53. (1) Offences. Any person who contravenes or fails to corl1ply with any provision of these Regulations shall be guilty of an offence.

(2) Where any person under the authority of these Regulations directs anything to be done or forbids anything to be done by another person then if that other person fails to do the thing directed to be done or, as the case may be, does the thing forbidden to be done, that other person shall be guilty of an offence against these Regulations.

(3) General Penalty. Any person guilty of an offence against any provision of these Regulations shall be liable to a penalty not exceeding two hundred dollars.

(4) Daily Penalty. Any person who, being convicted of an offence against these Regulations that consists of a contravention or failure to comply of such a nature that it may be committed from day to day, thereafter continues that offence, may be prosecuted from time to time for an offence against these Regulations that consists of the same contravention or failure to comply and is liable to a penalty of ten dollars for each day during which it is continued as from the date on which he was last convicted thereof until the date on which he is convicted or on which the default is rectified, whichever date is the earlier.

104 Regs. 54-56 REGULATIONS PART IX-GENERAL

54. Authority to enter engine room. A person (other than a person directly employed therein) shall not enter any engine room while the machinery is in motion unless authorised by the owner to do so.

55. Size of boilers. In computing the size of a boiler for the purposes of determining the fees payable under these Regulations and for the purposes of determining the required certificate of competency for an operator, the following rules shall be observed:-

(a) "Heating Surface" shall mean that surface of a boiler which has water on one side and heat on the other and includes water tubes but excludes superheater and economiser.

(b) For electrically heated steam generating boilers the heating surface shall be determined by multiplying the electric energy input in kilowatts per hour by O· 08.

56. Fees. ( 1 ) The fees set forth in the First Schedule to these Regulations shall be the fees payable with respect to the purposes and circumstances respectively set forth in such Schedule.

(2) Such prescribed fees shall be paid to the Chief Inspector at his office in Brisbane: Provided that it shall be sufficient compliance with this Regulation if such fees are paid to an inspector at his usual office.

REGULATIONS Scli.i 1'05

THE FIRST SCHEDULE

Substituted by regulations published Industrial Gazette 13 June 1981, pp. 187-92.

FEES 1. FEES TO BE PAID TO THE CmEF INSPECTOR:-

A For the periodical inspection of machinery-

(1) For every single steam boiler which does not exceed 5 square metres of heating surface

For every single steam boiler which-

Exceeds 5 square metres but does not exceed 14 square metres of heating surface

Exceeds 14 square metres but does not exceed 70 square metres of heating surface

Exceeds 70 square metres but does not exceed 140 square metres of heating surface

Exceeds 140 square metres but does not exceed 280 square metres of heating surface

Exceeds 280 square metres but does not exceed 930 square metres of heating surface

Exceeds 930 square metres, the sum of $162.50 plus $17.50 for each 93 square metres of heating surface or part thereof by which the total heating surface exceeds 930 square metres.

$ 26.50 41.00 69.50 105.50 125.50 162.50

For every portable plant where the boiler and engine are combined, the fee for inspection of the boiler shall be fifty per centum (50%) more than for a single boiler of the same dimensions which is not combined with an engine; such fee shall include the inspection fee for the engine of such portable plant and all attendant machinery being driven by such engine:

Provided that in the case of a boiler that is heated electrically the fee payable shall be calculated on the basis that one kilowatt equals 0·08 square metres of heating surface.

For the visit for the purpose of inspecting a boiler which is not ready for inspection on arrival of an Inspector-a fee of one half of the applicable prescribed fee as set out above plus any travelling expenses incurred by the Inspector but in any case the total fee payable shall not exceed $33.00.

(2) For every unfired pressure vessel the capacity of which- Does not exceed 0·14 cubic metres

Exceeds 0·14 cubic metres but does not exceed 0·7 cubic metres Exceeds 0·7 cubic metres but does not exceed 2·8 cubic metres Exceeds 2·8 cubic metres but does not exceed 14 cubic metres Exceeds 14 cubic metres but does not exceed 56 cubic metres Exceeds 56 cubic metres but does not exceed 140 cubic metres Exceeds 140 cubic metres the sum of $72 .50 plus $10.50 for each 140

cubic metres or part thereof by which the vessel exceeds a capacity of 140 cubic metres.

(3) For every 30 metres of pressure pipe line (steam or air) exceeding 75 millimetres diameter ..

(4) For every crane or hoist (other than a mobile crane or mobile excavating machinery)-

Not exceeding 2 tonnes capacity

Exceeding 2 tonnes but not exceeding 5 tonnes Exceeding 5 tonnes but not exceeding 15 tonnes Exceeding 15 tonnes but not exceeding 50 tonnes Exceeding 50 tonnes but not exceeding 100 tonnes

Exceeding 100 tonnes 54068-1

9.50 15.00 17.50 26.50 46.50 72.50

10.50

17.50 33.00 46.50 72.50 89.50 108 50

106 .Sch.1 REGULATIONS

THE FIRST SCHEDULE-continued FEES-continued

(5) For every mobile crane or mobile excavating machinery- Not exceeding 10 tonnes capacity

Exceeding 10 tonnes but not exceeding 50 tonnes Exceeding 50 tonnes but not exceeding 100 tonnes Exceeding 100 tonnes but not exceeding 200 tonnes Exceeding 200 tonnes

(6) For every lift-

Every lift (other than a service lift) up to and including 4 floors Every additional floor above 4 floors up to and including 10 floors Every additional floor above 10 floors __

Every escalator

Every service lift up to and including 6 floors Every service lift over 6 floors

(7) For every steam, gas, air, oil or hydraulic engine used as an initial prime mover the area of cylinder or combined area of cylinders of which-

Does not exceed 0·016 square metres

Exceeds 0·016 square metres but does not exceed 0·032 square metres Exceeds 0·032 square metres but does not exceed 0-064 square metres Exceeds 0·064 square metres but does not exceed 0·128 square metres Exceeds 0·128 square metres but does not exceed O· 32 square metres __

Exceeds 0·32 square metres but does not exceed 0·64 square metres ..

Exceeds 0·64 square metres

(8) For machinery driven by an electric motor or motors or by a turbine or turbines the power or aggregate power of which-

Does not exceed 7-5 kW _.

Exceeds 7·5 kW but does not exceed 15 kW Exceeds 15 kW but does not exceed 30 kW Exceeds 30 kW but does not exceed 75 kW Exceeds 75 kW but does not exceed 750 kW

(Plus $9.25 per 75 kW for every additional 75 kW or part thereof in excess of 75 kW up to 750 kW)

Exceeds 750 kW

(Plus an additional $2.00 per 75 kW for every additional 75 kW or part thereof in excess of 750 kW up to 3 750 kW)

Exceeds 3 750 kW ..

(9) For every tractor, grader, oil locomotive, end loader, ditcher, fork lift, tow motor, road roller or other mobile machinery not elsewhere specified B For the survey of blue prints, designs or drawings in connection with the

construction or alteration of machinery-

(1) For the survey of the design of every boiler which- Does not exceed 20 square metres of heating surface ..

Exceeds 20 square metres but does not exceed 47 square metres Exceeds 47 square metres but does not exceed 140 square metres Exceeds 140 square metres but does not exceed 470 square metres Exceeds 470 square metres but does not exceed 930 square metres ..

Exceeds 930 square metres but does not exceed 3 700 square metres Exceeds 3 700 square metres but does not exceed 9 300 square metres Exceeds 9 300 square metres

$ 26.50 46.50 89.50 108.50 135.00 54.00 5.25 9.25 46.50 17.50 46.50

5.25 9.25 17.50 33.00 41.00 48.50 54.00

10.50 16.00 23.00 46.50 46.50 152.00 244.00 16.00

55.00 81.50 92.00 136.00 180.50 228.00 274.50 329.50

REGULATIONS Sclt.I 107 THE FIRST SmmDULE-continued

FEES-continued

(2) For the survey of the design of every unfired pressure vessel which has a capacity-

(3)-

Not exceeding 0·28 cubic metres

Exceeds 0·28 cubic metres but does not exceed 1·4 cubic metres Exceeds 1·4 cubic metres but does not exceed 2-8 cubic metres Exceeds 2·8 cubic metres but does not exceed 7-0 cubic metres Exceeds 7-0 cubic metres but does not exceed 14·0 cubic metres Exceeds 14·0 cubic metres but does not exceed 21·0 cubic metres Exceeds 21·0 cubic metres but does not exceed 28'0 cubic metres Exceeds 28·0 cubic metres but does not exceed 140 cubic metres Exceeds 140 cubic metres

Provided that when the vessel is a tubular heat exchanger, other than of the U-tube type, a minimum fee of $66.00 shall apply.

(a) For the survey of the design of every crane or hoist (including a mobile crane) which has a lifting capacity which-

Does not exceed 2 tonnes

Exceeds 2 tonnes but does not exceed 5 tonnes Exceeds 5 tonnes but does not exceed 10 tonnes Exceeds 10 tonnes but does not exceed 20 tonnes Exceeds 20 tonnCB but does not exceed 50 tonnes Exceeds 50 tonnes but does not exceed 100 tonnes Exceeds 100 tonnes

For the survey of the design of every overhead travelling crane where the design of the-

(i) runway has not been combined with the submission of the crane a charge of eighty per centum (80%) of the prescribed fee above shall be made; and

(ii) crane bridge has not been combined with the submission of the crane a charge of forty per centum (40%) of the prescribed fee as specified above shall be made.

(b) For the survey of the design of a tower base crane

(c) For the survey of the design of every lifting beam or frame which- Does not exceed 10 tonnes

Exceeds 10 tonnes ..

(d) For the survey of designs of every special attachment for fork lifts, end loaders or back hoes

(4) For the survey of the design of- A passenger lift

A goods lift A service lift An escalator

(5) For the survey of the design of other machinery not included in this section ..

Provided that where the ChiefInspector considers that such design is of an unusual or intricate kind and required additional survey time the fee shall be

16.00 29.50 47.50 71.00 94.50 110.00 118.00 133.50 188.50

39.50 55.00 94.50 110.00 180.50 235.50 329.50

27.50 11.00 22.00 11.00

89.50 89.50 54.00 72.50

37.00 54.00

108 Sch.r REGULATIONS

THE FIRST SCHEDULE-continued FEES-continued

(6) Where the original design of machinery submitted for survey is amended in any material particular requiring a re-survey of the design, are-survey fee not exceeding seventy-five per centum (75 %) of the survey fee may be charged.

C For the initial inspection of the undermentioned classes 0/ machinery, including inspection during construction, installation and testing.

(1) For every steam boiler which-

Does not exceed 20 square metres heating surface

Exceeds 20 square metres heating surface but does not exceed 47 square metres

Exceeds 47 square metres heating surface but does not exceed 140 square metres

Exceeds 140 square metres but does not exceed 470 square metres ..

Exceeds 470 square metres but does not exceed 930 square metres ..

Exceeds 930 square metres but does not exceed 3 700 square metres Exceeds 3 700 square metres but does not exceed 9 300 square metres Exceeds 9 300 square metres

(2) For every unfired pressure vessel which has a capacity- Not exceeding 0·14 cubic metres

Exceeding 0·14 cubic metres but not exceeding 1'4 cubic metres Exceeding 1·4 cubic metres but not exceeding 2·8 cubic metres Exceeding 2·g cubic metres but not exceeding 7·0 cubic metres Exceeding 7·0 cubic metres but not exceeding 14·0 cubic metres Exceed ing 14·0 cubic metres but not exceeding 21·0 cubic metres Exceeding 21·0 cubic metres but not exceeding 28·0 cubic metres Exceeding 28·0 cubic metres but not exceeding 140 cubic metres Exceeding 140 cubic metres

Provided that where more than 10 vessels of the same type and size are initially inspected at the same place and on the same day a twenty- five per centum (25 %) reduction in the appropriate fee may, at the discretion of the Chief Inspector, apply for the inspection of all such vessels in excess of 10.

(3) For every crane or hoist (including a mobile crane or mobile excavating machinery) which has a capacity-

Not exceeding 2 tonnes

Exceeding 2 tonnes but not exceeding 5 tonnes Exceeding 5 tonnes but not exceeding 10 tonnes Exceeding 10 tonnes but not exceeding 20 tonnes Exceeding 20 tonnes but not exceeding 50 tonnes Exceeding 50 tonnes but not exceeding 100 tonnes Exceeding 100 tonnes

$

26.50 72.50 135.00 180.50 229.00 289.50 361.00 450.00

4.75 17.50 46.50 72.50 89.50 108.50 135.00 162.50 197.50

17.50 33.00 46.50 63.00 89.50 108.50 135.00

REGULATIONS Seh.! 109 THE FIRST SCHBDULE-continued

FEES-continued (4) For every lift or escalator-

Every lift (other than a service lift) up to and including 4 floors Every additional floor above 4 floors up to and including 10 floors Every additional floor above 10 floors ..

Every escalator

Every service lift up to and including 6 floors Every service lift over 6 floors

Provided that where any further inspection of a lift, escalator or service lift is required an additional fee equal to twenty-five per centum (25 %) of the applicable fee shall apply in respect of every such further inspection.

(5) For the inspection of any of the above classes of machinery subsequent to major repairs, alteration or erection, the fees shown in (1), (2), (3) and (4) may be charged.

(6) For every lifting beam, frame or special attachment for fork lifts which- Does not exceed 10 tonnes

Exceeds 10 tonnes ..

(7) For inspection and load testing on re-erection of tower cranes (including base or starting legs) having a current Certificate of Inspection which has a capacity-

Not exceeding 5 tonnes safe working load Exceeding 5 tonnes safe working load ..

(8) For every initial inspection of cage or box for the lifting of personneJ on cranes or fork lifts

D-

(a) For the inspection of a report (or copy) prepared by an Inspector in accordance with section 10 (1) of the Act ..

For a copy of, or extract from, a report or copy which is open for inspection under section 10 (1) of the Act

(b) For testing of every pressure gauge and the issuing of a certificate by the testing officer

E For examination for and the grant of Certificates of Competency Examination for-

Engineer's certificate ..

First class engine driver's certificate Second class engineer's certificate ..

Second class engine driver's certificate First class boiler attendant's certificate Second class boiler attendant's certificate ..

Third class boiler attendant's certificate Steam locomotive driver's certificate Oil locomotive driver's certificate ..

First class crane driver's certificate Second class crane driver's certificate

Internal combustion engine driver's certificate

$ 72.50

4.75 9.50 46.50 26.50 46.50

11.00 22.00

22.00 44.00 16.50

11.50 11.50 19.50

20.50 15.00 11.50 9.25 9.25 6.25 4.00 6.25 6.25 8.00 6.25 10.25

110 Sch.I REGULATIONS THE FIRST SCHEDULE-continued

FEES-continued Refrigeration engine driver's certificate Air-conditioning operator's certificate

"A" grade motor mechanic's certificate

" B " grade motor mechanic's certificate Plant operator's certificate ..

Slinger's certificate

Certificate No. I-Manual metal-arc (MMA) welding of carbon steel plate and double butt welded carbon steel pipe

Certificate No. IE-Manual metal-arc (MMA) welding of carbon steel plate and carbon steel pipe over 270 millimetres outside diameter

Certificate No.2-Manual metal-arc (MMA) weJding of carbon steel pipe Certificate No.3-Manual metal-arc (MMA) welding of alloy steel plate

and double butt welded alloy steel pipe

Certificate No. 3E-Manual metal-arc (MMA) welding of alloy steel plate and alloy steel pipe over 270 millimetres outside diameter

Certificate No.4-Manual metal-arc (MMA) welding of alloy steel pipe •.

Certificate No.5-Tungsten inert-gas/manual metal-arc (TIG/MMA) welding of alloy steel pipe ..

Certificate No. 6-0as welding ..

Certificate No. 7-Tungsten inert-gas (TIO) welding ..

Certificate No.8-Metal inert-gas (MIG) welding Certificate No.9-Automatic welding ..

Certificate No. 10-Welding supervisor

Where material for welding certificates is supplied by the division there will be an additional charge of ..

For the granting of any certificate of competency

A copy of any certificate of competepcy other than when an endorsement is required to a certificate which has been plastic laminated

Every subsequent copy of a certificate of competency other than when an endorsement is required to a certificate which has been plastic laminated A certiificate of competency in recognition of other equivalent certificate F For witnessing 0/ each weld procedure or each weld qualification test "

$ 10.25 10.25 10.25 6.25 6.25 4.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 20.00 4.00 6.25 8.00 8.00 5.50

REGULATIONS

THE SECOND SCHEDULE

Form 1 QUEENSLAND

Inspection of Machinery Act 1951-1979 (Regulation 17)

NOTICE BY OWNER OF MACHINERY To The Chief Inspector of Machinery

SIR,

Sch. II, r.1

District:

Registered No.:

Plant No.:

"'I1We hereby give you notice that :~:~re the Owner of at

111

which is Machinery within the provisions of the abovementioned Act, and particulars as to which are furnished hereunder and on the back hereof.

Full name (in block letters):

Address of Owner:

(State if only lessee or mortgagee in possession) Location of Machinery:

Purpose for which used or proposed to be used (to be stated in detail) :

Name and Address of Maker:

Engine No.: Serial No.: M.R.D. No.:

*I1We certify that the particulars hereby given are true and correct in every respect.

Signature of Owner:

Date:

*

Cross out whichever inapplicable.

t Insert type of machinery, i.e. lift, crane, boiler, air receiver, digester, etc.

DETAILS OF MACInNERY

BOILER OR UNFIRED PRESSURE VESSEL: Materials of Construction:

Type of Boiler or Unfired Pressure Vessel:

Age of Boiler or Unfired Pressure Vessel:

Capacity (Heating Surface or cubic metres):

Dimensions:

Working Pressure:

Name and Addr~ss of Maker:

Date of Last Inspection or Test , (State which or if both):

CRANE OR HOIST:

Lifting Capacity:

If Jib Crane-Length of Jib:

Or-

If Traveller-Span:

If Mobile-Make of Prime Monr:

112 Sch. II, f. 2 REGULATIONS

ELECTRIC MOTORS:

Type of Plant driven by motors:

Total kilowatts of motors:

Attach list of machines driven by motors and kilowatts capacity of motors:

OTHER MACHINERY:

Capacity:

Kilowatt:

Other relevant d~tails:

Form 2

QUEENSLAND

Inspection of Machinery Act 1951-<1979 (Regulation 13)

NOTICE UNDER SECTION 22 (1)

Office of the Inspector

, 19

To , of

I have inspected machinery. namely of which you are

*machinery,

the owner, and I am of opinion that the *part of the machinery, namely , is not securely fenced or otherwise sufficiently guarded and is likely to cause loss of life or bodily injury to any person employed or working with respect thereto.

Take notice that you are required within the period of from the date hereof to :~~ffi~f:~tl~eng~ard the said part of the machinery as follows:- t

Inspector.

ENDORSEMENT ON NOTICE

The within notice was given by me to the abovementioned owner

this day of , 19 , at

by (mode of service).

Inspector.

*

Cross out whichever inapplicable.

t Insert particulars of fencing or guarding.

To

REGULATIONS Form 2A

QUEENSLAND

Inspection of Machinery Act 1951-1979 (Regulation 14)

Sch. II, f. 2A

NOTICE UNDER SECTION 24 (MACHINERY) Office of the Inspector

• of

Take notice that I have inspected Machinery, namely

113

, 19 of which you are the owner, and that the machinery part arrangement thereof namely

*. *~ppears to me to be faulty or defective in that

*. *~ppears to me to be so dangerous as to be likely to cause loss of life or bodily injury to any person employed or working with respect thereto.

And that You ARE REQUIRED-

*to wholly desist from working or using such machinery forthwith until the replacements, repairs or alterations set out below have been effected;

*to wholly desist from working or using such machinery after the

day of ,19 ,until the replacements, repairs or alterations set out below have been effected;

*to have the replacements, repairs or alterations set out below effected within days of service of this Notice;

*to produce namely or dangerous directs;

and surrender to me the part of such machinery which appears to me to be faulty, defective for the making of such examinatioBs as the Chief Inspector

*to refrain from selling, hiring, or otherwise disposing of, or parting with the possession of, such machinery until the requirements of this notice have been complied with.

LIST OF REPLACEMENTS, REPAms OR ALTERATIONS-

Inspector.

ENDORSEMENT ON NOTICE

The within notice was given by me to the abovementioned owner this

day of , 19 , at

by (mode of service).

Inspector.

*

Cross out whichever inapplicable.

NOTE-Items struck out to be initialled by Inspector.