RENCANA/ RELISASI PENGADAAN TA 2009
*
Unit Kerja
Dinas Bina Marga & Pengairan Kabupaten Bekasi
Status : Januari 2009
No
Kode
Nama Paket
Estimasi Biaya
(Rp)
Estimasi Biaya
eqv(US$)
Pengadaan
Metode
Post/ Prior
Review
Pengumuman
Pengadaan
Pemasukan
Penawaran Eval/ Nego
Penandata-
nganan
Kontrak
Jangka
Waktu
Kontrak
Keterangan:
Permasalahan/
1 2 3 4 5 6 7 8 9 10 11 12 13I
KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING
1
CW 1
Pembuatan Sekretariat WISMP GP3A
108,000,000 12,706
FA
Review
Post
60 hari GP3A Caringin
GP3A Muara
Gembang
II
KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
1
Total Dana Pendamping WISMP
90,000,000
Sub Total Keg Cat 3 (Loan + Pend)
-
-Sub Total Keg Selain Cat 3 (Loan)
108,000,000
12,706
TOTAL KEGIATAN I (Loan + Pend)
108,000,000
12,706
TOTAL KEGIATAN II (GOI-PF/APBD)
90,000,000
-Sub Prject A2 (Category 8)
Water Resources and Irrigation Sector Management Project (WISMP) APL I
Komponen B & C
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
Unit Kerja
Dinas Bina Marga & Pengairan Kabupaten Bogor
Status : Januari 2009
No
Kode
Nama Paket
Estimasi Biaya
(Rp)
Estimasi Biaya
eqv(US$)
Pengadaan
Metode
Post/ Prior
Review
Pengumuman
Pengadaan
Pemasukan
Penawaran Eval/ Nego
Penandata-
nganan
Kontrak
Jangka
Waktu
Kontrak
Keterangan:
Permasalahan/
1 2 3 4 5 6 7 8 9 10 11 12 13I
KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING
1
CW 1
Pembangunan Gd. Sekretariat GP3A Tirta Buana
42,616,000
5,014 Swakelola Post Review
30 hari
2
CW 2
Pembangunan Gd. Sekretariat GP3A Ciunjang Jaya
42,616,000
5,014 Swakelola Post Review
30 hari
3
CW 3
Pembangunan Gd. Sekretariat GP3A Sugih Mukti
42,616,000
5,014 Swakelola Post Review
30 hari
4
CW 4
Pembangunan Gd. Sekretariat GP3A Sodong Saluyu
42,616,000
5,014 Swakelola Post Review
30 hari
5
CW 5
Pembangunan Gd. Sekretariat GP3A Sendung Lestari
42,616,000
5,014 Swakelola Post Review
30 hari
6
CW 6
Pembangunan Gd. Sekretariat GP3A Harum Sari
42,616,000
5,014 Swakelola Post Review
30 hari
7
CW 7
Pembangunan Gd. Sekretariat GP3A Mitra Tani
42,616,000
5,014 Swakelola Post Review
30 hari
8
CW 8
Pembangunan Gd. Sekretariat GP3A Selir Julangga
42,616,000
5,014 Swakelola Post Review
30 hari
9
CW 9
Pembangunan Gd. Sekretariat GP3A Sauyunan
42,616,000
5,014 Swakelola Post Review
30 hari
10
CW 10
Pembangunan Gd. Sekretariat GP3A Marayana Mukti
42,616,000
5,014 Swakelola Post Review
30 hari
11
CW 11
Pembangunan Gd. Sekretariat GP3A Tirta Saluyu
42,616,000
5,014 Swakelola Post Review
30 hari
12
CW 12
Pembangunan Gd. Sekretariat GP3A Wira Bakti
42,616,000
5,014 Swakelola Post Review
30 hari
Pelaksanaan Rehabilitasi Partisipatif DI :
13
CW 11
Ciomas Tonjong
50,000,000 5,882 Swakelola Post Review
Jun-09
Jul-09
Jul-09
Aug-09
30 hari
14
CW 12
Cibeet Cikumpeni
50,000,000 5,882 Swakelola Post Review
Jun-09
Jul-09
Jul-09
Aug-09
30 hari
15
CW 13
Cipangkis Leungsir
50,000,000 5,882 Swakelola Post Review
Jun-09
Jul-09
Jul-09
Aug-09
30 hari
16
CW 14
Cidurian Sodong
50,000,000 5,882 Swakelola Post Review
Jun-09
Jul-09
Jul-09
Aug-09
30 hari
17
CW 15
Cidurian Sendung
50,000,000 5,882 Swakelola Post Review
Jun-09
Jul-09
Jul-09
Aug-09
30 hari
18
CW 16
Cianten Cigatet
50,000,000 5,882 Swakelola Post Review
Jun-09
Jul-09
Jul-09
Aug-09
30 hari
19
CW 17
Cigamea
50,000,000 5,882 Swakelola Post Review
Jun-09
Jul-09
Jul-09
Aug-09
30 hari
20
CW 18
Situ Bala
50,000,000 5,882 Swakelola Post Review
Jun-09
Jul-09
Jul-09
Aug-09
30 hari
21
CW 19
Cigambreng
50,000,000 5,882 Swakelola Post Review
Jun-09
Jul-09
Jul-09
Aug-09
30 hari
22
CW 20
Cimarayana
50,000,000 5,882 Swakelola Post Review
Jun-09
Jul-09
Jul-09
Aug-09
30 hari
II
KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
Sub Total Keg Cat 3 (Loan + Pend)
-
-Sub Total Keg Selain Cat 3 (Loan)
1,011,392,000
118,987
TOTAL KEGIATAN I (Loan + Pend)
1,011,392,000
118,987
TOTAL KEGIATAN II (GOI-PF/APBD)
-
-Sub Prject A2 (Category 8)
Komponen B & C
Page 1 of 2
RENCANA/ RELISASI PENGADAAN TA 2009
*
Unit Kerja Dinas PSDA & Pertambangan Kab. Cianjur Status : Januari 2009 No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya eqv(US$) Pengadaan Post/ Prior ReviewMetode Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego Penandata-nganan
Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING
Pembangunan Gedung Kantor Sekretariat GP3A
1 CW 1 IP3A Tirta Mulya Rezeki DI Cihea 35,000,000 4,118 CDD Post Review Apr-09 60 hari 2 CW 2 IP3A Tri Cahya Banyu DI Cibalagung 35,000,000 4,118 CDD Post Review Apr-09 60 hari 3 CW 3 GP3A Sukatani DI Cisalak/Batu Sahulu 35,000,000 4,118 CDD Post Review Apr-09 60 hari 4 CW 4 GP3A Kayungyun DI Ciraden/Leuwi Leungsir 35,000,000 4,118 CDD Post Review Apr-09 60 hari 5 CW 5 GP3A Mitra Cikundul DI Leuwi Bokor 35,000,000 4,118 CDD Post Review Apr-09 60 hari 6 CW 6 GP3A Sauyunan Cikawung DI Cikawung 35,000,000 4,118 CDD Post Review Apr-09 60 hari 7 CW 7 GP3A Karya Selayu DI Leuwi Sodong 35,000,000 4,118 CDD Post Review Apr-09 60 hari 8 CW 8 GP3A Sauyunan Nagrog DI Nagrog 35,000,000 4,118 CDD Post Review Apr-09 60 hari 9 CW 9 GP3A Tirta Mukti DI Cilumut/Pasir Kerud 35,000,000 4,118 CDD Post Review Apr-09 60 hari 10 CW 10 GP3A Tirta Walatra DI Cihea Gol I 35,000,000 4,118 CDD Post Review Apr-09 60 hari 11 CW 11 GP3A Karya Sejahtera DI Cihea Gol II 35,000,000 4,118 CDD Post Review Apr-09 60 hari 12 CW 12 GP3A Sabanda Sariksa DI Cihea III 35,000,000 4,118 CDD Post Review Apr-09 60 hari 13 CW 13 GP3A Karangluyu DI Ciheulang 35,000,000 4,118 CDD Post Review Apr-09 60 hari 14 CW 14 GP3A Mahi Cai DI Susukan Gede 35,000,000 4,118 CDD Post Review Apr-09 60 hari 15 CS 1 Desain Partisipatif Rehabilitasi Jaringan Irigasi : 366,000,000 43,059 QCBS Prior Kontrak I May-09 Jun-09 Jun-09 Jul-09 150 hari
DI Ciraden LW. Leungsir DI Leuwi Bokor DI Leuwi Sodong DI Nagrog
DI Cilumut / Pasir Kerud
Water Resources and Irrigation Sector Management Project (WISMP) APL I
Komponen B & C
Civil Works (Category 1)
Page 2 of 2
(Rp) eqv(US$) Pengadaan Post/ Prior Review Pengadaan Penawaran Eval/ Nego Kontrak Kontrak Permasalahan/
1 2 3 4 5 6 7 8 9 10 11 12 13
Konstruksi Partisipatif Rehabilitasi jaringan Irigasi :
16 CW 15 GP3A Sukatani DI Cisalak/Batu Sahulu 326,500,000 38,412 CDD Post Review May-09 90 hari 17 CW 16 GP3A Kayungyun DI Ciraden/Leuwi Leungsir 220,000,000 25,882 CDD Post Review May-09 90 hari 18 CW 17 GP3A Mitra Cikundul DI Leuwi Bokor 150,000,000 17,647 CDD Post Review May-09 90 hari 19 CW 18 GP3A Sauyunan Cikawung DI Cikawung 200,000,000 23,529 CDD Post Review May-09 90 hari 20 CW 19 GP3A Karya Selayu DI Leuwi Sodong 100,000,000 11,765 CDD Post Review May-09 90 hari 21 CW 20 GP3A Sauyunan Nagrog DI Nagrog 350,000,000 41,176 CDD Post Review May-09 90 hari 22 CW 21 GP3A Tirta Mukti DI Cilumut/Pasir Kerud 350,000,000 41,176 CDD Post Review May-09 90 hari
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
1 Biaya Operasional & Kegiatan Penunjang 184,750,000 swakelola May-09 June-09 June-09 July-09 90 hari 4 Paket 1 - DI Cianjur Leutik, Kec. Cianjur Karang Tengah 125,000,000 LU May-09 June-09 June-09 July-09 90 hari 5 Paket 2 - DI Ciraden/Cibalu, Kec. Cianjur Karang Tengah 125,000,000 LU May-09 June-09 June-09 July-09 90 hari 6 Paket 3 - DI Gn. Lanjung/Rw Peuti Kec. Cugenang Cianjur 125,000,000 LU May-09 June-09 June-09 July-09 90 hari 7 Paket 4 - DI Cisarua II/Lw Jubleg Kec. Cilaku 153,375,000 LU May-09 June-09 June-09 July-09 90 hari
Sub Total Keg Cat 3 (Loan + Pend) - -Sub Total Keg Selain Cat 3 (Loan) 2,552,500,000 300,294 TOTAL KEGIATAN I (Loan + Pend) 2,552,500,000 300,294 TOTAL KEGIATAN II (GOI-PF/APBD) 713,125,000 -Sub Prject A2 (Category 8)
RENCANA/ RELISASI PENGADAAN TA 2009
*
Unit Kerja Dinas Bina Marga & Pengairan Kabupaten Subang Status : Januari 2009 No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya eqv(US$) PengadaanMetode Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego Penandata-nganan
Kontrak
Jangka Waktu
Kontrak Keterangan: Permasalahan/
1 2 3 4 5 6 7 8 9 10 11 12 13
I
KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING
Pelaksanaan Rehabilitasi & Peningkatan Dengan Metode Partisipatif di D.I?
1 CW 1 Cijuhung (264 ha) 234,000,000 27,529 NCB Prior Kontrak I Apr-09 May-09 May-09 Jun-09 75 hari GP3A Mekar Rahayu (NOL) 2 CW 2 Rancakanding (250 ha) 225,000,000 26,471 NCB Prior Kontrak I Apr-09 May-09 May-09 Jun-09 75 hari GP3A Subur Jaya (NOL) 3 CW 3 Cikalijambe (446 ha) 159,454,000 18,759 SW Post Apr-09 May-09 May-09 Jun-09 75 hari P3A Tirta Mukti
4 CW 4 Cijalupang (268 ha) 218,960,000 25,760 NCB Prior Kontrak I Apr-09 May-09 May-09 Jun-09 75 hari GP3A Karya Mukti Mandiri (NOL)
II
KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
1 Upah & Bahan Material di D.I :
DI. Cibarosole (42 ha) 50,000,000 Kepres Juli 09 Juli 09 Juli 09 Agst 09 60 hari GP3A Citra Jaya DI. Tambak Damai (245 ha) 125,000,000 Kepres Juli 09 Juli 09 Juli 09 Agst 09 60 hari GP3A Waluya DI. Cibitung (115 ha) 67,000,000 Kepres Juli 09 Juli 09 Juli 09 Agst 09 60 hari GP3A Tri Mukti DI. Cikamiri 60,150,000 Kepres Juli 09 Juli 09 Juli 09 Agst 09 60 hari GP3A Mekar Rahayu
Sub Total Keg Cat 3 (Loan + Pend) - -Sub Total Keg Selain Cat 3 (Loan) 837,414,000 98,519 TOTAL KEGIATAN I (Loan + Pend) 837,414,000 98,519 TOTAL KEGIATAN II (GOI-PF/APBD) 302,150,000 -Sub Prject A2 (Category 8)
Water Resources and Irrigation Sector Management Project (WISMP) APL I
Komponen B & C
Unit Kerja Dinas Bina Marga & PSDA Kab. Sukabumi Status : Januari 2009 No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya eqv(US$) PengadaanMetode Post/ Prior Review Pengumuman
Pengadaan
Pemasukan
Penawaran Eval/ Nego
Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING
Pembangunan Gedung Kantor Sekretariat GP3A :
1 CW 1 GP3A palagung 30,000,000 3,529 SW Post Review Mar-09 May-09 May-09 May-09 30 hari 2 CW 2 GP3A Subur Makmur 30,000,000 3,529 SW Post Review Mar-09 May-09 May-09 May-09 30 hari 3 CW 3 GP3A Cinta Mekar 30,000,000 3,529 SW Post Review Mar-09 May-09 May-09 May-09 30 hari
Desain Partisipatif Rehabilitasi Jaringan Irigasi di D.I :
4 CS 1 Lembur Sawah 60 Ha 2,700,000 318 IC Prior Kontrak I May-09 Jun-09 Jun-09 Jul-09 10 hari 5 CS 2 Ciutara 184 Ha 8,280,000 974 IC Prior Kontrak I May-09 Jun-09 Jun-09 Jul-09 20 hari 6 CS 3 Cikakak 200 Ha 9,000,000 1,059 IC Prior Kontrak I May-09 Jun-09 Jun-09 Jul-09 30 hari 7 CS 4 Pangkalan 365 Ha 16,425,000 1,932 IC Prior Kontrak I May-09 Jun-09 Jun-09 Jul-09 40 hari 8 CS 5 Cibodas 200 Ha 9,000,000 1,059 IC Prior Kontrak I May-09 Jun-09 Jun-09 Jul-09 30 hari 9 CS 6 Ciparangan 614 Ha 27,630,000 3,251 IC Prior Kontrak I May-09 Jun-09 Jun-09 Jul-09 50 hari 10 CS 7 Cisalada 632 Ha 28,440,000 3,346 IC Prior Kontrak I May-09 Jun-09 Jun-09 Jul-09 50 hari
Konstruksi Partisipatif Rehabilitasi Jaringan Irigasi di D.I :
11 CW 4 Ciparangan 614 Ha 75,850,000 8,924 CDD Post Review Jun-09 Jul-09 Jul-09 Aug-09 120 hari 12 CW 5 Cicatih 556 Ha 100,200,000 11,788 CDD Post Review Jun-09 Jul-09 Jul-09 Aug-09 120 hari
Konstruksi Partisipatif Jaringan Irigasi :
13 CW 6 P3A Sumber Sari DI Cimulek 43,650,000 5,135 CDD Post Review Apr-09 May-09 May-09 Jun-09 60 hari 14 CW 7 P3A Harapan Subur DI Cibojong BJ Lopang 41,500,000 4,882 CDD Post Review Apr-09 May-09 May-09 Jun-09 60 hari 15 CW 8 P3A Tani Jaya DI Cibening Girang 42,300,000 4,976 CDD Post Review Apr-09 May-09 May-09 Jun-09 60 hari 16 CW 9 P3A Tani Mukti DI Cisukawayana 37,350,000 4,394 CDD Post Review Apr-09 May-09 May-09 Jun-09 60 hari 17 CW 10 P3A Jaya Mukti DI Ciraua II 43,250,000 5,088 CDD Post Review Apr-09 May-09 May-09 Jun-09 60 hari 18 CW 11 P3A Sugih Tani DI Tegal Panjang 40,500,000 4,765 CDD Post Review Apr-09 May-09 May-09 Jun-09 60 hari 19 CW 12 P3A Guna Karya DI Cikolawing II 37,500,000 4,412 CDD Post Review Apr-09 May-09 May-09 Jun-09 60 hari 20 CW 13 P3A Berkah DI Cikupa 35,400,000 4,165 CDD Post Review Apr-09 May-09 May-09 Jun-09 60 hari 21 CW 14 P3A Harum Sari Irigasi Cibodas 38,750,000 4,559 CDD Post Review Apr-09 May-09 May-09 Jun-09 60 hari 22 CW 15 P3A Citra Karya Tirta Bakti 40,250,000 4,735 CDD Post Review Apr-09 May-09 May-09 Jun-09 60 hari Sub Prject A1 (Category 7)
Unit Kerja Dinas Bina Marga & PSDA Kab. Sukabumi Status : Januari 2009 No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya eqv(US$) PengadaanMetode Post/ Prior Review Pengumuman
Pengadaan
Pemasukan
Penawaran Eval/ Nego
Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13
II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
I Belanja Pegawai & Barang & Jasa 360,246,000 II Belanja Modal (Konstruksi)
III Desain Partisipatif Rehabilitasi Jaringan Irigasi di DI :
1 Cimuncang 229 Ha 10,305,000 2 Gegerbitung 220 Ha 9,900,000 3 Muara Cibodas 200 Ha 9,000,000 4 Cipeunduy/Cikawun 200 Ha 9,000,000 5 Cicatih Nyalindung 150 Ha 6,750,000 6 Cisarua Bojong 163 Ha 7,335,000 7 Tarisi 430 Ha 19,350,000 8 Cikurutung 400 Ha 18,000,000 9 Cipanumbangan 150 Ha 6,750,000 10 Cipuspa 162 Ha 7,290,000 11 Warujajar 300 Ha 13,500,000 12 Cikalong 162 Ha 7,290,000 13 Ciasih 324 Ha 14,580,000 14 Ciwirana 188 Ha 8,460,000 IV Konstruksi Partisipatif Rehabilitasi Jaringan Irigasi di DI:
1 Cisalada 632 Ha 50,750,000 2 Cikalong 150 Ha 75,525,000
Sub Total Keg Cat 3 (Loan + Pend) - -Sub Total Keg Selain Cat 3 (Loan) 767,975,000 90,350 TOTAL KEGIATAN I (Loan + Pend) 767,975,000 90,350 TOTAL KEGIATAN II (GOI-PF/APBD) 634,031,000
-Unit Kerja Status : Januari 2009 No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya eqv(US$) PengadaanMetode Post/ Prior Review Pengumuman
Pengadaan
Pemasukan
Penawaran Eval/ Nego
Penandata-nganan Kontrak
Jangka Waktu
Kontrak Keterangan: Permasalahan/
1 2 3 4 5 6 7 8 9 10 11 12 13
I
KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING
II
KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)
Sub Total Keg Cat 3 (Loan + Pend) -
-Sub Total Keg Selain Cat 3 (Loan) -
-TOTAL KEGIATAN I (Loan + Pend) -
-TOTAL KEGIATAN II (GOI-PF/APBD) - 0
Komponen B & C
Goods (Category 2)