• Tidak ada hasil yang ditemukan

Labor Cost: Foreman days 0.00 Skilled days 0.00 Labor days O.C.M

N/A
N/A
Protected

Academic year: 2023

Membagikan "Labor Cost: Foreman days 0.00 Skilled days 0.00 Labor days O.C.M"

Copied!
5
0
0

Teks penuh

(1)

UNIT QTY. UNIT COST AMOUNT I. POWER / ELECTRICAL ROOM: (16.00SQ.M)

Direct Cost:

a. Materials

Cement bags 0.00

Sand cu.m 0.00

Gravel cu.m 0.00

CHB 5" pcs. 0.00

9mm x 6m pcs. 0.00

10mm x 6m pcs. 0.00

16mm x 6m pcs. 0.00

Door with lockset set 0.00

Sliding Window sq.ft 0.00

Primer Latex Paint gal 0.00

Latex Paint gal 0.00

Water Proofing sq.m 0.00

Hardware lot 0.00

0.00 b. Labor Cost:

Foreman days 0.00

Skilled days 0.00

Labor days 0.00

0.00 0.00 O.C.M. (6%) :

Profit (8%) : VAT (7%) :

0.00 0.00

Direct Cost:

a. Materials

a.) LIGHTING & SWITCHES

36W FLUORESCENT LAMP (FL) pc 0.00

Single switch pc 0.00

b.) OUTLET 0.00

Convenience Outlet, 2 Gang, universal headboard pc 0.00

Exhaust Fan outlet pc 0.00

ACU outlet pc 0.00

c.) CONDUITS 0.00

IMC (20mm dia) m 0.00

IMC (50mm dia) m 0.00

II. ELECTRICAL WORKS

TOTAL INDIRECT COST INDIRECT COST:

TOTAL COST OF POWER HOUSE

TOTAL DIRECT COST

- - - ITEM OF WORK

PROJECT TITLE: Construction of Automated Guideway Transit (AGT) as Laboratory Facility of the Proposed Railway Engineering Program of College of Engineering and Architecture (CEA) at BPSU Main Campus LOCATION: BPSU MAIN CAMPUS

sub-total

sub-total

(2)

RSC (32mm dia) pc 0.00

RSC (20mm dia) pc 0.00

RSC (80mm dia) pc 0.00

PVC (20mm dia) pc 0.00

RMC (65mm dia) pc 0.00

d.) BREAKERS (ACB) 0.00

10 AT/AF, 1-phase pc 0.00

15 AT/AF, 1-phase pc 0.00

20 AT/AF, 1-phase pc 0.00

30 AT/AF, 1-phase pc 0.00

40 AT/AF, 1-phase pc 0.00

40 AT/AF, 1-phase, NEMA 1 ENCL pc 0.00

70 AT/AF, 1-phase pc 0.00

75 AT/AF, 1-phase pc 0.00

150 AT/AF, 1-phase, 15 kAIC pc 0.00

160 AT/AF, 1-phase pc 0.00

200 AT/AF, 1-phase, 15 Kaic, VDC pc 0.00

300 AT/AF, 3-phase, 15 kAIC pc 0.00

400 AT/AF, 1-phase, 100 kAIC pc 0.00

500 AT/AF, 3-phase, NEMA 1 ENCL pc 0.00

750 AT/AF, 3-phase, NEMA 1 ENCL pc 0.00

800 AT/AF, 3-phase, NEMA 1 ENCL pc 0.00

e.) WIRES AND CABLES 0.00

2.0 mm2 THHN Cu Wire (150 m) box 0.00

3.5 mm2 THHN Cu Wire (150 m) box 0.00

3.5 mm2 THWN Cu Wire (150 m) box 0.00

5.5 mm2 THHN Cu Wire (150 m) box 0.00

22 mm2 THHN Cu Wire m 0.00

30 mm2 THHN Cu Wire m 0.00

50 mm2 THHN Cu Wire m 0.00

60 mm2 THHN Cu Wire m 0.00

125 mm2 THHN Cu Wire m 0.00

150 mm2 THHN cu Wire m 0.00

200 mm2 THHN Cu Wire m 0.00

250 mm2 THHN Cu Wire m 0.00

f.) PANEL BOARDS 0.00

6 branches, 1-phase, MCCB pc 0.00

4 branches, 1-phase, MCCB pc 0.00

2 branches, 1-phase, MCCB pc 0.00

2 branches, 3-phase, MCCB pc 0.00

g.) TRANSFORMERS 0.00

300 KVA, 3ph, 60hz, 460/460V pc 0.00

300 KVA, 3ph, 60hz, 230/460V pc 0.00

30 FT, Galvanized steel pole pc 0.00

h.) FITTINGS and others 0.00

Grounding Rod, 3/4 x 8 ft pc 0.00

Solderless connector (250 mm2) pc 0.00

Electrical tape pc 0.00

Rubber Tape pc 0.00

Junction Box, galvanized pc 0.00

Utility Box, galvanized pc 0.00

Tox and screw pc 0.00

Lock Nuts pc 0.00

(3)

Conduit Clamps pc 0.00

i.) PENELCO 0.00

Provision of 3 - phase line (PENELCO) lot 0.00

Sensor and Signaling lot 0.00

Metering (PENELCO) lot 0.00

0.00 b. Labor Cost:

Electrical Engineer days 0.00

Electrician days 0.00

Helper days 0.00

0.00 0.00 O.C.M. (6%) :

Profit (8%) : VAT (7%) :

0.00 0.00

III. ELEVATED TRACK Direct Cost:

a. Materials

Cement bags 0.00

Sand cu.m 0.00

Gravel cu.m 0.00

10 mm pcs 0.00

12 mm pcs 0.00

16mm pcs 0.00

20 mm pcs 0.00

25 mm pcs 0.00

2" x 2" x 3.5mm x 6m angle bar pcs 0.00

8mm x 6m armoring dowel pcs 0.00

Primer paint gal 0.00

QDE Paint gal 0.00

scaffolding and formworks cu.m 0.00

hardware lot 0.00

0.00 b. Labor Cost:

Foreman days 0.00

Skilled days 0.00

Labor days 0.00

0.00 0.00 O.C.M. (6%) :

Profit (8%) : VAT (7%) :

0.00 sub-total

TOTAL DIRECT COST INDIRECT COST:

- - - TOTAL INDIRECT COST

TOTAL INDIRECT COST TOTAL COST OF ELECTRICAL WORKS

sub-total sub-total TOTAL DIRECT COST INDIRECT COST:

- - sub-total

-

(4)

0.00

IV. WALKWAY Direct Cost:

a. Materials

2" x 2" x 1.5mm Square Tube pcs 0.00

cement bags 0.00

sand cu.m 0.00

gravel cu.m 0.00

10 mm x 6m pcs 0.00

12 mm x 6m pcs 0.00

16 mm x 6m pcs 0.00

2" x 6" C Channel pcs 0.00

hardware lot 0.00

0.00 b. Labor Cost:

Foreman days 0.00

Skilled days 0.00

Labor days 0.00

0.00 0.00 O.C.M. (6%) :

Profit (8%) : VAT (7%) :

0.00 0.00

Direct Cost:

a. Materials

Cement bags 0.00

Sand cu.m 0.00

Gravel cu.m 0.00

10 mm pcs 0.00

16mm pcs 0.00

2" x 2" x 3.5mm x 6m angle bar pcs 0.00

2" Flat bar pcs 0.00

Primer paint gal 0.00

QDE Paint gal 0.00

landscape lot 0.00

hardware lot 0.00

0.00 b. Labor Cost:

Foreman days 0.00

Skilled days 0.00

Labor days 0.00

0.00 INDIRECT COST:

- - - TOTAL INDIRECT COST

V. SITE DEVELOPMENT

TOTAL COST OF WALKWAY

sub-total

sub-total TOTAL DIRECT COST TOTAL COST OF ELEVATED TRACK

sub-total

sub-total

(5)

0.00 O.C.M. (6%) :

Profit (8%) : VAT (7%) :

0.00 0.00

0.00 TOTAL CONSTRUCTION COST

- - - TOTAL INDIRECT COST

TOTAL COST OF SITE DEVELOPMENT INDIRECT COST:

TOTAL DIRECT COST

PREPARED BY:

NOTED BY:

Referensi

Dokumen terkait

Mathematically it can be written as follows: Efficiency of lowland rice farming R/C Ratio = Information : TR = Total Revenue / Receipt of paddy rice farming Rp TC = Total Cost / cost

Directors Name Direct Indirect Total direct & indirect shares % to Total Outstanding Shares Dr... Name Direct Indirect Total direct & indirect shares % to Total Outstanding