UNIT QTY. UNIT COST AMOUNT I. POWER / ELECTRICAL ROOM: (16.00SQ.M)
Direct Cost:
a. Materials
Cement bags 0.00
Sand cu.m 0.00
Gravel cu.m 0.00
CHB 5" pcs. 0.00
9mm x 6m pcs. 0.00
10mm x 6m pcs. 0.00
16mm x 6m pcs. 0.00
Door with lockset set 0.00
Sliding Window sq.ft 0.00
Primer Latex Paint gal 0.00
Latex Paint gal 0.00
Water Proofing sq.m 0.00
Hardware lot 0.00
0.00 b. Labor Cost:
Foreman days 0.00
Skilled days 0.00
Labor days 0.00
0.00 0.00 O.C.M. (6%) :
Profit (8%) : VAT (7%) :
0.00 0.00
Direct Cost:
a. Materials
a.) LIGHTING & SWITCHES
36W FLUORESCENT LAMP (FL) pc 0.00
Single switch pc 0.00
b.) OUTLET 0.00
Convenience Outlet, 2 Gang, universal headboard pc 0.00
Exhaust Fan outlet pc 0.00
ACU outlet pc 0.00
c.) CONDUITS 0.00
IMC (20mm dia) m 0.00
IMC (50mm dia) m 0.00
II. ELECTRICAL WORKS
TOTAL INDIRECT COST INDIRECT COST:
TOTAL COST OF POWER HOUSE
TOTAL DIRECT COST
- - - ITEM OF WORK
PROJECT TITLE: Construction of Automated Guideway Transit (AGT) as Laboratory Facility of the Proposed Railway Engineering Program of College of Engineering and Architecture (CEA) at BPSU Main Campus LOCATION: BPSU MAIN CAMPUS
sub-total
sub-total
RSC (32mm dia) pc 0.00
RSC (20mm dia) pc 0.00
RSC (80mm dia) pc 0.00
PVC (20mm dia) pc 0.00
RMC (65mm dia) pc 0.00
d.) BREAKERS (ACB) 0.00
10 AT/AF, 1-phase pc 0.00
15 AT/AF, 1-phase pc 0.00
20 AT/AF, 1-phase pc 0.00
30 AT/AF, 1-phase pc 0.00
40 AT/AF, 1-phase pc 0.00
40 AT/AF, 1-phase, NEMA 1 ENCL pc 0.00
70 AT/AF, 1-phase pc 0.00
75 AT/AF, 1-phase pc 0.00
150 AT/AF, 1-phase, 15 kAIC pc 0.00
160 AT/AF, 1-phase pc 0.00
200 AT/AF, 1-phase, 15 Kaic, VDC pc 0.00
300 AT/AF, 3-phase, 15 kAIC pc 0.00
400 AT/AF, 1-phase, 100 kAIC pc 0.00
500 AT/AF, 3-phase, NEMA 1 ENCL pc 0.00
750 AT/AF, 3-phase, NEMA 1 ENCL pc 0.00
800 AT/AF, 3-phase, NEMA 1 ENCL pc 0.00
e.) WIRES AND CABLES 0.00
2.0 mm2 THHN Cu Wire (150 m) box 0.00
3.5 mm2 THHN Cu Wire (150 m) box 0.00
3.5 mm2 THWN Cu Wire (150 m) box 0.00
5.5 mm2 THHN Cu Wire (150 m) box 0.00
22 mm2 THHN Cu Wire m 0.00
30 mm2 THHN Cu Wire m 0.00
50 mm2 THHN Cu Wire m 0.00
60 mm2 THHN Cu Wire m 0.00
125 mm2 THHN Cu Wire m 0.00
150 mm2 THHN cu Wire m 0.00
200 mm2 THHN Cu Wire m 0.00
250 mm2 THHN Cu Wire m 0.00
f.) PANEL BOARDS 0.00
6 branches, 1-phase, MCCB pc 0.00
4 branches, 1-phase, MCCB pc 0.00
2 branches, 1-phase, MCCB pc 0.00
2 branches, 3-phase, MCCB pc 0.00
g.) TRANSFORMERS 0.00
300 KVA, 3ph, 60hz, 460/460V pc 0.00
300 KVA, 3ph, 60hz, 230/460V pc 0.00
30 FT, Galvanized steel pole pc 0.00
h.) FITTINGS and others 0.00
Grounding Rod, 3/4 x 8 ft pc 0.00
Solderless connector (250 mm2) pc 0.00
Electrical tape pc 0.00
Rubber Tape pc 0.00
Junction Box, galvanized pc 0.00
Utility Box, galvanized pc 0.00
Tox and screw pc 0.00
Lock Nuts pc 0.00
Conduit Clamps pc 0.00
i.) PENELCO 0.00
Provision of 3 - phase line (PENELCO) lot 0.00
Sensor and Signaling lot 0.00
Metering (PENELCO) lot 0.00
0.00 b. Labor Cost:
Electrical Engineer days 0.00
Electrician days 0.00
Helper days 0.00
0.00 0.00 O.C.M. (6%) :
Profit (8%) : VAT (7%) :
0.00 0.00
III. ELEVATED TRACK Direct Cost:
a. Materials
Cement bags 0.00
Sand cu.m 0.00
Gravel cu.m 0.00
10 mm pcs 0.00
12 mm pcs 0.00
16mm pcs 0.00
20 mm pcs 0.00
25 mm pcs 0.00
2" x 2" x 3.5mm x 6m angle bar pcs 0.00
8mm x 6m armoring dowel pcs 0.00
Primer paint gal 0.00
QDE Paint gal 0.00
scaffolding and formworks cu.m 0.00
hardware lot 0.00
0.00 b. Labor Cost:
Foreman days 0.00
Skilled days 0.00
Labor days 0.00
0.00 0.00 O.C.M. (6%) :
Profit (8%) : VAT (7%) :
0.00 sub-total
TOTAL DIRECT COST INDIRECT COST:
- - - TOTAL INDIRECT COST
TOTAL INDIRECT COST TOTAL COST OF ELECTRICAL WORKS
sub-total sub-total TOTAL DIRECT COST INDIRECT COST:
- - sub-total
-
0.00
IV. WALKWAY Direct Cost:
a. Materials
2" x 2" x 1.5mm Square Tube pcs 0.00
cement bags 0.00
sand cu.m 0.00
gravel cu.m 0.00
10 mm x 6m pcs 0.00
12 mm x 6m pcs 0.00
16 mm x 6m pcs 0.00
2" x 6" C Channel pcs 0.00
hardware lot 0.00
0.00 b. Labor Cost:
Foreman days 0.00
Skilled days 0.00
Labor days 0.00
0.00 0.00 O.C.M. (6%) :
Profit (8%) : VAT (7%) :
0.00 0.00
Direct Cost:
a. Materials
Cement bags 0.00
Sand cu.m 0.00
Gravel cu.m 0.00
10 mm pcs 0.00
16mm pcs 0.00
2" x 2" x 3.5mm x 6m angle bar pcs 0.00
2" Flat bar pcs 0.00
Primer paint gal 0.00
QDE Paint gal 0.00
landscape lot 0.00
hardware lot 0.00
0.00 b. Labor Cost:
Foreman days 0.00
Skilled days 0.00
Labor days 0.00
0.00 INDIRECT COST:
- - - TOTAL INDIRECT COST
V. SITE DEVELOPMENT
TOTAL COST OF WALKWAY
sub-total
sub-total TOTAL DIRECT COST TOTAL COST OF ELEVATED TRACK
sub-total
sub-total
0.00 O.C.M. (6%) :
Profit (8%) : VAT (7%) :
0.00 0.00
0.00 TOTAL CONSTRUCTION COST
- - - TOTAL INDIRECT COST
TOTAL COST OF SITE DEVELOPMENT INDIRECT COST:
TOTAL DIRECT COST
PREPARED BY:
NOTED BY: