83 STORMWATER

Dalam dokumen TASMAN DISTRICT COUNCIL (Halaman 86-93)

83

84

How this activity contributes to the Council’s Community Outcomes

Our levels of service and how we measure progress against them Levels of Service

(We provide)

We will know we are meeting the Level of Service if...

Current Performance

Our stormwater systems do not adversely effect or degrade the receiving environment.

Council has resource consents in place for each of the 15 stormwater UDAs. Resource consents are held in Council’s Confirm database. [Target:

One out of 15 (Richmond)]

We do not currently have the consents in place that are required for our stormwater UDAs. The discharge consent for Richmond is to be applied for by November 2016, with other towns to follow in 2017.

Compliance with resource consents is achieved, as measured by the number of:

 - abatement notices

 - infringement notices

 - enforcement orders, or

 - convictions issued (Mandatory measure 2)

No abatement notices, infringement notices, enforcement orders or convictions were received in relation to

resource consents for stormwater.

We have adequate knowledge of our

The number of Urban Drainage Areas that have

Due to other work priorities we have not been able to meet this target. However, the Catchment Management Plan for

85

Levels of Service (We provide)

We will know we are meeting the Level of Service if...

Current Performance

stormwater systems capacity and usage to facilitate Improvement.

Catchment Management Plans meets the target.

[Target: 1 of 15]

Richmond has begun and is expected to be approved sometime in 2017. As resources allow other catchment management plans will also be developed.

The number of flooding events that occur (per year) is less than the target. As measured through complaints recorded in the Confirm database.

(Mandatory measure 1) [Target: <20]

Our complaints database shows that this target was achieved. Of the total number of flooding events that occurred in the year (11), there were a total of 36 separate locations of flooding reported. Five of the flooding events were from storm events and six of the flooding events were related to the high tide flooding properties where

floodgates did not close properly.

There were some significant rainfall events during the year. The two storms that affected Motueka were both one in 40 year events and caused significant flooding on both occasions.

Significant capital works were successfully completed in the District, including the open channel upgrades for Borck Creek, Poutama Drain and Seaton Valley Stream and the Champion Road culvert. These works provided significant improvement to help prevent flooding in those areas.

Number of habitable floors affected in each flood event for each 1000 properties

connected to the stormwater system is less than the target.

As measured through complaints recorded in the Confirm database.

(Mandatory measure 1) [Target: < 5]

The measure per 1000 properties (of which there is 13,881) was very low at 0.43, well below our target level.

In real terms there were six habitable floors flooded in Tasman District, three of these were house

basements. These were mainly due to two storms in Motueka on 23 to 24 March and 28 May. Both storms were significant with a one in 40 year return period.

Our stormwater activities are managed at a level which satisfies the community.

Percentage of customers satisfied with the stormwater service - as measured through the annual residents’ survey.

[Target: 80%]

In our resident survey 81% of receivers of our service were satisfied, with 16% of unsatisfied. This result is similar to that measured last year (2014/2015: 83% and 15% respectively).

Dissatisfaction by users was generally attributed to localised flooding, inadequate systems, and blocked drains.

See Figure 33 [LTP Figure 22]. Stormwater Services Satisfaction Rate, Page X

Complaints per 1000

connections are less than the target - as recorded through Council's Confirm database.

(Mandatory measure 4) [Target: < 20]

The total number of stormwater complaints recorded in our Confirm database was 36. This equates to 2.6 complaints per 1000 properties (of which there is 13,881) is. This is significantly below our target level of <20.

We have measures in place to respond to and reduce flood damage to property and risk to the

The median response time to attend a flooding event, is less than the target (3 hours) - as recorded through Council’s Confirm database.

This performance target was not measured. The system to record response times for each job was still in a development phase during the year.

86

Levels of Service (We provide)

We will know we are meeting the Level of Service if...

Current Performance

community within stormwater UDAs.

(Mandatory measure 3) [Target: < 3 hours]

Systems are now in place for the contractor to record the time when they arrive on site and when the job is completed.

Figure 34. Comparison of number of performance measures met over three years

The Long Term Plan 2015-2025 introduced 6 new performance measures for the Stormwater Activity Group.

Many of these are new mandatory measures. We also introduced a new measure for consent compliance. The majority of measures have been achieved and satisfaction with stormwater services by residents remains high.

We did not achieve our targets for the number of Catchment Management Plans or number of consents for the 15 Urban Drainage Areas.

[Insert figure 22 from excel data. Now renumbered as 33 in table above]

Major Activities

This group of activities involves ongoing management, maintenance and renewal of Council’s stormwater network, encompassing the provision of stormwater collection, reticulation and discharge systems. The assets used to provide this service include drainage channels, pipelines, tide gates, detention ponds, inlet structures, discharge structures and quality treatment assets.

Project Name

Years 1-3 ($)

Yr 1 2015/2016 Budget ($)

Actual 2015/2016

Pohara main settlement 920,700 920,700 $43,808 was spent in the current financial year. Council is awaiting a modelling report on options. Funds will be carried over to 2016/2017 as part of a report to Council in September.

Lower Borcks Creek Catchment Works - SH6 to outlet including land

3,149,486 1,023,000 Borcks Creek catchment works. $137,215 was spent in the current financial year. Reassessing options as property agreement issues. Funds will be carried over to 2016/2017 as part of a report to Council in

September.

0 1 2 3 4 5 6

2013/14 2014/15 2015/16 2013/14 2014/15 2015/16 2013/14 2014/15 2015/16 2013/14 2014/15 2015/16

Target Fully Achieved

Target Significantly Achieved

Not Achieved Not measured

Stormwater Performance Measures

87

Project Name

Years 1-3 ($)

Yr 1 2015/2016 Budget ($)

Actual 2015/2016

Richmond - Middlebank Drive 1,292,265 0 Installation of stormwater pipe from Gladstone Road to Olympus Way to Middlebank Drive. This project will commence in 2017/2018.

Richmond Central Improvements 7,299,908 332,475 5 year programme of major works in Queen Street, Oxford Street, Beach Road drain, Poutama link and Washbourn Gardens area. 1st stage is Queen St commencing in February 2017. Due to the revised staging of the project works and early underground services investigation an earlier budget spend of $2,088 occurred. This is not expected to lead to an overspend of the total budget available.

$417,319 was spent in the current financial year.

$82,756 was carried over from 2014/15 to the current year.

Richmond - Park Drive 1,111,619 108,620 Increase capacity through Ridings Grove. Duplicate line in walkway reserve and upgrade Hill Street crossing to Q50. No funds were spent in the current financial year. On hold until Richmond modelling completed and upgrade options can be assessed.

Funds will be carried over to 2016/2017 as part of a report to Council in September.

Richmond - Ranzau Road/Paton Road/White Road

860,792 860,792 Upgrade to White Road and Ranzau Road at Paton Road intersection. $47,606 was spent in the current financial year. Assessed improvement requirements in the area and now no house floors appear to be flooding on a regular basis following protection works that have occurred. On hold until Richmond modelling completed.

The Richmond modelling is being funded from this budget. Funds will be carried over to 2016/2017 as part of a report to Council in September.

Secondary flow management initiatives

317,643 51,150 District Wide as derived from the CMPs. No funds were spent in the current financial year. Internal list of upgrades being documented and prioritised to date.

Funds are anticipated to be carried over to 2016/2017.

Richmond Deviation bund drainage

969,199 0 Bird Street and Arbor-Lea works to reduce flood risk.

This project will commence in 2017/2018.

Motueka drainage improvements 48,460 0 Poole, Jocelyn, Wilkie, Fry pipe extension to drain low points. This project will commence in 2017/2018.

88

Comment:

Finance costs

These are under budget as result of favourable interest rates compared with the Annual Plan estimate coupled with an underspend on the capital programme.

Debt

The underspent capital programme meant less debt was raised than planned.

Capital expenditure

The programme of work was not completed as expected. We anticipate a significant amount of the underspend will be carried over to 2016/2017.

2 0 14 / 2 0 15 2 0 14 / 2 0 15 S t o rm wa t e r 2 0 15 / 2 0 16 2 0 15 / 2 0 16 % of

Long Te rm P la n Budge t $ 0 0 0

Ac tua l

$ 0 0 0

Ac tua l

$ 0 0 0

Annua l P la n Budge t $ 0 0 0

Annua l P la n Budge t

SOURCES OF OP ERA TING FUNDING -

- General rates, unifo rm annual general charges, rates penalties - - - 3,057

3,331 Targeted rates 3,905 3,885 101%

-

- Subsidies and grants fo r o perating purpo ses 370 - -

-

42 Fees and charges 15 - -

-

- Internal charges and o verheads reco vered - - -

84

72

Lo cal autho rities fuel tax, fines, infringement fees, and o ther

receipts - - -

3,141

3,445 TOTA L OP ERA TING FUNDING 4,290 3,885 110%

- -

A P P LICA TIONS OF OP ERA TING FUNDING

929

612 P ayments to staff and suppliers 1,077 1,198 90%

807

888 Finance co sts 841 1,027 82%

402

345 Internal charges and o verheads applied 435 424 103%

-

- Other o perating funding applicatio ns - - -

2,138

1,845 TOTA L A P P LICA TIONS OF OP ERA TING FUNDING 2,352 2,649 89%

- 1,003

1,600 SURP LUS (DEFICIT) OF OP ERA TING FUNDING 1,938 1,236 157%

- -

SOURCES OF CA P ITA L FUNDING

-

- Subsidies and grants fo r capital expenditure - - - 422

1,260 Develo pment and financial co ntributio ns 1,077 1,305 83%

3,225

99 Increase (decrease) in debt 178 1,830 10%

-

- Gro ss pro ceeds fro m sale o f assets - - -

-

- Lump sum co ntributio ns - - -

-

- Other dedicated capital funding - - -

3,647

1,359 TOTA L SOURCES OF CA P ITA L FUNDING 1,255 3,135 40%

- -

A P P LICA TIONS OF CA P ITA L FUNDING

-

Capital expenditure

966

279 - to meet additio nal demand 405 1,981 20%

3,919

1,351 - to impro ve the level o f service 1,390 1,932 72%

240

46 - to replace existing assets 692 458 151%

(475)

1,283 Increase (decrease) in reserves 706 - -

-

- Increase (decrease) in investments - - -

4,650

2,959 TOTA L A P P LICA TIONS OF CA P ITA L FUNDING 3,193 4,371 73%

-

(1,003)

(1,600) SURP LUS (DEFICIT) OF CA P ITA L FUNDING (1,938) (1,236) 157%

- -

- FUNDING B A LA NCE - - -

89

Reserve movements increase or decrease

The movement in reserve is a reflection of the underspend in this activity. The amount of surplus in this activity has increased.

90