• Tidak ada hasil yang ditemukan

Decision Support System for Rehabilitation Bond of Mining Area

N/A
N/A
Protected

Academic year: 2017

Membagikan "Decision Support System for Rehabilitation Bond of Mining Area"

Copied!
184
0
0

Teks penuh

(1)

DECISION SUPPORT SYSTEM FOR

REHABILITATION BOND OF MINING AREA

DEDE IDA SUHENDRA

GRADUATE SCHOOL

(2)

STATEMENT

I, Mr. Dede Ida Suhendra, herewith declare the thesis title:

‘Decision Support System for Rehabilitation Bond of Mining Area’

Contains correct results come in from my own work and it has not been published

ever before. All data sources and information have used factual and clear methods

in this research has been examined for its factualness.

Bogor, April 2007

(3)

ABSTRACT

DEDE IDA SUHENDRA (2007). Decision Support System for Rehabilitation Bond of Mining Area. Under the supervision of HARTISARI H. and HASRUL L. AZAHARI.

Mining is an effort to remove in situ minerals resources, which is in exploitation stage that employ surface mining method is critical, yet mostly close to huge spatial opening, therefore suitable planning and operation is required to synchronize both of economical and environmental interests. Due to the prudent principle of the Government on a mining company, by regardless its principal and scale, the company is obliged to insure any spatial opening during their operation period by allocating appropriate fund in a certain Bank, as Reclamation Bond. Determining the Reclamation Bond needs both skill and expertise, otherwise it would consume time, even perfunctorily. Dealing with the necessity of Reclamation Bond assessment tool, this study attempted to develop a decision support system (DSS) approach to support fast and objective problem solution for evading disputability.

The objective of this project is to develop a Mining Rehabilitation Bond System, which can provide the additional tool for the Government as Decision Support System to evaluate any company planning concerning cost estimation either suitable or not to be agreed with, determining adequate amount direct cost and indirect cost and emphasizing mine stakeholder awareness of any decision support related to cost of mining reclamation activity

The Mining Rehabilitation Bond System is designed to support decision making, in order to minimize DSS implementation, data base manipulation through Visual Basic programming language. Beside direct cost analysis and indirect cost analysis, there is also manual analysis to perform additional data for structure demolition calculation and earth moving activities. The main focus of this system design is to estimate the amount of escalation per year that have to meet mining company’s reclamation cost planning.

Based on the result, the combination of DSS Tool and reclamation formula can produce application system for rehabilitation bond. This calculation system is used to evaluate Reclamation Bond for 5 (five) years and annual reclamation cost based on direct and indirect cost of reclamation activity. This application tries to attempt evaluating system of mining company’s reclamation data. The application system has several weaknesses such as haul distance and grade consideration that should be measured manually, need socialization to mining company association and never published yet.

The Mining Rehabilitation Bond System still needs to be tested for knowing its performance including its database system through several data from company (KK, KP and PKP2B) and the calculation of haul distance and grade of equipment needs digital input using spatial approach or digital map digitizer.

(4)

DECISION SUPPORT SYSTEM FOR

REHABILITATION BOND OF MINING AREA

DEDE IDA SUHENDRA

A Thesis submitted for the degree of Master of Science of Bogor Agricultural University

GRADUATE SCHOOL

(5)

Research Title : Decision Support System for Rehabilitation Bond of Mining Area

Student Name : Dede Ida Suhendra

Student ID : G051030071

Study Program : Master of Science in Information Technology for Natural Resources Management

Approved by,

Advisory Board

Dr. Ir. Hartrisari Hardjomidjojo, DEA Dr. Ing. Hasrul L. Azahari, M.Met.E Supervisor Co-Supervisor

Endorsed by,

Program Coordinator Dean of Graduate School

Dr. Ir. Tania June, M.Sc Prof. Dr. Ir. Khairil A. Notodiputro, MS

(6)

CURRICULUM VITAE

Dede Ida Suhendra was born in Bandung, West Java,

Indonesia at December 26, 1957. He received his

undergraduate diploma from Bandung Institute of

Technology (ITB), Faculty of Industrial Technology -

Mining Technique Department majoring Exploration in

1983. He worked for oil and geothermal consultant project as geophysicist in PT

Alico during 1984 to 1986, and has been working for Department of Energy and

Mineral Resources since 1987.

In the year of 2003, Dede Ida Suhendra pursued his post graduate at MIT (Master

of Science in Information Technology) for Natural Resources Management from

Bogor Agricultural University and received his master degree in 2007

respectively. His thesis title was on “Decision Support System for Rehabilitation

(7)

ACKNOWLEDGEMENT

First of all I would like to grateful thanks to ALLAH SWT who The Most

Merciful and Gracious for blazing me, and allowing me to complete my post graduate

study. Furthermore, I realize the completion of this research would not have been

possible if not through the kind assistance and technical support of several individual

and organization.

I am thankful to Dr. Tania June, the Program Coordinator for her support and

for allowing me to use the MIT facilities during my study. I would like to express my

special appreciation to the following for their invaluable contributions at all stages

towards and finishing this thesis, Dr. Hartrisari Hardjomidjojo, my primary supervisor

who offered me not only excellent and patience guidance but also useful ideas; and

Dr. Ing. Hasrul L. Azahari, the co-supervisor for his constructive discussion and

suggestion. I would like to specially thank to my external examiner supervisor,

Dr Gatot Haryo Pramono who spent his time in seminar, gave general assistance and

suggestions. I also wish to thank all members of the staff of the MIT, including

Mr Bambang, Ms Uma and Ms Devy for their help in numerous ways.

I thank the Directorate General of Mineral, Coal and Geothermal, particularly

Ir. Soemarno Witoro S, Msi for allowing me to follow this study and to use technical

data from various mining companies.

Thanks also to my course mates MIT-2003 Generation, especially appreciation

is given to Ir. Andes Jayarsa, MSc and Ir. Iksal Yanuarsyah, MSc for the friendliness,

giving me encouragement and supporting throughout this period.

Finally, my special gratitude is also extended to my lovely mother, my wife

Lilis Mulyatie, my son Ilyasa Haqqani, and my daughters Nursyifaa Rabbani and the

(8)

LIST OF CONTENTS

Page

STATEMENT ... i

ACKNOWLEDGEMENT ... ii

CURRICULUM VITAE ... iii

ABSTRACT ... iv

List of Contents ... vi

List of Figures ... viii

List of Tables ... ix

List of Appendixes ... x

I. INTRODUCTION ... 1

1.1. Background ... 1

1.1.1. Mining Management ... 2

1.1.1.1. Mining Enterprises ... 2

1.1.1.2. Government Functionality ... 3

1.1.1.3. Company Responsibilities ... 4

1.1.2. Mining Method ... 5

1.1.2.1. Surface Mining ... 5

1.1.2.2. Underground Mining ... 7

1.1.2.3. Mining Supporting Facility ... 8

1.1.3. Land Management ... 8

1.1.4. Mining Reclamation Bond ... 10

1.2. Problem Identification ... 11

1.3. Objectives ... 12

II. LITERATURE REVIEW ... 13

2.1. Reclamation Bond Provision ... 13

2.1.1. Direct Cost Component ... 14

2.1.1.1. Mine Facilities Removal ... 14

2.1.1.2. Material handling plan ... 15

2.1.1.3. Re-Vegetation ... 21

2.1.1.4. Other Direct Reclamation Cost ... 21

2.1.2. Indirect Cost Component ... 22

2.1.2.1. Mob-Demob of Heavy Equipments ... 22

2.1.2.2. Reclamation Planning ... 22

2.1.2.3. Administration Cost and Contractor Profit ... 24

2.1.2.4. Management Cost ... 25

2.1.3. Determining the Total Performance Bond Amount ... 26

2.2. Decision Support System ... 26

2.2.1. Data Management ... 28

2.2.2. Model Management ... 28

2.2.3. Knowledge Management ... 28

(9)

III. METHODOLOGY ... 29

3.1. Time and Location Selection ... 29

3.2. Material and Tool ... 30

3.2.1. Hardware and Software Required ... 30

3.2.2. Data Requirement ... 30

3.3. Method ... 32

3.3.1. General Concept ... 32

3.3.2. Legal Aspect ... 33

3.3.3. Decision Support System (DSS) Analysis ... 33

3.3.3.1. Conceptual Process ... 33

3.3.3.2. User Need Analysis ... 34

3.3.3.3. DSS Construction ... 35

IV. RESULT AND DISCUSSION ... 37

4.1. System Analysis ... 37

4.1.1. Database Design ... 37

4.1.1.1. Process Modeling ... 37

4.1.1.2. Conceptual Model ... 38

4.1.1.3. Logical Model ... 40

4.1.1.4. Physical Model ... 41

4.1.2. User Interface Design ... 42

4.2. System Implementation ... 43

4.2.1. DSS Tool Application ... 43

4.2.2. DSS Tool Analysis ... 52

V. CONCLUSION AND RECOMMENDATION ... 58

5.1. Conclusion ... 58

5.2. Recommendation ... 59

REFERENCES ... 60

(10)

LIST OF FIGURES

Page

Figure 1.1 Land management principle of back filling of a coal surface mining method (Adopted from Skelly and Loy, 1975) ...

6

Figure 1.2 The underground mining method profile of an ore mining (Adopted from Microsoft ® Encarta 2005) ...

7

Figure 1.3 The Lay Out of a mining facility to support mining operation (Adopted from http://www.nrcan.gc.ca/mms/mining/) ...

8

Figure 1.4 The land management mechanism of a back filling surface mining method (Adopted from Skelly and Loy, 1975) ...

9

Figure 2.1 The relationship of reclamation planning cost and Direct Cost

23

Figure 2.2 The relationship of overhead and contractor profit

and Direct Cost ... 24

Figure 2.3 The relationship of reclamation management cost

and Direct Cost ... 25

Figure 2.4 The conceptual model of a DSS, showing four main software components facilitated by other parts of the system (Adapted from Turban, 2003) ...

27

Figure 3.1 The Mining Company PT Newmont Nusa Tenggara

Location Map ... 29

Figure 3.2 The general concept flowchart Rehabilitation mechanism ... 32

Figure 3.3 Conceptual of Input-Output Process in Reclamation Bond Determination ... 34 Figure 3.4 Diagram of User Needs Analysis 35

Figure 3.5 Flowchart of DSS Construction ... 35

Figure 4.1 Rehabilitation Bond Context Diagram ... 37

Figure 4.2 Rehabilitation Bond DFD Level 1 ... 38

Figure 4.3 Rehabilitation Bond ERD ... 39

Figure 4.4 Rehabilitation Bond ‘user login’ application ... 44

Figure 4.5 Rehabilitation Bond ‘main form’ application ... 44

Figure 4.6 Rehabilitation Bond ‘main form’ application ... 45

Figure 4.7 Mine facilities removal cost form ... 46

Figure 4.8 Material Handling Plan form ... 46

Figure 4.9 Additional Equipment Activity form ... 47

Figure 4.10 Revegetation Cost form ... 47

Figure 4.11 Indirect Cost form ... 48

Figure 4.12 Total Reclamation Cost form ... 49

Figure 4.13 Material Handling Recapitulation form ... 49

Figure 4.14 Reclamation Bond Calculation form ... 50

Figure 4.15 Financial Compulsory form ... 50

Figure 4.16 Equipment and Labour Cost form ... 51

Figure 4.17 Cost component form ... 52

(11)

DECISION SUPPORT SYSTEM FOR

REHABILITATION BOND OF MINING AREA

DEDE IDA SUHENDRA

GRADUATE SCHOOL

(12)

STATEMENT

I, Mr. Dede Ida Suhendra, herewith declare the thesis title:

‘Decision Support System for Rehabilitation Bond of Mining Area’

Contains correct results come in from my own work and it has not been published

ever before. All data sources and information have used factual and clear methods

in this research has been examined for its factualness.

Bogor, April 2007

(13)

ABSTRACT

DEDE IDA SUHENDRA (2007). Decision Support System for Rehabilitation Bond of Mining Area. Under the supervision of HARTISARI H. and HASRUL L. AZAHARI.

Mining is an effort to remove in situ minerals resources, which is in exploitation stage that employ surface mining method is critical, yet mostly close to huge spatial opening, therefore suitable planning and operation is required to synchronize both of economical and environmental interests. Due to the prudent principle of the Government on a mining company, by regardless its principal and scale, the company is obliged to insure any spatial opening during their operation period by allocating appropriate fund in a certain Bank, as Reclamation Bond. Determining the Reclamation Bond needs both skill and expertise, otherwise it would consume time, even perfunctorily. Dealing with the necessity of Reclamation Bond assessment tool, this study attempted to develop a decision support system (DSS) approach to support fast and objective problem solution for evading disputability.

The objective of this project is to develop a Mining Rehabilitation Bond System, which can provide the additional tool for the Government as Decision Support System to evaluate any company planning concerning cost estimation either suitable or not to be agreed with, determining adequate amount direct cost and indirect cost and emphasizing mine stakeholder awareness of any decision support related to cost of mining reclamation activity

The Mining Rehabilitation Bond System is designed to support decision making, in order to minimize DSS implementation, data base manipulation through Visual Basic programming language. Beside direct cost analysis and indirect cost analysis, there is also manual analysis to perform additional data for structure demolition calculation and earth moving activities. The main focus of this system design is to estimate the amount of escalation per year that have to meet mining company’s reclamation cost planning.

Based on the result, the combination of DSS Tool and reclamation formula can produce application system for rehabilitation bond. This calculation system is used to evaluate Reclamation Bond for 5 (five) years and annual reclamation cost based on direct and indirect cost of reclamation activity. This application tries to attempt evaluating system of mining company’s reclamation data. The application system has several weaknesses such as haul distance and grade consideration that should be measured manually, need socialization to mining company association and never published yet.

The Mining Rehabilitation Bond System still needs to be tested for knowing its performance including its database system through several data from company (KK, KP and PKP2B) and the calculation of haul distance and grade of equipment needs digital input using spatial approach or digital map digitizer.

(14)

DECISION SUPPORT SYSTEM FOR

REHABILITATION BOND OF MINING AREA

DEDE IDA SUHENDRA

A Thesis submitted for the degree of Master of Science of Bogor Agricultural University

GRADUATE SCHOOL

(15)

Research Title : Decision Support System for Rehabilitation Bond of Mining Area

Student Name : Dede Ida Suhendra

Student ID : G051030071

Study Program : Master of Science in Information Technology for Natural Resources Management

Approved by,

Advisory Board

Dr. Ir. Hartrisari Hardjomidjojo, DEA Dr. Ing. Hasrul L. Azahari, M.Met.E Supervisor Co-Supervisor

Endorsed by,

Program Coordinator Dean of Graduate School

Dr. Ir. Tania June, M.Sc Prof. Dr. Ir. Khairil A. Notodiputro, MS

(16)

CURRICULUM VITAE

Dede Ida Suhendra was born in Bandung, West Java,

Indonesia at December 26, 1957. He received his

undergraduate diploma from Bandung Institute of

Technology (ITB), Faculty of Industrial Technology -

Mining Technique Department majoring Exploration in

1983. He worked for oil and geothermal consultant project as geophysicist in PT

Alico during 1984 to 1986, and has been working for Department of Energy and

Mineral Resources since 1987.

In the year of 2003, Dede Ida Suhendra pursued his post graduate at MIT (Master

of Science in Information Technology) for Natural Resources Management from

Bogor Agricultural University and received his master degree in 2007

respectively. His thesis title was on “Decision Support System for Rehabilitation

(17)

ACKNOWLEDGEMENT

First of all I would like to grateful thanks to ALLAH SWT who The Most

Merciful and Gracious for blazing me, and allowing me to complete my post graduate

study. Furthermore, I realize the completion of this research would not have been

possible if not through the kind assistance and technical support of several individual

and organization.

I am thankful to Dr. Tania June, the Program Coordinator for her support and

for allowing me to use the MIT facilities during my study. I would like to express my

special appreciation to the following for their invaluable contributions at all stages

towards and finishing this thesis, Dr. Hartrisari Hardjomidjojo, my primary supervisor

who offered me not only excellent and patience guidance but also useful ideas; and

Dr. Ing. Hasrul L. Azahari, the co-supervisor for his constructive discussion and

suggestion. I would like to specially thank to my external examiner supervisor,

Dr Gatot Haryo Pramono who spent his time in seminar, gave general assistance and

suggestions. I also wish to thank all members of the staff of the MIT, including

Mr Bambang, Ms Uma and Ms Devy for their help in numerous ways.

I thank the Directorate General of Mineral, Coal and Geothermal, particularly

Ir. Soemarno Witoro S, Msi for allowing me to follow this study and to use technical

data from various mining companies.

Thanks also to my course mates MIT-2003 Generation, especially appreciation

is given to Ir. Andes Jayarsa, MSc and Ir. Iksal Yanuarsyah, MSc for the friendliness,

giving me encouragement and supporting throughout this period.

Finally, my special gratitude is also extended to my lovely mother, my wife

Lilis Mulyatie, my son Ilyasa Haqqani, and my daughters Nursyifaa Rabbani and the

(18)

LIST OF CONTENTS

Page

STATEMENT ... i

ACKNOWLEDGEMENT ... ii

CURRICULUM VITAE ... iii

ABSTRACT ... iv

List of Contents ... vi

List of Figures ... viii

List of Tables ... ix

List of Appendixes ... x

I. INTRODUCTION ... 1

1.1. Background ... 1

1.1.1. Mining Management ... 2

1.1.1.1. Mining Enterprises ... 2

1.1.1.2. Government Functionality ... 3

1.1.1.3. Company Responsibilities ... 4

1.1.2. Mining Method ... 5

1.1.2.1. Surface Mining ... 5

1.1.2.2. Underground Mining ... 7

1.1.2.3. Mining Supporting Facility ... 8

1.1.3. Land Management ... 8

1.1.4. Mining Reclamation Bond ... 10

1.2. Problem Identification ... 11

1.3. Objectives ... 12

II. LITERATURE REVIEW ... 13

2.1. Reclamation Bond Provision ... 13

2.1.1. Direct Cost Component ... 14

2.1.1.1. Mine Facilities Removal ... 14

2.1.1.2. Material handling plan ... 15

2.1.1.3. Re-Vegetation ... 21

2.1.1.4. Other Direct Reclamation Cost ... 21

2.1.2. Indirect Cost Component ... 22

2.1.2.1. Mob-Demob of Heavy Equipments ... 22

2.1.2.2. Reclamation Planning ... 22

2.1.2.3. Administration Cost and Contractor Profit ... 24

2.1.2.4. Management Cost ... 25

2.1.3. Determining the Total Performance Bond Amount ... 26

2.2. Decision Support System ... 26

2.2.1. Data Management ... 28

2.2.2. Model Management ... 28

2.2.3. Knowledge Management ... 28

(19)

III. METHODOLOGY ... 29

3.1. Time and Location Selection ... 29

3.2. Material and Tool ... 30

3.2.1. Hardware and Software Required ... 30

3.2.2. Data Requirement ... 30

3.3. Method ... 32

3.3.1. General Concept ... 32

3.3.2. Legal Aspect ... 33

3.3.3. Decision Support System (DSS) Analysis ... 33

3.3.3.1. Conceptual Process ... 33

3.3.3.2. User Need Analysis ... 34

3.3.3.3. DSS Construction ... 35

IV. RESULT AND DISCUSSION ... 37

4.1. System Analysis ... 37

4.1.1. Database Design ... 37

4.1.1.1. Process Modeling ... 37

4.1.1.2. Conceptual Model ... 38

4.1.1.3. Logical Model ... 40

4.1.1.4. Physical Model ... 41

4.1.2. User Interface Design ... 42

4.2. System Implementation ... 43

4.2.1. DSS Tool Application ... 43

4.2.2. DSS Tool Analysis ... 52

V. CONCLUSION AND RECOMMENDATION ... 58

5.1. Conclusion ... 58

5.2. Recommendation ... 59

REFERENCES ... 60

(20)

LIST OF FIGURES

Page

Figure 1.1 Land management principle of back filling of a coal surface mining method (Adopted from Skelly and Loy, 1975) ...

6

Figure 1.2 The underground mining method profile of an ore mining (Adopted from Microsoft ® Encarta 2005) ...

7

Figure 1.3 The Lay Out of a mining facility to support mining operation (Adopted from http://www.nrcan.gc.ca/mms/mining/) ...

8

Figure 1.4 The land management mechanism of a back filling surface mining method (Adopted from Skelly and Loy, 1975) ...

9

Figure 2.1 The relationship of reclamation planning cost and Direct Cost

23

Figure 2.2 The relationship of overhead and contractor profit

and Direct Cost ... 24

Figure 2.3 The relationship of reclamation management cost

and Direct Cost ... 25

Figure 2.4 The conceptual model of a DSS, showing four main software components facilitated by other parts of the system (Adapted from Turban, 2003) ...

27

Figure 3.1 The Mining Company PT Newmont Nusa Tenggara

Location Map ... 29

Figure 3.2 The general concept flowchart Rehabilitation mechanism ... 32

Figure 3.3 Conceptual of Input-Output Process in Reclamation Bond Determination ... 34 Figure 3.4 Diagram of User Needs Analysis 35

Figure 3.5 Flowchart of DSS Construction ... 35

Figure 4.1 Rehabilitation Bond Context Diagram ... 37

Figure 4.2 Rehabilitation Bond DFD Level 1 ... 38

Figure 4.3 Rehabilitation Bond ERD ... 39

Figure 4.4 Rehabilitation Bond ‘user login’ application ... 44

Figure 4.5 Rehabilitation Bond ‘main form’ application ... 44

Figure 4.6 Rehabilitation Bond ‘main form’ application ... 45

Figure 4.7 Mine facilities removal cost form ... 46

Figure 4.8 Material Handling Plan form ... 46

Figure 4.9 Additional Equipment Activity form ... 47

Figure 4.10 Revegetation Cost form ... 47

Figure 4.11 Indirect Cost form ... 48

Figure 4.12 Total Reclamation Cost form ... 49

Figure 4.13 Material Handling Recapitulation form ... 49

Figure 4.14 Reclamation Bond Calculation form ... 50

Figure 4.15 Financial Compulsory form ... 50

Figure 4.16 Equipment and Labour Cost form ... 51

Figure 4.17 Cost component form ... 52

(21)

LIST OF TABLES

Page

Table 2.1 The commonly material used and the removal cost 14 Table 2.2 Relevant building and specific construction in a mining

operation (Means, 2000 ... 14

Table 2.3 Initial and final swells of selected material ... 16

Table 2.4 Heavy Duty / Construction Equipments Rental Prices (APKASI, October 2005) ... 20

Table 2.5 The Average of Heavy Equipment’s Lubricant and Fuel Consumptions ... 21

Table 4.1 Rehabilitation Bond logical data model ... 40

Table 4.2 Rehabilitation Bond physical design ... 41

Table 4.3 List of PT.NNT’s mine facilities removal cost ... 53

Table 4.4 List of PT.NNT’s Reclamation Bond ... 56

(22)

LIST OF APPENDIXES

Page

(23)

I. INTRODUCTION

1.1. Background

The mandate of Act Number 11 Year 1967 concerning The Basic

Provisions of Mining, on article (1) asserted that:” All minerals found within the

Indonesian mining jurisdiction in the form of natural deposits as blessing of God

Almighty are national wealth of the Indonesian people and shall, therefore, be

controlled and utilized by the State for the maximum welfare of the people”.

Mining is an effort to remove in situ minerals resources, which is

processed and refined into more valuable matters to become raw material for

downstream industries. The operation could be conducted by surface and/or

under-ground mining methods depend on natural deposit character by through

several stages of mining operation. The stages consist of general survey,

exploration, exploitation, processing and refining, transportation and sales; which

can be operated either by a Government Agency, a state own company, a

cooperative, a private body, or by way of people mining, through technically,

economically and environmentally feasibility studies with respect to prevailing

regulation. This activity is very potential to change the surrounding of

environmental working area significantly, either positive or negative impacts.

Positively, it could play a role as an agent of economical development. Contrary,

it could be also as the source of environment deterioration, whether physical,

chemical, biological, or social-economically if it is not managed appropriately.

Improving the positive impact and to maintain the environment, a mining

company is compulsory to conduct environmental management and

environmental monitoring during the operation.

The mining operation, especially in exploitation stage that employ surface

mining method is critical, yet mostly close to huge spatial opening, therefore

suitable planning and operation is required to synchronize both of economical and

environmental interests. Surface method has several subsequent steps, which are

land clearing, topsoil removal, overburden/waste rock removal, minerals deposits

excavation, and back filling. Those successive processes are driven eventually in

(24)

previously usage or change to another more benefit one. Some diverting usages

mined out area are used as water reservoir, tourism, fish cultivation, and sport

facility. Otherwise, if there is not any benefit of mined out area, except

deterioration for the environment, no mining activity might be much better.

1.1.1. Mining Management

In principle, since 1999 in line with regional autonomy policy, almost all

of mining management has decentralized, except for the existing contract in

respect of Foreign Capital Investment, which is still under Central Government

authority until the licenses is finished.

1.1.1.1. Mining Enterprises

All investors are able to invest in mining sector, regardless nationality and

company scale; could be in term of multinational company, State Own Company,

private company, cooperation, or local community based. Due to this scheme,

which refers to the prevailing regulation, mining enterprises and the type of

license are classified as follow.

• Mining Authorization holders (Kuasa Pertambangan/KP) managed by National Agency, State Own Company, national company, and

cooperation

• Contract of Work for mineral mining (Kontrak Karya/KK) and Work Agreement for Coal Mining Enterprises (Perjanjian Karya Pengusahaan

Pertambangan Batubara/PKP2B), managed by multinational companies in

term of Foreign Capital Investment Company (PMA) as contractor

• People based Mining, managed by local community on certain Area for People Mining, where determined by Local Government

The mining license is given in respect to mining activities stages

successively in a definite period of time which each can be extended if necessary.

The following are the stages with each duration permit.

(25)

• exploration, mainly for 3 years period and can be extended twice for 1 year each

• exploitation, processing and refining, transportation and sales, for maximum 30 years period and can be extended twice for 10 years each

This condition is omitted for the company in term of PMA, the license is

given once as a package.

1.1.1.2. Government Functionality;

Actually, the Government functionality based on the prevailing policy is

as follows:

a. Central Government

- Proposing, determining, and updating national mineral management

policies, guideline, standardization, norms, criteria, and procedures;

- Socialization and technical guidance for environment, safety, added

value and community development aspects, whether for local

government, community and company;

- Supervising and evaluating local government official performances in

conducting mining services both deskwork and fieldwork,

- Managing overlying license area between provinces and exceeding 12

miles of offshore area.

- Monitoring and evaluating contractors performance in conducting their

becoming obligations comprises; environmental, safety, added value,

community development, taxes and financial aspects, both deskwork

and fieldwork,

b. Local Government

- Managing coal and minerals resources under their authorities’ area.

- Monitoring and evaluating company performance in conducting their

becoming obligations comprises; environmental, safety, added value,

community development, taxes and financial aspects, both deskwork

and fieldwork,

- Socialization and technical guidance of each aspects whether to local

(26)

- Supervising the provincial and regional official in conducting mining

services related to Regional Autonomy.

1.1.1.3. Company Responsibilities

a. Implementing Good Mining Practices

Good Mining Practices is conducted by implementing appropriate

method and compliance of any related prevailing regulations to create

accountable mining,

- Applying an effective and efficient mining method

- Environmental eligibility, based on Environmental Impact Assessment

(EIM) to keep the environment components as ambient condition and

to meet environmental policies.

- Added Value eligibility, concerning the company effort to improve

their yield and condition such as conservation, quality, human aspect,

community development and multiplying effect.

- Safety and health occupancy of the employee, to avoid mining

accident.

- Standardization of any aspect of mining activities, whether operational

procedure, equipment appropriateness, and official or operator

competency; by referring to the national or international standards.

- Economics eligibility to meet any finance and taxes obligations

b. Fulfilling Taxes and Other Financial Obligation - Deadrent in respect of the mining area

- Royalties in respect of the company’s production

- Corporate Income Tax in respect of income received or accrued by the

contractor

- Personal Income Tax

- Income Tax under Article 23 and Article 26 of Income Tax Law Year

1994

- Value Added Tax and Sales Tax of Luxury Goods

- Stamp Duty on Documents

- Import Duty on goods imported into Indonesia

(27)

• The area of the mining area; and

• The utilization of land and building in the area where the contractor constructs facilities for its mining operations.

- Levies, taxes, charges and duties imposed by Regional Governments in

Indonesia, which have been approved by the Central Government.

- General administrative fees and charges for facilities or services

rendered and particular rights granted by the Government to the extent

that such fees and charges have been approved by the Central

Government

- Duties on the transfer of ownership for motor vehicles and ships or sea

transportation.

- Capital goods and materials, imported by private Contractor Company

within the context of the Agreement, are exempted from import Duty,

Import Levies and Duty of Ownership Transfer according to the

prevailing legislative rules.

- Allocating appropriate amount of fund in certain Bank, which have

been approved by the Government as Mining Reclamation Bond, since

it’s commencing up to decommissioning.

1.1.2. Mining Method

In principle, mining is classified into two main categories namely surface

mining and underground mining. Implementations of these methods rely on the

occurrences of mineral deposit, which are characteristics, kind of mineral, deposit

type, position, spreading, and host-rock/ over-burden.

1.1.2.1. Surface Mining

Surface mining is excavation of mineral deposit at or near the surface,

where the whole work is open to the atmosphere. The name is also designated by

a modifying word or phrases depending on the mineral deposit types such as the

following.

a. Open-pit/open-cut/open-cast/open-mine is open surface for removing

(28)

South-East Sulawesi Province, Bintan alluminium mine at Kepulauan Riau

Province, Eastberg cupper mine at Papua Province.

b. Quarry is excavation for economic-minerals/industrial-minerals; for

example Tulungagung marble mine at East Java Province, Padalarang

limestone mine at West Java Province, Karimun granite mine at

Kepulauan Riau Province.

c. Strip mine is excavation for flat or slightly oblique of coal bed/seam/layer;

for example Ombilin coal mine at West Sumatera, Tanjungenim coal mine

at South Sumatera, Sangata coal mine at East Kalimantan,

d. Alluvial/placer mine is excavation for alluvium deposit of sand, gravel, or

talus from which some valuable mineral is extracted; for example Logas

gold mine at Riau Propince, Cilacap iron mine at Central Java Province,

Martapura diamond mine at South Kalimantan Province.

e. Hydraulic mine, a placer mine worked by means of a stream of water

directed against a bank of sand, gravel, or talus; soft rock similarly

worked; for example almost all of ore tin mine on the islands of

Bangka-Belitung Province.

(29)

1.1.2.2. Underground Mining

Underground mining is also known as a “deep” mine; it’s usually located

several hundred meters beneath the earth’s surface by means of the certain

opening hole to connect to the surface. The opening hole could be employed

either for main entrance, main haulage, or supporting facility way, those provide

work for material and labor transportation, ventilation, drainage.

a. Shafts, a vertical or incline opening hole.

b. Tunnel, a horizontal or gentle inclining hole through in both sides of

foothill.

c. Drift a horizontal or slight inclining hole at or parallel to adjacent strike of

the mineral/coal deposit. Strike is the longest part of the deposit.

d. Adit, a horizontal or gentle inclining hole through the foothill in one side,

it’s a dead end tunnel.

The broken mineral or coal as product material is removed mechanically

and transferred by shuttle car or conveyor to the surface.

(30)

1.1.2.3. Mining Supporting Facility

Both of surface and underground mining methods operation are supported

by several interrelation facilities, such as; processing plant, official buildings,

warehouse, workshop, stock pile, settling pond, tailing pond, polishing pond,

dumping area, roads, emplacements, erosion controls, dock, jetty, conveyor,

railway-tract, water channel, bridges, electricity transmission, dormitory, fencing

[image:30.595.138.487.267.499.2]

and other related various ones.

Figure 1.3 The Lay Out of a mining facility to support mining operation (Adopted from http://www.nrcan.gc.ca/mms/mining/)

1.1.3. Land Management

Based on the character where the whole excavation is opened, surface

mining is more extensive on spatial opening than underground mining, and tends

to evoke morphological change. The surface mining is critical, therefore suitable

planning and operation to synchronize both of environmental and economical

interests on land usage in exploitation is required. Exploitation is one of mining

operation stages, which mostly related to spatial opening, since the purpose of

(31)

Surface mining method exploitation stage occupies several subsequent

steps as follows:

a. Land clearing, it’s an attempt to eliminate working area of vegetation

coverage.

b. Topsoil removal, to strip an upper part of earth layer called humus, then be

loaded, hauled and stocked on certain area or be spread directly to a

reclamation area, as a growth medium to accelerate re-vegetation.

c. Overburden/waste rock removal is to strip or to dig the covered rock layer

or host rock of valuable minerals, then be loaded and hauled to be dumped

either on permanently or provisional dumping areas, or even be dumped

directly to a mined out area as reclamation filling material.

d. Minerals deposit excavation, then be loaded and hauled to processing plant

stockpile, becoming feed for processing and or refining/purification

process. The mineral deposit, which at least one of its metal content could

be extracted economically, is also called ore.

e. Back filling, it’s the reclamation process, especially conducted in coal

mining by returning the over burden or the waste rock, whether derive

from the dumping area or directly from the active area to the void mined

[image:31.595.120.503.499.702.2]

area, then being re-contoured, covered by humus, and re-vegetation.

(32)

1.1.4. Mining Reclamation Bond

Due to the prudent principle of the Government on a mining company, by

regardless its principal and scale, the company is obliged to insure any spatial

opening during their operation period by allocating appropriate fund in a certain

Bank, as Reclamation Bond. Every mining company is compulsory to reclaim

their mined area during operation and it will have had to finish before

decommissioning. The reclamation should be agreed by Local Regional

Government, whether it is fit with existing General Planning of Regional

Land-use (RUTRD) or diverting to another more benefit one. The bond should be an

adequate amount; therefore on default condition, it would be sufficient for any

third party to do so. This is determined based on the Government regulation,

which has been stipulated by Directorate General of Geological and Mineral

Resources Decree (DGMR) - Department of Energy and Mineral Resources

(DEMR) No. 336.K/271/DDJP/1996 concerning Reclamation Bond.

The Reclamation Bond mechanism is proposed by the company to be

consulted with the government in order to achieve an agreement. The Reclamation

Bond that has been agreed then being saved by the company in a certain Bank on

behalf of Head of Regional Government, prior DGMR representing Minister of

DEMR. The company could withdraw the bond when any requirements are

satisfied, otherwise as default condition the Government will conduct an action to

determine a third party to do so. The amount of bond is based on annual company

planning pertain mined area reclamation for every five years period, which consist

of direct and indirect cost. These costs are allocated for appropriate mined and

disturbed area management, mobilizing material sources, procurement vegetation

types, engineering method and equipment. Concerning spatial management

related to engineering method and equipment, the fund determination relies on

equipments and employment cost, which has unique characteristics such as

bulldozer, loader, dump truck, excavator, grader, etc. These could be considered

as effective and efficient whether single or combination operational. Determining

the Reclamation Bond needs both skill and expertise, otherwise it would consume

(33)

Due to Regional Autonomy policy, since year 1999, the actual mineral

resource management is belonging to the regional authority. However, in

transition period, these would raise some technical problem, particularly in

expertise-required aspects in determining the Reclamation Bond. The Central

Government realizes that there is a need to provide a supporting tool to accelerate

knowledge transformation and to improve the capability of Regional Government

human resources. This tool whether in term of a guideline or an application

program insists to be developed for synchronizing the mining management

policies between Central and Regional Governments.

Dealing with the necessity of Reclamation Bond assessment tool, this

study attempted to develop a decision supporting system (DSS) approach to

support fast and objective problem solution for evading disputability, namely

Mining Rehabilitation Bond System (MR BoS). This is an interactive, flexible,

and adaptable computerized based information system, which re-useable and be

replicable tool by using model and knowledge for solving comparable projects

and replicated for concerned users. The components of Mining Rehabilitation

Bond System, whether variable, parameter and criterion are input into the system,

to be processed within available formula eventually resulted an adequate amount

of fund and rendering interrelated maps. In principle this yield will have been a

main consideration reference for the Reclamation Bond decision maker.

1.2. Problem Identification

Reclamation Bond is crucial policy in mining industry, which needs

prudential and peer principal of both company and government as this decisive to

drive the post mining environment condition. It has to be proposed and allocated

by a company before conducting any production activity, after through evaluation

by the government. Mining is an investment, which limited by time and

production frameworks. Therefore if this were constraint, either would delay to

inflict financial loss of company operations or be determined perfunctorily, which

would be flaw mining environmental image.

In this case both skill and expertise of government officials are required,

(34)

management planning, and cost estimation. The mining principle is also involved

in form of land management, which mostly employs mechanical earth moving as

well. Environmental management planning is a part of Environmental Impact

Assessment, which performs the steps of mined out area management fit with post

mining area usage. The cost estimation is based on any economical calculation in

conducting both land and environmental managements technically in effective and

efficient manners.

Regional Autonomy provision requires appropriate official capacity

building, related to their authority and responsibility. Consuming time and costly

are common obstacles of Regional Government in improving their official

capacity. Based on this reason, some of them might release a contradictive

Reclamation Bond provision according to their perception eventually to increase

regional income. Therefore, it is necessary to develop an integrated and

user-friendly tool to determine Reclamation Bond.

1.3. Objectives

The main objective of this project is to develop a Mining Rehabilitation

Bond System, with specific purposes are:

1). To provide the additional tool for the Government as Decision Support

System to evaluate any company planning concerning cost estimation in accordance with spatial management and material removal through any

equipment employment, ether suitable or not to be agreed with.

2). Determining adequate amount of fund, which has to be saved by a mining

company in certain Bank as Reclamation Bond, which classified into;

- Direct cost; mine facilities removal, land structuring, re-vegetation,

erosion control, acid mine drainage mitigation; and

- Indirect cost; mobilization and demobilization of heavy equipments,

establish reclamation planning, administration and contractor

(35)

II. LITERATURE REVIEW

Rehabilitation bonds and bank guarantees are broadly accepted as

instruments available to governments to ensure completion of rehabilitation of

mined areas. Bond and guarantees are seen to provide a financial incentive for the

proper completion of rehabilitation work and to ensure that the cost of

rehabilitation will be met by the miner rather than through public funding (McGill

and Fox, 1998).

Several terms are commonly used to express this bond and guarantees

including rehabilitation guarantee, rehabilitation bond, reclamation bond,

performance bond etc. In this case, the differences between rehabilitation bond

and reclamation bond merely by the author to distinguish between the name of

application and the Government Provisions which has legal aspect. The Mining

Rehabilitation Bond System is designed to support decision making of

Reclamation Bond.

2.1. Reclamation Bond Provision

According to Director General of Geological and Mineral Resources

Decree number: 336.K/271/DDJP/1996 concerning Reclamation Bond, asserted;

“Reclamation Bond is a definite fund, which is provided by a mining company as

a guarantee in conducting reclamation on mined area”, though “reclamation is an

effort to restructure and improve condition upon a disturb land that is impacted by

mining operation to fit either with previous or divert land use to be more useful

one”, and “the adequate amount of bond is based on annual company planning

pertain mined area reclamation for every five years period, with the premise

would be conducted by the third party”.

Realization of Reclamation Bond is based on the “Guideline of

Established Annual Planning of Environmental Management regarding

Determining of Reclamation Bond (DEMR, 1996)”. The components of

Reclamation Bond could be classified into two main components those comprise

of direct and indirect costs regarding establishment of company annual

(36)

2.1.1. Direct Cost Component

The cost is prepared to cover mine facilities removal, material handling,

re-vegetation, and supporting efforts for post mining condition; erosion control,

acid mine drainage mitigation.

2.1.1.1. Mine Facilities Removal

This cost is proposed for removing or demolishing and disposal of any

supporting facilities of mining operation, if not any exception for post mining

usage of a certain items. There is not any specific calculation method could be

implemented to whole mine facilities removal, since that almost developed by

civil work. The structure demolition, disposal cost and equipments are decisive

driven by their physical characteristics such as material types, foundation, and

dimension.

Table 2.1 The commonly material used and the removal cost (Means, 2000)

Material Structure Based Type Cost ($) Units

Bricks 5 m3

Concrete 6 m3

Metal 5 m3

Iron Pipe / Water Channel 2.50 m3

Belt Conveyor 38.00 Ft

Wood / Electricity Pole 250 Ft

Wires 3.00 Ft

Shaped Concrete / Foundation 2.67 Ft

Table 2.2 Relevant building and specific construction in a mining operation (Means, 2000)

Building Based Types Specific Based Types

Offices Foundations

Warehouse Belt Conveyor

Workshop Railway

Fuel Tank Water Channel

Primary Processing Bridges

Secondary Processing Electricity Transmission

Stacker Poles

(37)

According to Means (2000), the structure demolition and disposal cost is

based on the material type in certain units as shown on Table 2.1, and the

common building and other specific types that relevant to be built in a mining

operation. The common material used and the removal cost is shown in Table 2.2.

2.1.1.2. Material Handling Plan

Land structuring or earthmoving consists of several operations, i.e. back

filled of mined area, re-contouring, top soil spreading, erosion and surface water

controls.

a. Earthmoving

The material-handling plan is determined by estimation of material

volume to be done, haulage distance, road grade, and employed equipment

types.

1) Waste rock volume estimation

Determination of material amount that must be handled

(earthmoving volumes calculation) uses standards engineering methods.

Volume calculation can be obtained by comparing the pre-reclamation and

post-reclamation topography of the site. A series of pre-reclamation and

post-reclamation cross sections can be used to calculate volumes by the

average-end-area method as follow:

i=n

V =

{[(

A(i)+A(i+1)

)

/2

]

*Li +…..+

[(

A(n-1)+A(n)

)

/2

]

*L(n-1)

}

...1)

i=1

V : Volume

Ai : Area of cross Ai section.

Li : Length between the section of area A (i) - A (i+1).

n : Number of section

Material volume is defined according to its state in the earth

moving process. There are three volume measurements, which are bank of

cubic meters (BCM), loose cubic meters (LCM), and compacted cubic

meters (CCM), which driven by a swell factor. Swell is the volume

increasing resulting from a change of bank state to loose state. Some

(38)

divided by the bank density. The following equation is used to determine

the swell factor.

SF = [100 / (LD / BD)] – 100 ……….……….. 2)

SF : Swell Factor

LD : Loose Density

BD : Bank Density

Table 2.3 Initial and final swells of selected material

Material Types Initial Swell (%) Final Swell (%)

Mixed waste rock

Siltstone

Sandstone

25-45

35-45

60-70

10-25

10-25

25-45

2) Haulage distance estimation

Haulage distance estimation is based on the reclamation and

operation plans of the permit application. This includes haul-roads and

routes designation for each area where backfilling, grading, topsoil

replacement, or other earth moving activities occurred, identify the

approximate centroid of each source material and its destination, and

determine the centroid-to-centroid distance. Centroid is a surface

expression of the center of mass.

3) Grade estimation

Haul road grade and its surface roughness conditions greatly

impact equipment productivity and may confine the type of equipment to

be employed. Most equipment productivity and guideline express these

limitations in term of the total resistance of the haul, which is the sum of

the rolling resistance and grade resistance.

TR = RR + GR ……….. 3)

(39)

4) Equipment selection

The following are the principle process in selecting appropriate

equipments.

• Determines types of equipment such as bulldozer, scraper,

excavator, dump truck, loader, grader or dragline.

• Determines model and capacity of equipments based on the

reclamation plan information; concerning land management,

material handling, and manual of equipments.

5) Land management

The land management in order to meet the reclamation plan has to

select the appropriate equipment that is efficient and effective. Typical

earthmoving activities together with equipment needed are described

bellow.

• Spoil ridge reduction: to move tops of the spoil ridges into the valley between the ridges, the operations normally rely upon

bulldozers.

• Final pit/highwall elimination; to fill the last pit with material, which its sources obtained from such following area.

- Adjacent spoil ridges or the area above the highwall, these usually by

using bulldozer.

- Overburden stockpile; normally uses scrappers or combination of

loaders and trucks to move material to the pit. When trucks and loaders

are used, bulldozers spread the material in the pit area. If the pit is going

to be reconfigured for retention as a permanent impoundment,

bulldozers are normally used to reduce the highwall and spoil slopes into

acceptable grades.

• Final grading; to re-contour backfilled area, excess spoil disposal structures and other disturbed areas, to facilitate proper drainage

and the approved post mining land use and to prepare disturbed

areas for topsoil redistribution These usually use scrapers,

bulldozers and motor graders. In some cases, especially for sites

(40)

may be required to reduce compaction in the root zone and provide

a slightly rough surface to enhance topsoil adhesion.

• Topsoil redistribution: this considers soil horizon placement, soil

depth, compaction, and drainage systems. The choice of equipment

depends on grade, the haulage distance between stockpiles and

placement areas, and the volume of material to be moved. These

normally involving the use of scrapers, front-end loaders, trucks,

bulldozers, and/or graders.

• Removal of diversions and siltation structures: to grade out

diversions and excavated siltation structures, generally bulldozers

is adequate to be used. In some cases, a hydraulic backhoe

excavator or small dragline is required to dredge accumulated

sediment.

• Covering of coal mine waste or other acid-toxic forming materials exposed: when the reclamation and operation plans require the

application of cover material prior to revegetation, the similar

equipment considerations as the topsoil redistribution activities

discussed above apply to the transport and distribution of this

material, i.e. include the covering of coarse coal mine refuse, slurry

impoundments and coal stockpile pads.

b. Productivity and Equipment Cost Calculations

The development of the materials handling plan requires a

determination of equipment productivity and earthmoving costs. Generally,

the productivity of certain equipment is expressed in cubic meter per hour.

Several factors relates to equipment productivity are capacity, cycle time, site

conditions, and material characteristics. Actually, reclamation activities do not

operate at 100% efficiency, it relies on complex factors such as operator skill,

repairing and adjustments, and personnel and job layout delays. Human factor

either addressed individual factor as part of the operator factor or combined in

(41)

factors. The total hours of an equipment usage determined by applying

productivity rates to the amount of material removed.

The following are several formulas related to the capacity estimation

for dozing, excavating, loading, and hauling of certain equipment to be

adjusted with the selected equipment specification.

1) Estimation of Bulldozer production capacities

q * 60 * b

Q = ………..……. 4)

(D/F) + (D/R) + Z

Q : Production capacity (m³/hour) q : Blade capacity (m³)

b : Blade factor

D : Dozing distance (m)

F : Forward speed (m/mnt)

R : Reverse speed (m/mnt)

Z : Transmission (mnt)

2) Estimation of Excavator production capacities

q * 3600 * e

Q = ………...……. 5)

Ct

Q : Production capacity (m³/hour) q : Bucket capacity (m³)

e : Correction factor

Ct : Cycle time (sec)

3) Estimation of Dump Truck production capacities

q * 60 * d

Q = …………...…… 6)

(n*Ct) + (D/V1) + (D/V2) + T1 +T2

Q : Production capacity (m³/hour) q : Haulage capacity (m³/hour)

d : Correction factor

(42)

4) Estimation of Wheel Loader production capacities

q * 60 * w

Q = ………...……. 7)

(D/F) + (D/R) + Z

Q : Production capacity (m³/hour) q : Bucket capacity (m³)

w : Correction factor D : Loading distance (m)

F : Forward speed (m/mnt)

R : Reverse speed (m/mnt)

Z : Transmission (mnt)

Table 2.4 Heavy Duty / Construction Equipments Rental Prices (APKASI, October 2005)

Prices / Unit ($ US)

No. Types Capacity Per Month /

210 Hours Per Hours

1 Bulldozer 160 HP 6430 32

2 Bulldozer 200 HP 8064 40

3 Bulldozer 320 HP 12860 64

4 Bulldozer 425 HP 17161 86

5 Wheel Loader 1.5 m3 3871 19

6 Wheel Loader 2.5 m3 4516 23

7 Wheel Loader 3.0 m3 4710 24

8 Wheel Loader 4.0 m3 9419 47

9 Track Loader 2.3 m3 4301 21

10 Track Loader 2.8 m3 5161 26

11 Motor Grader 135 HP 5054 25

12 Motor Grader 150 HP 5591 28

13 Hyd Excavator 0.5 m3 3527 18

14 Hyd Excavator 0.9 m3 4516 23

15 Hyd Excavator 1.5 m3 6279 31

16 Hyd Excavator 2 m3 8344 42

17 Hyd Breaker 3000 9763 49

18 Back Hoe Loader 0.3 – 1 m3 3720 19

19 Dump Truck 20 Ton 3048 17

20 Dump Truck 12 Ton 2903 14

21 Dump Truck 8 Ton 1935 10

The required cost for material handling is based on the equipment

productivity and number of equipments used, whether individual or/and

combinations. While to determine the hourly cost of equipment during

(43)

Reference Guide for Construction Equipment, for the number of shifts, oil and

fuel costs, etc.

Table 2.5 The Average of Heavy Equipment’s Lubricant and Fuel Consumptions

Consumption (Unit/hr)

No. Oil Type Unit

Excavator Bulldozer

Prices/ Unit ($ US)

1 Fuel Ltr 0.14 22.5 0.7

2 Engine Oil Ltr 0.108 0.1 2.5

3 Final Drive Oil Ltr 0.007 0.04 2.5

4 Hydraulic Oil Ltr 0.075 0.11 2.5

5 Swing Machine Oil Ltr 0.007 - 2.5

6 Transmission Oil Ltr - 0.15 2.5

7 Grease Kg 0.07 0.02 3.0

2.1.1.3. Re-vegetation

The initial re-vegetation process generally consists of seedbed preparation,

including application of soil amendment to improve soil quality, seeding,

planting, maintenance, and monitoring. The reclamation plan will specify the soil

condition and specific plantation, which has been agreed. Generally the cost of

each revegetation activities is determined per hectare.

2.1.1.4. Other Direct Reclamation Cost

Other direct reclamation cost depends on the site conditions and applicable

requirements of the reclamation and operation plans, other necessary reclamation

activities may include:

• Pumping and treating impounded waters

• Replacing wetlands

• Sealing underground mine entries and openings

• Plugging auger holes

• Sealing monitoring wells and other drilled holes.

• Constructing rock drains.

(44)

• Maintaining roads during reclamation including grading, surfacing, ditches and culverts.

• Maintaining ponds.

• Evaluating and rehabilitating structures to be retained as part of the post-mining land use (ponds, roads, diversions, etc).

There is no established method of estimating costs for most of these

activities; therefore a case-by-case basis calculation by using professional

judgment is needed.

2.1.2. Indirect Cost Component

This cost is non-technical fund, which proposed to support the realization

of reclamation planning.

2.1.2.1. Mobilization and Demobilization of Heavy Equipments

Mobilization and Demobilization (mob-demob) of heavy equipments is an

allowance for the cost of moving equipment, to and from the reclamation site. The

cost will be varied depend on such condition:

• the type and number of equipment,

• the haul distance to the site,

• the needing for special equipment;

• the presence of non standard features or condition,

• the remote location

• a necessity of separate mob-demob at a later one.

Generally the cost is range up to 10% of the total direct costs in

accordance with its constraint that should be recognized, and normally is

determined 2.5% of direct cost.

2.1.2.2. Reclamation Planning

The cost of reclamation planning is addressed to engineering redesign cost,

in the event of bond forfeiture; due to the plans in the permit application may be

not reflect site conditions at the time of bond. Necessary activities may include:

• Preparing maps and plans to show the extent of required reclamation.

(45)

• Analyzing topsoil and overburden stockpiles to determine whether special handling is necessary.

• Evaluating structures to assess the difficulty of demolition and removal.

• Evaluating impoundments and roads to determine any special reclamation needs (such as the presence of toxic materials), the feasibility of leaving those structures in place, and the reclamation needed to ensure stability and facilitate the post mining landuse.

• Assessing the condition of area reclaimed by the permitee to determine whether additional work is needed to complete the reclamation plan.

[image:45.595.132.481.161.492.2]

• Preparing contract documents.

Figure 2.1 The relationship of reclamation planning cost and Direct Cost

Based on the manual chart of “Englemen’s Heavy Construction Cost File”

(on Handbook for Calculation of Reclamation Bond Amounts - OSM US

Department of the Interior, 2000), the cost of reclamation plan generally allocate

in between 2.5%-6.0% of direct cost, whilst DEMR has been determined in

between 2%-10% as shown on Figure 2.1. The following formula is derived from

this chart.

Y = exp(13.8155105579643-1.15129254649702X) ; or

(LN(Y))=13.8155105579643-1.15129254649702X ... 8)

Y : Direct Cost

(46)

2.1.2.3. Administration Cost and Contractor Profit

The reclamation plan is designed likely to be conducted by a third party,

thus overhead and profit for the contractor as reclamation doer have to be included

in bond amount. This allowance is needed to anticipate when an uncertainty event

or in default condition occurred.

Based on the manual chart of “Englemen’s Heavy Construction Cost File”

(on Annual Plan of Environmental Management for Reclamation Bond, DEMR),

the overhead and profit costs related to the direct cost is in between 3%-14% as

classified follow:

• for Y

21000, then X=14, and

• for Y

100000000, then X=3, else

• for 21000

<

Y

<

100000000, then X is determined by the following equation;

Y= exp(20.7232658369464-0.767528364331349X), or

(LN(Y))=20.7232658369464-0.767528364331349X ……...………..9)

Y : Direct cost (US$ million) X : Overhead and profit (%)

[image:46.595.135.497.310.729.2]
(47)

2.1.2.4. Management Cost

Reclamation management cost is addressed to hire an independence

project management firm related to inspect and supervise the reclamation

contractor work performance. Some activities may include as additional work,

such as dam inspection.

Based on the manually chart of “Englemen’s Heavy Construction Cost

File” (on Annual Plan of Environmental Management for Reclamation Bond,

DEMR), the fee is in between 2%-7% related to the direct cost is configured in

equations and shown on chart below.

• for Y

10000, then X = 7, and

• for Y

100000000, then X = 2, else

• for 10000

<

Y

<

100000000, then X is determined by the following equation;

Y = exp(22.1048168927428 - 1.84206807439524X), or

(LN(y)) = 22.1048168927428 - 1.84206807439524X …………………10)

Y : Direct cost (US$ million)

X : Reclamation management cost (%)

[image:47.595.139.479.444.719.2]
(48)

2.1.3. Determining the Total Performance Bond Amount

Reclamation cost is total amount of direct and indirect cost components,

whilst the Reclamation Bond is determined for its five years period. Therefore

actual reclamation cost as the first annum bond must be in detail, and the

calculation of each component can be expressed in a certain price per units. In the

absence of major changes to the reclamation and operation plans, accordingly

without redoing the both calculation, the cost of remaining fourth years can be

estimated by considering a predicted annually escalation price or inflations.

Rc = DC + IC .……….…11)

RC : Reclamation Cost

DC : Direct Cost IC : Indirect Cost

i= 5

Rb =

[(

1+E(i)

)

*Dc(i) + IC(i)

]

...12)

i=1

Rb : Reclamation Bond

Ei : Escalation year i Dc(i) : Direct Cost year i IC(i) : Indirect Cost year i

2.2. Decision Support System

Decision theory is an essential branch of operations and resource

management and its methodology has been developed at the intersection between

applied mathematics and computer engineering. In the past, decision processes

were considered to be simple rational mathematical optimizations, based on linear

programming and graphical techniques. However, this oversimplification resulted

in system representations which were far from real conditions and consequently of

limited practical application. Since the end of 1950s, the Nobel prize-winner H.

Simmon introduced the need to human capacity to process it. Simmon suggested

the formulation of realistic goals that reflect satisfactory solution instead of

optimal ones, and proposed adapting the decision procedure to human heuristic

behavior, by introducing the concept of three interactive and iterative phases:

intelligence, design, and choice phases. Together with the introduction of

(49)

construction of integrated Decision Support Systems (Hernandez and Carnelli,

1996).

Decision making can be a complicated process, because decision makers

are faced with an ever-increasing number of alternatives, the relationships

between the variables involved are complex, and frequent changes are occurring.

Decision often must be made under time pressure, and several decisions may be

interrelated (Turban, 2003).

Turban (2003) stated that Decision Support System (DSS) is a computer

based information system that combines models and data to provide support for

decision makers in solving non-structured and semi-structured or interdependent

problems with extensive user involvement. DSS consist of the following four

main components; Data Management, User Interface, Model Management, and

[image:49.595.119.511.365.703.2]

Knowledge Management subsystems.

(50)

2.2.1. Data Management

The data management includes a specially constructed database or set of

files that contain relevant data for the decision situation and is managed by a

database management system (DBMS). Data can also be obtained directly from

the corporate data warehouse, from regular databases, or from other sources.

2.2.2. Model Management

Model management includes software with financial, statistical,

management science, or other quantitative models. These provide the systems

analytical capabilities and an appropriate software management program to

manage the models. Some of the models are preprogrammed, while others are

built by the DSS builder or end user.

2.2.3. Knowledge Management

The knowledge management subsystem can support any of the other

subsystems or act as an independent component, providing knowledge for the

solution of the specific problem. This subsystem is available in only some DSSs.

2.2.4. User Interface

The user interface subsystem enables the user to communicate with and

(51)

III. METHODOLOGY

This section describes the materials and the methods used in designing,

creating and implementing Mining Rehabilitation Bond System of a mining area.

3.1. Time and Location Selection

The research has been conducted from April 2005 to January 2006 at

Gambar

Figure 1.3  The Lay Out of a mining facility to support mining operation (Adopted from http://www.nrcan.gc.ca/mms/mining/)
Figure 1.4   The land management mechanism of a back filling surface mining method (Adopted from Skelly and Loy, 1975)
Figure 2.1  The relationship of reclamation planning cost and Direct Cost
Figure 2.2  The relationship of overhead and contractor profit and Direct Cost
+7

Referensi

Dokumen terkait

Decision Support System for Organizing Supervision Distribution (DSSOSD) is an online system that is developed to support the management process of auto generates the

Figure 4 shows transformation that exists in the process of extracting and transforming data for decision support system at XYZ University, that is taking data from

A decision support system or DSS is a computer based system intended for use by a particular manager or usually a group of managers at any organizational level in making a decision

Selanjutnya, tiga teknik klasifikasi data mining yang berbeda seperti OneR, Decision Tree, dan Naive Bayes digunakan untuk analisis dataset dengan menggunakan training set pada tool

In building a decision support system for determining employee bonuses using the Simple Additive Weighting SAW method, information is needed in the form of employee data which is an

9% SIMILARITY INDEX 8% INTERNET SOURCES 7% PUBLICATIONS 8% STUDENT PAPERS 1 5% 2 1% 3 1% 4 1% 5 < 1% Decision Support System for Selecting Type of Moveable Dam Gate to

METHODS This chapter explains the approach and steps used in the research to develop a Decision Support System for the Selection of Productive Individuals at Sahabat Sampulo

MINING AND MINERALS SECTOR R&D Roadmap for Technologies in Support of Rehabilitation of Abandoned and Mined-out Area Done Ongoing Not yet Available 2021 2023 2024 2025 2028