL) 27.90 sq.m

1027 CEMENT PLASTER FINISH 0.36 sq.m

1032(1)a1 PAINTING(MASONRY/CONCRETE) 0.36 sq.m

1100 ELECTRICAL 1.00 ls

B.7 OCCUPATIONAL SAFETY AND HEALTH

PROGRAM 1.00 ls

TOTAL BID AMOUNT (in figures): Php TOTAL BID AMOUNT (in words): Pesos

Note: The Bill of Quantities (BOQ) contains the following parts:

a. BOQ for each Part of the Contract.

b. Summary of Bid Prices for all Parts of the Contract.

Project Duration: 27 calendar days

Submitted by:

Name and Signature of Bidder’s Representative: _________________________________

Position: ________________________________

Name of Bidder: ______________________________

Date: ________________