• Tidak ada hasil yang ditemukan

Slide TSP305 TSP 305 008 Manajemen Konstruksi

N/A
N/A
Protected

Academic year: 2017

Membagikan "Slide TSP305 TSP 305 008 Manajemen Konstruksi"

Copied!
8
0
0

Teks penuh

(1)

Construction Operation

Ferdinand Fassa

(2)

Outline

1. Authority and Responsibility of all Parties

2. Time of Inspection and Test

3. Contractor Submittals

4. Instruction to field

(3)

1. Authority and Responsibility of all Parties

Owner

Authorized to award contract

To make changes in the work

To withhold payments from the contractor for adequate cause

To inspect the work as progresses

To direct contractor to expedite the work

To make payment deductions from incomplete or faulty work

Contractor

Major responsibility is to construct the project in accordance with the drawings, specification, and other contract documents.

Resident Project Representative

(4)

2. Time of Inspection and Test

a. Contractor must give the engineer timely notice

b. Tests and inspections required by public agencies must usuaslly be paid for by the contractor

c. Test and inspections, other than those mentioned, that are required by the contract document will be paid for by the owner

d. Extra inspection required as the result of a deficiency noted by the inspector must be paid for by the contractor

(5)

3. Contractor Submittals

a. All submittals from the contractor should be handled in a systematic, consistent, and orderly manner.

b. Contractor submittals are to be documented both when

coming in going out

c. Keep photographic records of progress and all potential

claim issue

d. Contractor submittal handled only through Resident Project

(6)

4. Instruction to field

a. Inspect the work as it progress

b. No field changes without Project Manager Instruction

c. Instruction to the contractor through superintendent or Project Manager

d. Field orders and change orders must be handled through Resident Project Representative

e. No changes on oral instructions without written confirmation

f. No significant deviatons from plans and specifications except by change order-event if no cost or time extension is

involved

g. Emergency changes by work directive change followed latter by a change order

(7)

5. Suspension or Termination of The Work

a. Suspension of work by the Owner

(8)

Referensi

Dokumen terkait

Setelah dimensi assurance, dimensi responsivenes ditanggapi baik 73% dengan indikator konsistensi perawat untuk menyiapkan waktu menemani pasien dinilai benar 53%

Men etapk an : PERATURAN PEMERINTAH TENTANG J ENIS DAN TARIF ATAS J ENIS PENERIMAAN NEGARA BUKAN PAJAK YANG BERLAKU PADA KEMENTERIAN AGAMA.. Kant or Ur u san Agam

Sebuah skripsi yang diajukan untuk memenuhi salah satu syarat memperoleh gelar Sarjana Teknik pada Fakultas Pendidikan Teknologi dan Kejuruan. © Cherry Cendana Hapit 2014

Siklus menu 10 hari di rumah sakit ini menunjukkan, bahwa nilai gizi makanan disajikan masih sangat rendah jika dibandingkan dengan yang disajikan di RS

Gambar 4.23 Profil Muka Air memanjang sungai dengan Retensi

Pelatihan Aplikasi Spreadsheet sebagai Media Pembelajaran SMK Bangunan dalam Perencanaan Tulangan Lentur dan Geser Balok Beton Bertulang Menurut SNI 03-2847-2002. Anggota 2008

Adapun pengaruhnya adalah sebesar 0.323, dan signifikan pada taraf 5% yang berarti semakin baik penerapan consumer edu- cation dalam setiap pelayanan yang diberikan oleh pihak

Pokok bahasan dalam buku ini diawali dengan tinjauan sifat, perilaku dan metode pengujian material yang digunakan dalam struktur beton bertulang, dilanjutkan