Latihan Soal Network
1.
Find the shortest path from node 1 to node 5 in Figure 4.3.
Draw the project network and determine the critical path for the network, the total float for each activity, and the free float for each activity. Also set up the LP that can be used to find the project’s critical path.
4. Consider the project network in Figure 40. For each activity, you are given the estimates of a, b, and m in Table 18. Determine the critical path for this network, the total float for each activity, the free float for each activity, and the probability that the project is completed within 40 days. Also set up the LP that could be used to find the critical path.