PERFORMANCE INDICATORS USED IN THE PERFORMANCE INCENTIVE
SCHEME OF THE NATIONAL TRANSMISSION CORPORATION
PAULA MICHELLE R. ARAGON
2004-39960
SUBMITTED TO THE FACULTY OF THE
COLLEGE OF ENGINEERING AND AGRO-INDUSTRIAL TECHNOLOGY, UNIVERSITY OF THE PHILIPPINES LOS BAÑOS,
IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE DEGREE OF
BACHELOR OF SCIENCE IN ELECTRICAL ENGINEERING
MARCH 2009
TABLE OF CONTENTS
Biographical Sketch iii
Acknowledgement iv
Table of Contents vi
List of Figures ix
List of Tables x
I. Introduction 1
A. Description of the Study 2
B. Significance of the Study 2
C. Objectives 3
D. Scope and Limitations 3
E. Date and Place of Study 4
F. Company Profile 4
G. Training Activities 7
II. Review of Literature 8
A. Reliability 9
A.1. Definition 9
A.2. Reliability Indicators 9
A.2.1. System Average Interruption Frequency Index 9 A.2.2. System Average Interruption Duration Index 9 A.2.3. Customer Average Interruption Duration Index 10 A.2.4. Momentary Average Interruption Frequency Index 10
B. Power Quality 10
C. Classification of Outages 11
C.1. Forced Outage 11
C.1.1. Momentary Fault 11
C.1.2. Oversized Fuse Cut-out Along the Line 12
C.1.3. Vegetation 12
C.1.4. Sagging 12
C.1.5. Substation Equipment Trouble 12
C.1.6. Human Error 13
C.1.7. Broken Cross Arm 13
C.1.8. Cut Conductor 13
C.1.9. Insulation Failure 13
C.1.10. Damaged Pole/Tower 13
C.1.11. Defective Connectors 14
C.1.12. Cut Guy Wire 14
C.1.13. Fire 14
C.1.14. Sustained Fault 14
C.1.15. Cut Overhead Ground Wires 15
C.1.16. Delayed Completion of Maintenance Activity 15
C.1.17. Sustained Fault 15
C.1.18. Customer Caused Outage Protection Coordination
Without Validation 15
C.1.19. Delayed Switching/Normalization of Load 16
C.2. Planned Outage 16
C.2.1. Planned/Scheduled Maintenance Outage 16
C.2.2. Corrective Maintenance Outage 16
C.3. Other Outages 16
C.3.1. Forced Majeure 16
C.3.2. Manual Load Dropping Due to Generation Deficiency 17
C.3.3. Design/Construction Deficiency 17
C.3.4. Automatic Load Dropping Due to Plant Outage 17
C.3.5. System Planning Deficiency 17
C.3.6. Delayed Project Completion 18
C.3.7. Customer Caused Outage 18
C.3.8. Switching 18
C.3.9. Tariff Metering 18
C.1.10. Accidents/Intrusion/Incursion of Foreign Objects 19
C.3.11. Uncooperative Land Owner 19
C.3.12. War, Rebellion, Vandalism, Pilferage and Criminal 19 C.3.13. Fault Clearance Failure/Misoperations 19 C.3.14. Planned Required by Projects and Other Groups 19
C.3.15. Human Error of Other Groups 20
C.3.16. Management 20
C.3.17. General Contingency Plan 20
C.3.18. Communication Problems 20
D. Monitoring, Recording and Processing of Data 20
D.1. System Performance Monitoring 21
D.2. Power Quality Monitoring 22
D.2.1. Supervisory Control and Data Acquisition 22
D.2.1.1. Human Machine Interface 22
D.2.1.2. Remote Terminal Units 23
D.2.1.3. Supervisory Station 23
D.2.2. TransCo Communications and Remote SCADA Systems 23
III. Study Methodology 25
IV. Discussion and Analysis 27
A. Performance Based Regulation 28
B. TransCo’s Performance Incentive Scheme 29
B.1. Performance Indicators 29
B.1.1. System Interruption Severity Index (SISI) 29 B.1.2. Frequency of Tripping per 100ckt-km (FOT) 30
B.1.3. System Availability (SA) 31
B.1.4. Frequency Limit Compliance (FLC) 32
B.1.5. Voltage Limit Compliance (VLC) 33
B.2. Performance Targets 35
B.3. Weightings of Performance Indicators 38 B.4. Computation of the Performance Indicators 38
B.4.1. Calculation of SISI 39
B.4.2. Calculation of FOT 41
B.4.3. Calculation of SA 42
B.4.4. Calculation of FLC 43
B.4.5. Calculation of VLC 46
B.5. Performance Evaluation 49
B.6. Computation of Reward or Penalty 50
B.6.1. Incentive/Penalty Multiplier 52
B.6.2. Calculation of Net Reward 53
V. Observations 57
VI. Conclusion 59
VII. Recommendations 61
Literature Cited 63
Appendices 65
LIST OF FIGURES
Figure 1. Performance vs. Reward/Penalty for a Negative Measure 37 Figure 2. Performance vs. Reward/Penalty for a Positive Measure 37
LIST OF TABLES
Table 1. Activities held at the Performance Assessment Division of the Power
Network Planning of the National Transmission Corporation. 7 Table 2. Control Centers of the National Transmission Corporation 22 Table 3. List of Interruption Events Excluded from the Calculation of Reliability
Indices SISI & FOT 30
Table 4. Frequency Monitoring Points 33
Table 5. Nominal Voltages per Grid that are Monitored for VLC 33
Table 6. Voltage Monitoring Points 34
Table 7. Five (5) Year Average of TransCo’s Historical Data from 2000 to 2004 35 Table 8. Bandwidth for the Performance Indicators for each Grid 36 Table 9. Weightings of the Performance Indices by Grid 38 Table 10. SISI Sample Data of Luzon Grid from August 26, 2007- August 25,
2008 39
Table 11. SISI Sample Data of Visayas Grid from August 26, 2007- August 25,
2008 40
Table 12. SISI Sample Data of Mindanao Grid from August 26, 2007- August 25,
2008 40
Table 13. FOT Sample Data of Luzon Grid from August 26, 2007- August 25,
2008 41
Table 14. FOT Sample Data of Visayas Grid from August 26, 2007- August 25,
2008 42
Table 15. FOT Sample Data of Mindanao Grid from August 26, 2007- August 25,
2008 42
Table 16. SA Sample Data of the Grids from August 26, 2007- August 25, 2008 43 Table 17. FLC Sample Data of Luzon Grid from August 26, 2007- August 25,
2008 44
Table 18. FLC Sample Data of Visayas Grid from August 26, 2007- August 25,
2008 45
Table 19. FLC Sample Data of Mindanao Grid from August 26, 2007 - August 25,
2008 46
Table 20. VLC Sample Data of Luzon Grid from August 26, 2007- August 25,
2008 47
Table 21. FLC Sample Data of Visayas Grid from August 26, 2007- August 25,
2008 48
Table 22. FLC Sample Data of Mindanao Grid from August 26, 2007- August 25,
2008 49
Table 23. Evaluation of TransCo’s Performance for the Year 2008 50 Table 24. Breakdown of Allocated Incentives and Allowable Reward and Penalty 51
Table 25. Incentive/ (Penalty) Multiplier 53
Table 26. Calculation of the Net Reward 55