WP01: Background of Deployment of ICRM Project

45

Deployment of ICRM Projects in the Southeast Asian Countries

Seiichi Etoh

Project Leader, Coastal Resources Management SEAFDEC/TD

Introduction

In most Southeast Asian countries, the deterioration of livelihoods in coastal fishing communities resulting from the over-exploitation of fishery resources and the degradation of coastal environments had became a pivotal concern for fishery policy makers that steered the relevant authorities to introduce some measures to improve the situation. One of the approaches recognized as appropriate was the introduction of the concept of community-based fisheries management (CBFM) within the framework of the devolution of coastal fisheries development and management.

Based on the SEAFDEC project on the Regionalization of the Code of Conduct for Responsible Fisheries and under the collaborative mechanism of the ASEAN-SEAFDEC Fisheries Consultative Group (FCG), Thailand was designated as the lead country for the SEAFDEC Member Countries and the SEAFDEC Training Department (SEAFDEC/TD) as the Lead SEAFDEC Department for activities related to fisheries management. Thus, SEAFDEC/TD collaborated with the Department of Fisheries (DOF) of Thailand in implementing a coastal resource management program. This led to the reformatting of an existing project proposal on coastal resource management for Chumpon Province prepared by DOF Thailand as it became a joint initiative with SEAFDEC/TD. It was further agreed that the knowledge and experience gained through the project operation in Thailand would be disseminated to the other SEAFDEC Member Countries through the technology transfer mechanism of SEAFDEC.

Locally Based Coastal Resources Management/Integrated Coastal Resources Management Project

Consequently, the five-year project on “Locally Based Coastal Fishery Management in Pathew District (LBCFM-PD)” commenced in November 2001 in Chumpon Province, Thailand with the overall objectives of: (1) establishing sustainable coastal resources management mechanism at the local level; (2) rehabilitating the coastal fishery resources; and (3) alleviating poverty in coastal fishing communities.

The LBCFM-PD project had produced tangible impact as acknowledged by the SEAFDEC Member Countries during the 4th SEAFDEC FCG Meeting in Myanmar in March 2002 and at the 25th SEAFDEC Program Committee Meeting in Singapore in October 2002. It was during the latter meeting that a recommendation was raised to impart the technologies including the experience and knowledge gained from the project LBCFM-PD to the other Member Countries. In this connection, the Committee Member for Malaysia offered Langkawi as a pilot site for the implementation of a similar approach to the LBCFM-PD project. Subsequently, SEAFDEC/TD missions to Langkawi were organized to look into the possibility of setting up a similar coastal fishery resources management and development project. Eventually, the second project on “Locally Based Coastal Resources Management – Pulau Langkawi (LBCRM–PL)” took off in August 2003 for a period of four years.

These two projects were jointly financed by their respective governments and the Japanese Trust Fund I Program in SEAFDEC through TD, and later reformulated to fit into the new thrust of the Japanese Trust Fund IV Program, which commenced in 2005 under the new program domain on “Capacity Building of Human Resources and Participation in Integrated Coastal Resources Management”. Since this new program placed more emphasis on human resources development (HRD), the projects’ titles were changed correspondingly into Integrated Coastal Resources Management in Pathew District (ICRM-PD) and Integrated Coastal Resources Management in Langkawi (ICRM-PL) to take into consideration the thrust of the new program, and eventually comprising the second phase of the project.

(2)

Meanwh meeting project collabor initiate s take pla CBRM the prop fisheries submitte were the Eventua While th in Lang devastat were de was cha order to years un the rehab the end tsunami terminat the proje 2009 to practices

The Prov ICR

Region Approa hile, further

s (PCM) in operations rative project

similar proje ce in Cambo approach in posed site an

s. Based on ed to the 27 en taken to ally, the proje he ICRM-PD gkawi, Malay ting tsunami

stroyed or lo anged in orde pursue the r ntil Decembe bilitation of

of 2007 tha . Consequen ted in Decem ect ICRM-SV

complete th s following t

ICRM pilot vince: ICRM RM-SV)

nal Seminar o ach in Southea

recommend 2003 and 20 should be t approach. T ects in their r

odia taking i the country.

d to collect r n the finding

th PCM held put the proj ect commenc D project in

ysia had als damaged th ost, and the er to focus on

remaining ac er 2007. Wit

the fishing f at the fishin ntly, the proj mber 2007 w

V in Sihanou he on-going the communi

projects imp M-PD), in Mala

on Integrated ast Asia: Revi dations were 004 specifyin transferred To this end, t respective co into account . The prelim relevant data gs and obse d in Decemb oject forward ced its operat Chumphon w so progresse he pro ject op fish landing n the rehabil ctivities base th the main fleet and fish ng activity h ject activitie ith the final ukville, Cam activities in ity developm

lemented by aysia (Pulau

Coastal Resou iew of the proj e put forwa ng that expe

to other the other Me ountries. Fina the geograp minary site su a and inform ervations fro ber 2004 wh d and for th tion on 11 N was terminat ed but was perational are

facilities we litation of th ed on the ori

focus of the hery facilities had more or es which hav project evalu mbodia, has b

n connection ment approac

SEAFDEC in Langkawi: IC

urces Manage ject ICRM-PL ard at the S eriences and

SEAFDEC ember Count ally, it was d phical advant urvey was ca mation with re

om the surv hich was sub he initiation November 200

ted in Decem disrupted on ea in Langka ere ruined. T he area includ iginal object

project activ s damaged by less resume ve also norm uation condu een extended n with coasta

h.

n Thailand (P CRM-PL), an

ement L

SEAFDEC knowledge

Member C tries express decided that tage and the arried out in egards to res vey, a tenta bsequently e

of the actua 05 signaling mber 2006, t

n 26 Decem awi. Most fi Thereafter, th

ding repair o tive, the proj vity in 2005 y the tsunam ed as it was malized in ea

ucted in Mar d for another al fishery re

Pathew Distr nd in Cambo

Program Co gained throu Countries un

ed their inten the 3rd proje

prioritized n June 2004 to sponsible com ative work-p

ndorsed. Th al activities its three-yea the ICRM-PL mber 2004 w ishing gear a he project or of the fishing ject for anot 5 and 2006 p mi, it was onl s in 2004 be

arly 2007 h ch 2008. Me r year until th

sources man

ict, Chumpho odia (Sihanou

46 ommittee ugh these nder the

nsions to ect would need of a o inspect mmunity plan was hus, steps

in 2005.

ar tenure.

L project when the and boats rientation g fleet. In her three placed on ly toward efore the

ad to be eanwhile,

he end of nagement

on ukville:

(3)

WP01: Background of Deployment of ICRM Project

47 The timeframe of the implementation of the ICRM projects in Thailand, Malaysia and Cambodia focusing on the introduction of the CBRM concept to the Southeast Asian countries, is as shown in Table 1.

Table 1: Timeframe of ICRM implementation in Southeast Asia (2001-2009)

2001 2002 2003 2004 2005 2006 2007 2008 2009 1

Component 1: Thailand

LBCFM-PD: 1st Phase (JTF - 1) ICRM-PD: 2nd Phase (JTF - 4) 2

Component 1: Malaysia

LBCRM-PL: 1st Phase (JTF - 1) ICRM-PL: 2nd Phase (JTF - 4) 3 Component 2: Cambodia

ICRM-SV (JTF - 4) Component Year No

Regional Seminar on Integrated Coastal Resources Management Approach in Southeast Asia As the first component of the LBCRM/ICRM project, the LBCRM-PD/ICRM-PD in Chumphon Province, Thailand was completed in 2006. The project’s progress in the span of five years and two months had been reported in detail in the respective biannual progress reports. To consolidate the reports, a review of the achievement of LBCRM-PD/ICRM-PD project and its impacts to the target fishing communities was conducted through the Regional Seminar on Integrated Coastal Resources Management in Southeast Asia: Lessons Learned through the Integrated Coastal Resources Management in Pathew District, Chumphon Province (ICRM-PD) in Chumphon, Thailand from 10 to 12 July 2007. The said Regional Seminar aimed to: (1) report on the achievement and outcome of the project during its 5-year implementation and review its progress in line with the original project concept; (2) verify the impacts of the concept to the beneficiaries from the project’s activities in terms of quantity as well as quality considering both facets of community development as well as sustainable fishery resources management; (3) discuss the resultant rationale and implication in the dissemination of the project concept to other SEAFDEC Member Countries under component 2; and (4) identify the necessary follow-up actions to be undertaken by Thailand and other collaborating local agencies.

As a matter of policy in the implementation of the LBCRM/ICRM project, the final evaluation of each sub-project should be done by an external consultant. In the case of the LBCRM-PD/ICRM-PD project, the final project evaluation was conducted by Dr. Somsak Boromthanarat of the Coastal Resources Institute (CORIN) of Prince of Songkhla University, Hat Yai, Songkhla, Thailand. In his report, he commended the project design and objectives as such were able to address the core need of the fishers in the project site. He also noted that the project components, namely: baseline survey, CBRM supporting activities, local business development, human resources development, extension services, and resource enhancement were very relevant and directly contributed to the development of CBRM in the project site.

Moreover, during the Regional Seminar in Chumphon, the participants considered the outcomes of the project to be very substantial and conducive not only for the beneficiaries but also for the agencies which took over the operation of the project after the completion of the direct involvement by SEAFDEC/TD. The proceedings of the first Regional Seminar were compiled and published in September 2007.

Similarly, the second regional seminar on ICRM was organized in October 2008 in order to review the impacts made by the project operation to the fishing communities. Therefore, as a similar exercise the Regional Seminar on Integrated Coastal Resources Management Approach in Southeast Asia:

Review of the Project ICRM-PL was held in Langkawi, Malaysia from 21 to 23 October 2008.

(4)

The Sem the DOF represen Develop Institute (LADA) Moreove fisherme Fishery priority by an ou The field included with DO the follo the Kua pivotal r Sustaina In term occasion managem Malaysi activity shifted t Malaysi even aft Fig. 1. In

Initiatives in project operation

Region Approa minar in Lan F Malaysia an ntatives from pment Autho e of Malaysi ), and Drain er, the most en’s group, i

Resources M beneficiaries utsourced con d trip to insp d in the Sem OF Malaysia ow-up stage ala Teriang role in the pl ability of th s of the su ns that it is v ment regime a. As seen introduced b to the KPSP

a should con er completio nitiatives and

2003 100%

0%

Collab

nal Seminar o ach in Southea ngkawi was a nd SEAFDE m the relate ority of Mala ia (IPM), S nage and Irr important p i.e. the Fishe Management s of this proj nsultant was pect the vario minar in Lang

and SEAFD under the su Fishery Res anning and i e ICRM-PL stainability vital for the e after the in Fig. 1, t by the joint

towards the ntinue its in on of the follo d involvement

2004

SEAFDEC

DOF & Loca borative project

on Integrated ast Asia: Revi attended by t EC/TD under ed agencies

aysia (LKIM tate Fisherie rigation Dep persons who ermen Econo t Community

ject. The rep also present ous activitie gkawi. Altho DEC/TD has b

upervision of sources Man implementati L

of the activ KPSP in par completion the manager

initiatives of end of the fo volvement in ow-up stage.

ts in the proj

2005 2

al Agncies t operation (SEA

Coastal Resou iew of the proj the executive r the collabor

involved in M), Fishery R es Office in partment in attended th omic Group y (KPSP) an port of the fi ted during th s in the proje ough the proj

been termina f the DOF M nagement Co ion of the pro vities of the

rticular, to c of the proj rial responsi f SEAFDEC ollow-up stag

n this activi .

ect operation

2006 2007

Ye AFDEC & DOF)

urces Manage ject ICRM-PL e agencies in rative project n the proje Research Ins n Kedah, La Langkawi (J e Seminar w (KEN) whic nd Women inal evaluatio he Regional S

ect site in K ject operatio ated, the mai Malaysia and ommunity (K oject.

e ICRM-PL, continue this

ect initiative ibility in the C/TD and DO ge. However

ty as the sup n

7 2008

ear

Follow

ement L

nvolved in th t operational ct operation stitute (FRI) angkawi Dev

JPS) also sh were the repr ch was re-org Economic G on of ICRM Seminar.

Kuala Teriang on under the in activities h d other relate

KPSP), whic

it was emp self-regulato es by SEAF e fishery res OF Malaysia

r, it was also pervising an

2009

w-up phase by D

he ICRM-PL l scheme. In n, e.g. the in Penang, F velopment A howed their resentatives ganized later Group (KEW M-PL which w g, Langkawi

collaborativ have been on ed agencies i

ch has expa

phasized on ory fishery r FDEC/TD a sources man a has been ev o agreed that

nd supporting

2010 2011 self-

KPSP DOF

48 L such as addition, Fisheries Fisheries Authority support.

from the r into the W) as the was done was also ve regime ngoing at including anded its

n various resources and DOF nagement

ventually the DOF g agency

1 onward operation

Referensi

Dokumen terkait

As shown in Figure II.A4, except for Thailand under the new exchange rate regime, a shock to the emerging market risk premium does not have significant effects on the domestic interest

With these characteristics, companies are encouraged to make maximum use of external resources through political affiliations to provide certainty of business processes that result in

BOTTOM LONGLINE AND VERTICAL HANDLINE OPERATIONS For the purpose of developing and exploiting demersal fisheries resources in untrawlable fishing grounds the Research Department

Towards this end and in an effort to pave the way for the countries to attain such objective, the ASEAN and SEAFDEC through the 2011 Resolution would want to make sure that the

PREPARATION AND DISTRIBUTION OF THIS DOCUMENT Report of the Second Regional Technical Consultation on Development of the Regional Plan of Action for Managing Fishing Capacity

Activities lined up for 2021—2022 under the project “Regional Collaborative Research and Capacity Building for Monitoring and Reduction of Marine Debris from Fisheries in Southeast