RENCANA PENGADAAN/PROCUREMENT PLAN TA 2009
Unit Kerja DINAS Pengairan Provinsi Sumatera Utara
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya
eqv(US$)
Metode
Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego Penandatanganan Kontrak
Jangka Waktu Kontrak (Hari Kalender) Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN
1 G4-A-DIN PEMBANGUNAN JARINGAN-LAN 83,000,000 9,765 NS Post Mar-09 Apr-09 May-09 May-09 20
2 G5-A-DIN PENGADAAN KENDARAAN 300,000,000 35,294 NCB Prior Review Kontrak I Mar-09 Apr-09 May-09 May-09 20
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD) Supporting WISMP (DPA-APBD) 193,309,000
TOTAL KEGIATAN I (Loan) 383,000,000 45,059 TOTAL KEGIATAN II (GOI-PF/APBD) 193,309,000 -Water Resources and Irrigation Sector Management Project (WISMP) APL I
Komponen A
Status : 31 Januari 2009
Goods (Category 2)
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
RENCANA PENGADAAN/PROCUREMENT PLAN TA 2009
Unit Kerja DINAS Pengairan Provinsi Sumatera Utara
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya
eqv(US$)
Metode
Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego Penandatanganan Kontrak
Jangka Waktu Kontrak (Hari Kalender) Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN
C.3.2. PELAKSANAAN REHABILITASI DENGAN METODA PARTISIPATIF
A. DI. Javakolonisasi/ Purbogondo ( 1030 Ha )
1 W10-B-D - Paket I ( 100 Ha ) 150,000,000 17,647 SW Post Mar-09 Apr-09 May-09 May-09 60
2 W11-B-D - Paket II ( 100 Ha ) 150,000,000 17,647 SW Post Mar-09 Apr-09 May-09 May-09 60
3 W12-B-D - Paket III ( 100 Ha) 150,000,000 17,647 SW Post Mar-09 Apr-09 May-09 May-09 60
B. DI. RAJA MALIGAS (1000 HA)
4 W13-B-D - Paket I ( 150 Ha ) 200,000,000 23,529 SW Post Mar-09 Apr-09 May-09 May-09 60
C. DI. BAH KORAH II/NEGERI BOSAR (2700 HA)
5 W14-B-D - Paket I ( 150 Ha ) 200,000,000 23,529 SW Post Mar-09 Apr-09 May-09 May-09 60
6 W15-B-D - Paket I ( 150 Ha ) 200,000,000 23,529 SW Post Mar-09 Apr-09 May-09 May-09 60
D. DI. PEKAN KEMIS (1100 HA)
7 W16-B-D - Paket I ( 100 Ha ) 150,000,000 17,647 SW Post Mar-09 Apr-09 May-09 May-09 60
E. DI. PEKAN DOLOK (1050 HA)
8 W17-B-D - Paket I ( 100 Ha ) 150,000,000 17,647 SW Post Mar-09 Apr-09 May-09 May-09 60
F. DI. SUMBER REJO LAMA (2064 HA)
9 W18-B-D - Paket I ( 100 Ha ) 150,000,000 17,647 SW Post Mar-09 Apr-09 May-09 May-09 60
10 W19-B-D - Paket II ( 100 Ha ) 150,000,000 17,647 SW Post Mar-09 Apr-09 May-09 May-09 60
G. DI. LANGAU (2300 HA)
11 W20-B-D - Paket I ( 100 Ha ) 150,000,000 17,647 SW Post Mar-09 Apr-09 May-09 May-09 60
12 W21-B-D - Paket II ( 100 Ha ) 150,000,000 17,647 SW Post Mar-09 Apr-09 May-09 May-09 60
G. DI. LANGAU (2300 HA)
13 W22-B-D - Paket I ( 100 Ha ) 150,000,000 17,647 SW Post Mar-09 Apr-09 May-09 May-09 60
14 W23-B-D - Paket II ( 100 Ha ) 150,000,000 17,647 SW Post Mar-09 Apr-09 May-09 May-09 60
H. DI. NAMURAMBE (1036 HA)
15 W24-B-D - Paket I ( 100 Ha ) 400,000,000 47,059 NCB Prior Mar-09 Apr-09 May-09 May-09 60 16 W25-B-D - Paket II ( 100 Ha ) 400,000,000 47,059 NCB Prior Mar-09 Apr-09 May-09 May-09 60
17 G5-B-DINPENGADAAN THEODOLIT 65,000,000 7,647 NS Post Mar-09 Apr-09 May-09 May-09 20
Status : 31 Januari 2009
Goods (Category 2)
Water Resources and Irrigation Sector Management Project (WISMP) APL I Komponen B
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya eqv(US$)
Metode
Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego Penandatanganan Kontrak
Jangka Waktu Kontrak (Hari Kalender) Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
SURVEY PENDAHULUAN, INVESTIGASI, PENGUKURAN JAR. IRIGASI, ANALISA DATA,
SYSTIM PLANNING, PRA DESAIN DAN PELAPORAN
19 CS5-B-DI DI. JAVAKOLONISASI/PURBOGONDO (1030 HA) 45,000,000 5,294 CQS Mar-09 Apr-09 May-09 May-09 60 20 CS6-B-DI DI. RAJA MALIGAS (1000 HA) 48,000,000 5,647 CQS Mar-09 Apr-09 May-09 May-09 60 21 CS7-B-DI DI. BAH KORAH II (1995 HA) LINTAS KABUPATEN 48,000,000 5,647 CQS Mar-09 Apr-09 May-09 May-09 60 22 CS8-B-DI DI. RAMBUNG MERAH (944 HA) . 47,000,000 5,529 CQS Mar-09 Apr-09 May-09 May-09 60 23 CS9-B-DI DI. PEKAN KEMIS (1050 HA) 47,000,000 5,529 CQS Mar-09 Apr-09 May-09 May-09 60 24 CS10-B-D DI. PEKAN DOLOK (1100 HA) 47,000,000 5,529 CQS Mar-09 Apr-09 May-09 May-09 60 25 CS11-B-D DI. BENDANG (1380 HA) 48,000,000 5,647 CQS Mar-09 Apr-09 May-09 May-09 60 26 CS12-B-D DI. MEDAN KRIO (2800 HA) 48,000,000 5,647 CQS Mar-09 Apr-09 May-09 May-09 60 27 CS13-B-D DI. SUMBER REJO LAMA (2064 HA) 45,000,000 5,294 CQS Mar-09 Apr-09 May-09 May-09 60 28 CS14-B-D DI. NAMURAMBE (1036 HA) 45,000,000 5,294 CQS Mar-09 Apr-09 May-09 May-09 60
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD) C.3.2. PELAKSANAAN REHABILITASI DENGAN
METODA PARTISIPATIF I. DI. Ramunia (1880 Ha)
1 - Paket I ( 345 Ha ) 75,000,000 Mar-09 Apr-09 May-09 May-09 60
2 - Paket II ( 345 Ha ) 100,000,000 Mar-09 Apr-09 May-09 May-09 60
3 - Paket III ( 345 Ha ) 82,711,700 Mar-09 Apr-09 May-09 May-09 60
J. DI. Langau (2300 Ha)
4 - Paket I ( 345 Ha ) 75,000,000 Mar-09 Apr-09 May-09 May-09 60
K. DI. Bekala (1880 Ha)
5 - Paket I ( 345 Ha ) 75,000,000 Mar-09 Apr-09 May-09 May-09 60
6 - Paket II ( 345 Ha ) 85,000,000 Mar-09 Apr-09 May-09 May-09 60
TOTAL KEGIATAN I (Loan) 3,643,000,000 428,588 TOTAL KEGIATAN II (GOI-PF/APBD) 492,711,700
-Kepres
Prior Review Kontrak I
RENCANA PENGADAAN/PROCUREMENT PLAN TA 2009
Unit Kerja BPSDA ASAHAN DANAU TOBA
No Kode Nama Paket Estimasi Biaya
(Rp)
Estimasi Biaya eqv(US$)
Metode
Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego Penandatanganan Kontrak
Jangka Waktu Kontrak (Hari Kalender) Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN
1 CW5-ADT Pembangunan Pos ARR 30,000,000 3,529 SW Post Mar-09 Apr-09 May-09 May-09 20
2 G6-ADT Pengadaan Komputer dan Printer (1,00 KEG) 15,000,000 1,765 NS Post Mar-09 Apr-09 May-09 May-09 20
3 G7-ADT Pengadaan Current Meter (1,00 KEG) 95,000,000 11,176 NS Post Mar-09 Apr-09 May-09 May-09 20
4 G8-ADT Pengadaan ARR (1,00 KEG) 25,000,000 2,941 NS Post Mar-09 Apr-09 May-09 May-09 20
5 G9-ADT Pembelian Genset + Chainshaw (1,00 KEG) 21,000,000 2,471 NS Post Mar-09 Apr-09 May-09 May-09 20
6 RA1-ADT Pengadaan Peralatan Lapangan 42,000,000 4,941 NS Post Mar-09 Apr-09 May-09 May-09 20
7 RA2-ADT Sungai Silau, Perkuatan Tanggul Sungai Sepj. 40
m 120,000,000 14,118 SW Post Mar-09 Apr-09 May-09 May-09 60
8 RA3-ADT Sei Gambus, Peninggian Tanggul Sepj. 500 m 120,000,000 14,118 SW Post Mar-09 Apr-09 May-09 May-09 60
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD) Supporting WISMP (DPA-APBD) 124,485,500 Water Resources and Irrigation Sector Management Project (WISMP) APL I Komponen A
Status : 31 Januari 2009
Civil Works (Category 1)
Goods (Category 2)
RENCANA PENGADAAN/PROCUREMENT PLAN TA 2009
Unit Kerja BPSDA LAU RENUN
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya
eqv(US$)
Metode
Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego Penandatanganan Kontrak
Jangka Waktu Kontrak (Hari Kalender) Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN
1 CW5-LR Pembangunan Pos ARR 30,000,000 3,529 SW Post Mar-09 Apr-09 May-09 May-09 20
2 G6-LR Pengadaan Komputer dan Printer (1,00 KEG) 15,000,000 1,765 NS Post Mar-09 Apr-09 May-09 May-09 20
3 G7-LR Pengadaan Current Meter (1,00 KEG) 95,000,000 11,176 NS Post Mar-09 Apr-09 May-09 May-09 20
4 G8-LR Pengadaan ARR (1,00 KEG) 25,000,000 2,941 NS Post Mar-09 Apr-09 May-09 May-09 20
5 G9-LR Pembelian Genset + Chainshaw (1,00 KEG) 21,000,000 2,471 NS Post Mar-09 Apr-09 May-09 May-09 20
6 RA1-LR Pengadaan Peralatan Lapangan 42,000,000 4,941 NS Post Mar-09 Apr-09 May-09 May-09 20
7 RA2-LR Sungai Lae Bongkaras, Perkuatan Tebing Sungai Sepj. 50 M 120,000,000 14,118 SW Post Mar-09 Apr-09 May-09 May-09 60
8 RA3-LR Sungai Lae Nuaha, Perkuatan Tebing Sungai Sepj. 50 m 120,000,000 14,118 SW Post Mar-09 Apr-09 May-09 May-09 60
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
1 Supporting WISMP (DPA-APBD) 124,485,500
TOTAL KEGIATAN I (Loan) 468,000,000 55,059 TOTAL KEGIATAN II (GOI-PF/APBD) 124,485,500
-Status : 31 Januari 2009 Water Resources and Irrigation Sector Management Project (WISMP) APL I
Komponen A
RIM-A (Category 5) Civil Works (Category 1) Goods (Category 2)
RENCANA PENGADAAN/PROCUREMENT PLAN TA 2009
Unit Kerja BPSDA SIBUNDONG BATANG TORU
No Kode Nama Paket Estimasi Biaya
(Rp)
Estimasi Biaya eqv(US$)
Metode
Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego Penandatanganan Kontrak
Jangka Waktu Kontrak (Hari Kalender) Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN
1 CW5-SBT Pembangunan Pos ARR 30,000,000 3,529 SW Post Mar-09 Apr-09 May-09 May-09 20
2 G6-SBT Pengadaan Komputer dan Printer (1,00 KEG) 15,000,000 1,765 NS Post Mar-09 Apr-09 May-09 May-09 20
3 G7-SBT Pengadaan Current Meter (1,00 KEG) 95,000,000 11,176 NS Post Mar-09 Apr-09 May-09 May-09 20
4 G8-SBT Pengadaan ARR (1,00 KEG) 25,000,000 2,941 NS Post Mar-09 Apr-09 May-09 May-09 20
5 G9-SBT Pembelian Genset + Chainshaw (1,00 KEG) 21,000,000 2,471 NS Post Mar-09 Apr-09 May-09 May-09 20
6 RA1-SBT Pengadaan Peralatan Lapangan 42,000,000 4,941 NS Post Mar-09 Apr-09 May-09 May-09 20
7 RA2-SBT Sungai Aek Pinang Sori, Perkuatan Tanggul
Sungai Sepj. 40 m 100,000,000 11,765 SW Post Mar-09 Apr-09 May-09 May-09 60
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
1 Supporting WISMP (DPA-APBD) 124,485,500
TOTAL KEGIATAN I (Loan) 328,000,000 38,588 TOTAL KEGIATAN II (GOI-PF/APBD) 124,485,500
-Status : 31 Januari 2009 Water Resources and Irrigation Sector Management Project (WISMP) APL I
Komponen A
RIM-A (Category 5) Civil Works (Category 1)
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya eqv(US$)
Metode
Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego Penandatanganan Kontrak
Jangka Waktu Kontrak (Hari Kalender) Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA PENGADAAN/PROCUREMENT PLAN TA 2009
Unit Kerja BPSDA KUALUH BARUMUN
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya
eqv(US$)
Metode
Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego Penandatanganan Kontrak
Jangka Waktu Kontrak (Hari Kalender) Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN
1 CW5-KB Pembangunan Pos ARR 30,000,000 3,529 SW Post Mar-09 Apr-09 May-09 May-09 20
2 G6-KB Pengadaan Komputer dan Printer (1,00 KEG) 15,000,000 1,765 NS Post Mar-09 Apr-09 May-09 May-09 20
3 G7-KB Pengadaan Current Meter (1,00 KEG) 95,000,000 11,176 NS Post Mar-09 Apr-09 May-09 May-09 20
4 G8-KB Pengadaan ARR (1,00 KEG) 25,000,000 2,941 NS Post Mar-09 Apr-09 May-09 May-09 20
5 G9-KB Pembelian Genset + Chainshaw (1,00 KEG) 21,000,000 2,471 NS Post Mar-09 Apr-09 May-09 May-09 20
6 RA1-KB Pengadaan Peralatan Lapangan 42,000,000 4,941 NS Post Mar-09 Apr-09 May-09 May-09 20
7 RA2-KB Sei Bilah, Peninggian Tanggul Kiri Sei Bilah Sep. 400 m 130,000,000 15,294 SW Post Mar-09 Apr-09 May-09 May-09 60
8 RA3-KB Sei Kenopan, Perkuatan Tebing Sungai Sepj. 50 m 130,000,000 15,294 SW Post Mar-09 Apr-09 May-09 May-09 60
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
1 Supporting WISMP (DPA-APBD) 124,485,500
Water Resources and Irrigation Sector Management Project (WISMP) APL I Komponen A
Status : 31 Januari 2009
RIM-A (Category 5) Civil Works (Category 1) Goods (Category 2)
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya eqv(US$)
Metode
Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego Penandatanganan Kontrak
Jangka Waktu Kontrak (Hari Kalender) Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA PENGADAAN/PROCUREMENT PLAN TA 2009
Unit Kerja BPSDA BAH BOLON
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya
eqv(US$)
Metode
Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego Penandatanganan Kontrak
Jangka Waktu Kontrak (Hari Kalender) Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN
1 CW5-BB Pembangunan Pos ARR 30,000,000 3,529 SW Post Mar-09 Apr-09 May-09 May-09 20
2 G6-BB Pengadaan Komputer dan Printer (1,00 KEG) 15,000,000 1,765 NS Post Mar-09 Apr-09 May-09 May-09 20
3 G7-BB Pengadaan Current Meter (1,00 KEG) 95,000,000 11,176 NS Post Mar-09 Apr-09 May-09 May-09 20
4 G8-BB Pengadaan ARR (1,00 KEG) 25,000,000 2,941 NS Post Mar-09 Apr-09 May-09 May-09 20
5 G9-BB Pembelian Genset + Chainshaw (1,00 KEG) 21,000,000 2,471 NS Post Mar-09 Apr-09 May-09 May-09 20
6 RA1-BB Pengadaan Peralatan Lapangan 42,000,000 4,941 NS Post Mar-09 Apr-09 May-09 May-09 20
7 RA2-BB Sei Bah Bolon, Perkuatan Tanggul Sungai Sepj. 40 m 130,000,000 15,294 SW Post Mar-09 Apr-09 May-09 May-09 60
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
1 Supporting WISMP (DPA-APBD) 124,485,500
TOTAL KEGIATAN I (Loan) 358,000,000 42,118
Status : 31 Januari 2009 Water Resources and Irrigation Sector Management Project (WISMP) APL I
Komponen A
RIM-A (Category 5) Civil Works (Category 1)
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya eqv(US$) Metode
Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego Penandatanganan Kontrak
Jangka Waktu Kontrak (Hari Kalender) Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA PENGADAAN/PROCUREMENT PLAN TA 2009
Unit Kerja BPSDA BATANG GADIS BATANG NATAL
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya
eqv(US$)
Metode
Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego Penandatanganan Kontrak
Jangka Waktu Kontrak (Hari Kalender) Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN
1 CW5-BGBN Pembangunan Pos ARR 30,000,000 3,529 SW Post Mar-09 Apr-09 May-09 May-09 60
2 G6-BGBN Pengadaan Komputer dan Printer (1,00 KEG) 15,000,000 1,765 NS Post Mar-09 Apr-09 May-09 May-09 20
3 G7-BGBN Pengadaan Current Meter (1,00 KEG) 95,000,000 11,176 NS Post Mar-09 Apr-09 May-09 May-09 20
4 G8-BGBN Pengadaan ARR (1,00 KEG) 25,000,000 2,941 NS Post Mar-09 Apr-09 May-09 May-09 20
5 G9-BGBN Pembelian Genset + Chainshaw (1,00 KEG) 21,000,000 2,471 NS Post Mar-09 Apr-09 May-09 May-09 20
6 RA1-BGBN Pengadaan Peralatan Lapangan 42,000,000 4,941 NS Post Mar-09 Apr-09 May-09 May-09 20
7 RA2-BGBN Aek Tambangan, Perkuatan Tanggul Sungai Sepanjang 40 m 100,000,000 11,765 SW Post Mar-09 Apr-09 May-09 May-09 60
8 RA3-BGBN Aek Soma, Perkuatan Tebing Sungai Sepj. 40 m 100,000,000 11,765 SW Post Mar-09 Apr-09 May-09 May-09 60
9 RA4-BGBN Aek Simangutong, Perkuatan Tebing Sungai Sepj. 50 m 100,000,000 11,765 SW Post Mar-09 Apr-09 May-09 May-09 60
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
1 Supporting WISMP (DPA-APBD) 124,485,500
Status : 31 Januari 2009 Water Resources and Irrigation Sector Management Project (WISMP) APL I
Komponen A
RIM-A (Category 5) Civil Works (Category 1) Goods (Category 2)
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya eqv(US$)
Metode
Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego Penandatanganan Kontrak
Jangka Waktu Kontrak (Hari Kalender) Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA PENGADAAN/PROCUREMENT PLAN TA 2009
Unit Kerja BPSDA BELAWAN PADANG
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya
eqv(US$)
Metode
Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego Penandatanganan Kontrak
Jangka Waktu Kontrak (Hari Kalender) Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN
1 G10-BP Pengadaan Current Meter +Peilschaal(1,00 KEG) 98,000,000 11,529 NS Post Mar-09 Apr-09 May-09 May-09 20
2 G11-BP PEMBANGUNAN JARINGAN-LAN 39,000,000 4,588 NS Post Mar-09 Apr-09 May-09 May-09 20
3 G12-BP Peralatan Lab Kualitas Air 70,900,000 8,341 NS Post Mar-09 Apr-09 May-09 May-09 20
4 RA13-BP Pengadaan Peralatan Lapangan 34,000,000 4,000 NS Post Mar-09 Apr-09 May-09 May-09 20
5 RA14-BP Sungai Bah Karai ( Anak Sungai Ular ) 100,000,000 11,765 SW Post Mar-09 Apr-09 May-09 May-09 20
Perkuatan Tebing Sungai dengan Bronjong Kawat sepj. 50 M' Desa Bandar Kuala Kab. Serdang Bedagai
6 RA15-BP Sungai Belumai 100,000,000 11,765 SW Post Mar-09 Apr-09 May-09 May-09 20
Perkuatan Tebing Sungai dengan Bronjong Kawat Sepj. 60 M' Desa Tumpatan Nibung Kab. Deli Serdang
7 RA16-BP Sungai Batugingging 100,000,000 11,765 SW Post Mar-09 Apr-09 May-09 May-09 20
Perkuatan Tebing Sungai dengan pasangan Sepj. 65 M' Desa tanjung Mulia Kec. T. Morawa Kab. D. Serdang
8 RA16-BP Sungai Kuala Namo ( Anak Sungai Serdang) 100,000,000 11,765 SW Post Mar-09 Apr-09 May-09 May-09 20
PerkuatanTebing Sungai dengan Bronjong kawat sepj. 50 M' Desa Paluh Kemiri Kec. Tanjung Morawa Kab. Deli Serdang
9 RA17-BP Sungai Batang Kuis 100,000,000 11,765 SW Post Mar-09 Apr-09 May-09 May-09 20
Perkuatan Tebing Sungai dengan pasangan sepj. 60 M' Desa Bandar Khalipah Kec. Percut sei Tuan Kab. Deli Serdang
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
1 Supporting WISMP (DPA-APBD) 166,814,000
RIM-A (Category 5)
Status : 31 Januari 2009
Water Resources and Irrigation Sector Management Project (WISMP) APL I Komponen A
RENCANA PENGADAAN/PROCUREMENT PLAN TA 2009
Unit Kerja BPSDA BATANG ANGKOLA
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya
eqv(US$)
Metode
Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego Penandatanganan Kontrak
Jangka Waktu Kontrak (Hari Kalender) Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN
1 CW5-BA Pembangunan Pos AWLR 135,000,000 15,882 SW Post Mar-09 Apr-09 May-09 May-09 60
2 G6-BA Pengadaan AWLR (1,00 KEG) 96,000,000 11,294 NS Post Mar-09 Apr-09 May-09 May-09 20
3 G7-BA Pengadaan Jaringan LAN (1,00 KEG) 39,000,000 4,588 NS Post Mar-09 Apr-09 May-09 May-09 20
4 RA1-BA Pengadaan Peralatan Lapangan 34,000,000 4,000 NS Post Mar-09 Apr-09 May-09 May-09 20
5 RA2-BA - Sungai Aek Rukkare, Desa Partihaman Saroha 120,000,000 14,118 SW Post Mar-09 Apr-09 May-09 May-09 60
Kec Huta imbaru Kota Padang Sidimpuan Perkuatan Aek Rukkare Sepanjng 35 m'
6 RA3-BA - Sungai Batang Ayumi Kelurahan Bincar 120,000,000 14,118 SW Post Mar-09 Apr-09 May-09 May-09 60
Kec Padang Sidimpuan Utara Kota Padang Sidimpuan Perkuatan tebing Sungai Batang Ayumi Sepanjang 30 m'
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
1 Supporting WISMP (DPA-APBD) 129,230,000
TOTAL KEGIATAN I (Loan) 544,000,000 64,000 TOTAL KEGIATAN II (GOI-PF/APBD) 129,230,000 -Water Resources and Irrigation Sector Management Project (WISMP) APL I
Komponen A
Status : 31 Januari 2009
Civil Works (Category 1)
Goods (Category 2)
RENCANA PENGADAAN/PROCUREMENT PLAN TA 2009
Unit Kerja BPSDA WAMPU BESITANG
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya eqv(US$)
Metode
Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego Penandatanganan Kontrak
Jangka Waktu Kontrak (Hari Kalender) Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN
1 CW5-WB Pembangunan Pos AWLR 100,000,000 11,765 SW Post Mar-09 Apr-09 May-09 May-09 60
2 G6-WB Pengadaan AWLR (1,00 KEG) 96,000,000 11,294 NS Post Mar-09 Apr-09 May-09 May-09 20
3 G7-WB Pengadaan Jaringan LAN (1,00 KEG) 39,000,000 4,588 NS Post Mar-09 Apr-09 May-09 May-09 20
4 RA1-WB Pengadaan Peralatan Lapangan 34,000,000 4,000 NS Post Mar-09 Apr-09 May-09 May-09 20
5 RA2-WB - Sei. Bangkatan, Perkuatan tebing sungai sepj. 80 m' 135,000,000 15,882 SW Post Mar-09 Apr-09 May-09 May-09 60 Desa Pujidadi Kec. Binjai Selatan
6 RA3-WB - Sei. Buah Apem, Perkuatan Tebing Sungai sepj. 80 m' 135,000,000 15,882 SW Post Mar-09 Apr-09 May-09 May-09 60 7 Desa Bruam Kec. Kuala
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
1 Supporting WISMP (DPA-APBD) 113,930,000
TOTAL KEGIATAN I (Loan) 539,000,000 63,412
Status : 31 Januari 2009 Water Resources and Irrigation Sector Management Project (WISMP) APL I
Komponen A
RIM-A (Category 5) Civil Works (Category 1)
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya eqv(US$)
Metode
Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego Penandatanganan Kontrak
Jangka Waktu Kontrak (Hari Kalender) Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA PENGADAAN/PROCUREMENT PLAN TA 2009
Unit Kerja BPSDA NIAS
No Kode Nama Paket Estimasi Biaya
(Rp)
Estimasi Biaya eqv(US$)
Metode
Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego Penandatanganan Kontrak
Jangka Waktu Kontrak (Hari Kalender) Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN
1 CW5-N Pembangunan Pos AWLR 135,000,000 15,882 SW Post Mar-09 Apr-09 May-09 May-09 60
2 G6-N Pengadaan AWLR (1,00 KEG) 96,000,000 11,294 NS Post Mar-09 Apr-09 May-09 May-09 20
3 G7-N Pengadaan Jaringan LAN (1,00 KEG) 39,000,000 4,588 NS Post Mar-09 Apr-09 May-09 May-09 20
4 G8-N Pengadaan Papan Duga Air (1,00 KEG) 20,000,000 2,353 NS Post Mar-09 Apr-09 May-09 May-09 20
5 RA1-N Muzoi Kec. Lahewa Kab. Nias 135,000,000 15,882 SW Post Mar-09 Apr-09 May-09 May-09 60
Pembersihan Tanggul 300 m Pemb. Krib 3 (tiga) buah
6 RA2-N Gidosihite Kec. Gido Kab. Nias 135,000,000 15,882 SW Post Mar-09 Apr-09 May-09 May-09 60
Pembersihan Tanggul 300 m Pemb. Krib 3 (tiga) buah
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
1 Supporting WISMP (DPA-APBD) 129,230,000
TOTAL KEGIATAN I (Loan) 560,000,000 65,882 TOTAL KEGIATAN II (GOI-PF/APBD)
Water Resources and Irrigation Sector Management Project (WISMP) APL I Komponen A
Status : 31 Januari 2009
Civil Works (Category 1)
Goods (Category 2)
No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya eqv(US$)
Metode
Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego Penandatanganan Kontrak
Jangka Waktu Kontrak (Hari Kalender) Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13