B ILL OF Q UANTITIES

Dalam dokumen Bidding Document (Halaman 48-57)

49

BID PROPOSAL

PROJECT: Improvement and Expansion of Crop Biotech Center Power House LOCATION: PhilRice Central Experiment Station, Maligaya, S. C. Muñoz, Nueva Ecija

____________________________

Company Name

______________________________________________________

Name of Bidder

______________________________________________________

Position

______________________________________________________

Address of Bidder

______________________________________________________

Signature of Bidder

(Submit in Duplicate) ___________________

Date

50

Bid Form for the Procurement of Infrastructure Projects

[shall be submitted with the Bid]

__________________________________________________________________

BID FORM

Date : _________________

Project Identification No. : _________________

To: [name and address of Procuring Entity]

Having examined the Philippine Bidding Documents (PBDs) including the Supplemental or Bid Bulletin Numbers [insert numbers], the receipt of which is hereby duly acknowledged, we, the undersigned, declare that:

a. We have no reservation to the PBDs, including the Supplemental or Bid Bulletins, for the Procurement Project: [insert name of contract];

b. We offer to execute the Works for this Contract in accordance with the PBDs;

c. The total price of our Bid in words and figures, excluding any discounts offered below is: [insert information];

d. The discounts offered and the methodology for their application are: [insert information];

e. The total bid price includes the cost of all taxes, such as, but not limited to: [specify the applicable taxes, e.g. (i) value added tax (VAT), (ii) income tax, (iii) local taxes, and (iv) other fiscal levies and duties], which are itemized herein and reflected in the detailed estimates,

f. Our Bid shall be valid within the a period stated in the PBDs, and it shall remain binding upon us at any time before the expiration of that period;

g. If our Bid is accepted, we commit to obtain a Performance Security in the amount of [insert percentage amount] percent of the Contract Price for the due performance of the Contract, or a Performance Securing Declaration in lieu of the the allowable forms of Performance Security, subject to the terms and conditions of issued GPPB guidelines1 for this purpose;

h. We are not participating, as Bidders, in more than one Bid in this bidding process, other than alternative offers in accordance with the Bidding Documents;

i. We understand that this Bid, together with your written acceptance thereof included in your notification of award, shall constitute a binding contract between us, until a formal Contract is prepared and executed; and

j. We understand that you are not bound to accept the Lowest Calculated Bid or any other Bid that you may receive.

k. We likewise certify/confirm that the undersigned, is the duly authorized representative of the bidder, and granted full power and authority to do, execute and perform any and all acts necessary to participate, submit the bid, and to sign and

1 currently based on GPPB Resolution No. 09-2020

51

execute the ensuing contract for the [Name of Project] of the [Name of the Procuring Entity].

l. We acknowledge that failure to sign each and every page of this Bid Form, including the Bill of Quantities, shall be a ground for the rejection of our bid.

Name: ___________________________________________________________________

Legal Capacity: ____________________________________________________________

Signature: ________________________________________________________________

Duly authorized to sign the Bid for and behalf of: __________________________________

Date: ___________________

52

PROJECT: Improvement and Expansion of Crop Biotech Center Power House

LOCATION: PhilRice Central Experiment Station, Maligaya, S. C. Muñoz, Nueva Ecija SUBJECT: SUMMARY OF BID PROPOSAL/BREAKDOWN OF VALUES OF WORK

ITEM SCOPE OF WORKS

DIRECT COST

INDIRECT COST (Profit,

Tax, OCM)

TOTAL COST (Direct + Indirect Cost) Materials Labor

I. SITE WORKS

II. CONCRETE WORKS

III. REINFORCING STEEL BARS

IV. FORMWORKS AND SCAFFOLDINGS V. MASONRY WORKS

VI. PAINTING WORKS VII. ELECTRICAL WORKS

VIII.

ROLL-UP DOOR, CABLE RACK &

STEEL GRATING COVER, AND WATERPROOFING

IX. OTHERS

TOTAL PROJECT COST

Breakdown of Indirect Cost (%):

OCM ( %) ____________________

Profit ( %) ____________________

Tax (5%) ____________________

Others (Specify) ____________________

TOTAL ____________________

53

PROJECTS : IMPROVEMENT AND EXPANSION OF CROP BIOTECH CENTER POWER HOUSE

SUBJECT BILL OF QUANTITIES

LOCATION : PHILRICE-CES, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA

Scope of Works

EXPANSION/IMPROVEMENTOF POWER HOUSE - 23.8 sq.m. building expansion

- 2meters width x 0.125mm thk perimeter pathwalk with 10mm dia. reinforcing steel bars

WALL FINISHED

- Repair of damage louver blocks and installation of new louver block walls (same design of existing louver blocks)

- External and Internal walls Paint Finished FLOOR FINISHED

- 0.125m thk slab-on-grade with 12mm dia. reinforcing steel bars spaced at 0.3m bothways

- 0.125m thk roof slab with 12mm dia. reinforcing steel bars spaced at 0.15m bothways top and bottom, with waterproofing

- 4.5m x 2.2m x 0.5m thk concrete pad for genset with 12mm dia. reinforcing steel bars - 0.6m x 0.6m cable pit with 1" dia G.I. pipe cable rack

- 0.3m x 0.1m depth spil canal

- 3.5 x 2.8m G.A 18 Aluminum G.I Roll - Up Door, 2.0 x 2.8m G.A 18 Aluminum G.I Roll - Up Door

ELECTRICAL:

- Installation of Electrical Lines and Panelboard

- Brand New Electrical Wirings/ Conduits, Electrical Devices and Fixtures.

- Rehabilitation/Replacement of existing panel for traning dorm 1&2 - 18watts, T8 LED Lights, Explosion Proof

- Solar Street Lights, Premium Integrated Solar 100watts, 250wattws Solar Panel with Built-in Motion Sensor Visual Angle 120 degrees, Lithium Battery, Work time ≥ 10hours full power / ≥ 24hours half power, Bracket Included, IP Rating : IP65 - Temporary relocation of transformer and reinstallation upon completion of building

extension

- Cable rack and steel grating cover

3.5 x 2.8m G.A 18 Aluminum G.I Roll - Up Door, 2.0 x 2.8m G.A 18 Aluminum G.I Roll - Up Door

Fuel Dispensing Pump (Single)

54

QUANTITY UNIT PARTICULARS MATERIALS COST

LABOR + EQUIPMENT

COST

AMOUNT

I. SITE WORKS

1 lot A. Site Clearing and

Demolition Works

21.92 cu.m B. Structural Excavation

21.92 cu.m C. Backfill

47.71 Cu.m

D. Earth fill/ Rice field soil &

Compaction

9.18 Cu.m E. Gravel bedding &

Compaction

1 lot F. Temporary Facilities

TOTAL

II. CONCRETE WORKS

2.9 cu.m A. Column, Column Footing &

Wall Footing

2.89 cu.m B. Tie Beam & RC Beam

13.04 cu.m C. Slab on Fill, Roof Slab and

Perimeter Pathway

4.95 cu.m D. Concrete Pad for Genset

TOTAL

III. REINFORCING STEEL BAR

1790.39 kgs

16 mm dia DRSB x 6.0m,12 mm dia DRSB x 6.0m,10 mm dia DRSB x 6.0m & #16 G.I.

Tie Wire

TOTAL

IV. FORM WORKS AND SCAFFOLDINGS

1 lot

Form Plywood 1/2" thk (4ft x 8ft), Form Lumber 2" x 3", Form Lumber 2" x 2", Assorted CWN, Consumables ( jigsaw

blade,Cutting accessories. Etc)

TOTAL

V. MASONRY WORKS

113.12 sq.m

5" thk CHB, 0.20M X 0.20M LOUVER BLOCKS, Portland Cement, 40kgs/bag, Washed Sand, 10 mm dia DRSB, #16 G.I. Wire, Consumables

(string, CWN. Etc)

TOTAL

VI. PAINTING WORKS

276.7 sq.m.

Flat Latex Paint ( Boysen), Semi-Gloss Latex Paint ( Boysen), Concrete Nuetralizer, Assorted paint roller with tray, Assorted Paint Brush, Painting Consumables (Masking Tape,Sanding Paper, Rugs

etc.)

TOTAL

55 VII. ELECTRICAL WORKS

1 lot

A. Boxes , Conduits And Fittings:

Utility Box, Junction Box, Emt Pipe, 25mm², Consumables (Tie Wire, Rags, Solvent,

Coupling, etc.)

B. Wires And Cables:

2.0mm², 3.5mm², 5.5mm²

THHN cu wire (150m/box) C. ELECTRICAL FIXTURES &

DEVICES : 18watts,8.0mm² THHN cu wire, T8 LED Lights, Explosion Proof, Convenience outlet 2-gang Universal with ground, Special Purpose Outlet, Switch 2-gang with reflector, 26" x 26" Exhaust Fan with Louver Cover and Ducting, Emergency Light, Panel Board (75AT,100AT, 240V,60hz,MCCB branches 1- 15AT, 3-20AT, Bolt-on Type, 3Phase with Grounding Busbar Industrial Type), Replacement of enclosure with grounding busbar, floor

standing, Solar Street Lights, Premium Integrated Solar 100watts, 250wattws Solar Panel with Built-in Motion Sensor Visual Angle 120 degrees, Lithium Battery, Work time ≥ 10hours full power / ≥ 24hours half power, Bracket

Included, IP Rating : IP65 D.

REHABILITATION/REPLACE MENT OF EXISTING PANEL

FOR TRAINING DORM : Panel Board - 250AT Main

Breaker, 3Phase with

Branches, 6-150AT 2-70AT 2- 60AT breaker, 3Phase MCCB Bolt-on Type (Industrial Type), In NEMA 1 Enclosure with Grounding Busbar with Push Lock Keys Guage #18 floor standing, Butt Connector (325mm², 150mm²), 150mm²

THHN cu wire (150m/roll)

TOTAL

VIII. ROLL-UP DOOR, CABLE RACK & STEEL GRATING COVER, AND WATERPROOFING

1 lot

3.5 x 2.8m G.A 18 Aluminum G.I Roll - Up Door, 2.0 x 2.8m G.A 18 Aluminum G.I Roll - Up Door, 1 1/2" x 1/4" thk Angle Bar, 1" G.I. Pipe, Bituminous

Membrane Waterproofing

TOTAL

IX. OTHERS

56 1 lot Professional Fees / Permits /

Testing Fees /PPE'S/ Signage

TOTAL

Summary of Cost

Direct Cost

Material Cost + labor Cost + Equipment Rental Cost

Indirect Cost

OCM

Profit

Tax

GRAND TOTAL Amount in Words:

57