TIME AND COST CONTROLLING USING CRITICAL PATH

METHOD (CASE STUDY AT PALUR FLY-OVER SURAKARTA)

A THESIS

Submitted as a Partial Fullfilment of the Requirements

For the completion of Getting the Postgraduate Degree in Civil Engineering

study Program

Arranged by:

Adel Issa Elsosan

S 100130016

POSTGRADUATE PROGRAM

DEPARTMENT OF CIVIL ENGINEERING

UNIVERSITAS MUHAMMADIYAH SURAKARTA

(2)

ii

TIME AND COST CONTROLLING USING CRITICAL PATH

METHOD (CASE STUDY AT PALUR FLY-OVER SURAKARTA)

A THESIS

Submitted as a Partial Fullfilment of the Requirements

For the completion of Getting the Postgraduate Degree in Civil Engineering

study Program

Arranged by:

Adel Issa Elsosan

S 100130016

POSTGRADUATE PROGRAM

DEPARTMENT OF CIVIL ENGINEERING

UNIVERSITAS MUHAMMADIYAH SURAKARTA

(3)
(4)
(5)
(6)
(7)
(8)

vii

ABSTRACT

ABSTRACT-The purpose of this study is to (1.To analyze the remaining work items at month of 14th from the project starts, 2). To analyze the remaining cost items at month of 14th after the project start. And the last is 3). To reschedule and to optimize the time and cost by use Critical Path Method (CPM).

This study will analyze time and cost controlling by using CPM approach on the project. Based on the background of the study, the statements of the problems can be formulated as follows: (1) How is rescheduling in optimization of time on Palur Fly over of Surakarta by using Critical Path Method (CPM)? and (2) How is the implement of the normal and the crash of the cost on Palur flyover in Surakarta by using Critical Path Method (CPM)?. The writer analyzed the fly-over project implementation fly over Palur in Surakarta whether according to the time plan. By rescheduling the plan and make optimization of time and minimizing cost with CPM (Critical Path Method).

Based on the result and discussion, the conclusion of this research as follows: The implementation of the project is not in accordance with the plan, it is too late because of the weather and can be solved by increasing the valve of workers. Based on the rescheduling alternatives can be implemented as the alternative I with 160 days shorter and the rest of cost Rp 32.556.381.150

(9)

viii

ACKNOWLEDGEMENT

Bismillahirrahmaanirrahiim Assalaamu’alaikum wr.wb.

Alhamdulillahirrahmaanirrahiim, praise and gratitude to the most Merciful Allah

Ta’ala, for blessing the writer in finishing this Thesis entitled

TIME AND COST

CONTROLLING USING CRITICAL PATH METHOD (CASE STUDY

AT PALUR FLY-OVER SURAKARTA)

as one of the requirement for getting the Postgraduate Degree in Civil Engineering Program. The researchers do not forget to praise to the messenger, our prophet Muhammad S A W, and his followers.

The writer really realizes that he cannot finish this research because of great attention, motivation, material, and support given by his parents, relatives, beloved ones, friends, and others. In addition, the writer also thanks much to the people who helped him to complete this research paper. Therefore, the writer wants to dedicatee his sincerest gratitude for all them.

The writer would like to express his appreciation to those ones. They are: Nurul Hidayati, ST, MT., Ph.D, as the Head of Magister of Civil Engineering Study. The next is Mohamad Solikin, PhD, as the first consultant for his kindness in guiding, helping, teaching to the writer and also Ir. M. Muh Nursahid, M.M., M.T as the second consultant for his patience in guiding the writer to complete this thesis. With the third examiner Sri Sunarjono, Ph.D from the buttonm of his hearth, the writer would like to devote his everlasting mercy and thanks so much for your time besides precautio.

NO workcan be done perfectly , nor can this research paper. The witer expects that this research paper will become useful for the development of academic study and following research.

(10)

ix

TABLE OF CONTENT

THE TITTLE OF THE RESEARCH ... i

APPROVAL ... iii

NOTE OF ADVISOR I ... iv

NOTE OF ADVISOR II ... v

THESIS STATEMENT OF AUTHENTICITY ... vi

ABSTRACT ... vii

ACKNOWLEDGEMENT... viii

TABLE OF CONTENT ... x

LIST OF TABLES ... xii

LIST OF FIGURES ... xiii

CHAPTER I INTRODUCTION... 1

1.1 Background ... 1

1.2 Problem Statement ... 5

1.3 Research Question ... 5

1.4 Purpose of the Study ... 5

1.5 Scope of the research ... 6

CHAPTER II LITERATURE REVIEW... 7

2.1 Project Management ... 7

2.2 Critical Path Method (CPM) ... 9

2.3 Advantages of using the Critical Path Method... 21

2.4 Disadvantages of using the Critical Path Method ... 23

2.5 The Human Element Project Teams and Decision Making ... 25

2.6 Minimizing Project Completion Time ... 28

2.7 Minimizing Costs ... 30

CHAPTER III METHODOLOGY ... 32

3.1 Type and Research Approach ... 32

(11)

x

3.2.1 Observation ... 33

3.2.2 Interview ... 33

3.3 Location of the Research ... 34

3.4 Method for Data Collection ... 34

3.5 Data Analysis Technique ... 34

3.6 Research Framework ... 36

CHAPTER IV RESULT AND DISCUSSION ... 37

4.1 General ... 37

4.2 Contact Project ... 38

4.3 Budget of Project ... 39

4.4 Analyse the Remaining Works Items ... 44

4.5 Analyse of the Remaining Cost ... 48

4.5.1 Minimizing Cost of Division (6) ... 48

4.5.2 Minimizing Cost of Division (8) ... 49

4.5.3 Minimizing Cost of Division (2) ... 50

4.6 Rescheduling ... 50

4.6.1 Alternative I ... 52

4.6.2 Alternative II ... 53

4.6.3 Alternative III ... 54

4.6.4 Alternative IV ... 54

4.6.5 Alternative V ... 56

4.7 Discussion ... 56

CHAPTER V CONCLUSION AND RECOMMENDATION ... 60

5.1 General... 60

5.2 Contact Project ... 60 APPENDICES

(12)

xi

LIST OF TABLES

Table 4.1 List of the budget project 39

Table 4.2 The Remaining of Works preparatory on Month14th 44 Table 4.3 The Total of Remaining Works n Cost After 13 Month 50

Table 4.4 Curve S of Reschedulling 51

(13)

xii

LIST OF FIGURES

Figure 2.1 Conventional Schedule and CCPM Schedule

With Time Buffers Shown Explicitly 25

Figure 2.2. The Calculation CPM 31

Figure 2.3. Example of CPM 31

Figure 3.1. Research Framework 36

Figure 4.1 Location of Palur Fly-Over, Karanganyar 37

Figure 4.1a Network CPM Alternative I 52

Figure 4.1b Network CPM Alternative I, Normal Day for

Rescheduling 52

Figure 4.2 Network CPM Alternative II 53

Figure 4.3 Network CPM Alternative III 54

Figure 4.4 Network CPM Alternative IV 55

Gambar

Conventional Schedule and CCPM ScheduleFigure 2.1With Time Buffers Shown Explicitly25

Referensi

Dokumen terkait

Rakit komponen yang belum terpasang, sambung kelistrikan dan saluran udara Distribution Station sesuai diagram kelistrikan dan pneumatik yang telah tersedia.. Rancang programnya

Kepada peserta yang merasa keberatan atas penetapan ini, diberikan hak untuk menyampaikan sanggahan-sanggahan mulai tanggal 14 Februari 2013 sampai dengan tanggal

Pelanggaran pertama terhadap peraturan ini akan dihitung sebagai kesalahan, pelanggaran kedua akan diberi sanksi berupa pendiskualifikasian pemain pelanggar hingga

II (Bali Concord II), adopted during the 9 th ASEAN Summit in Bali, Indonesia, on 7 October 2003, which aims to realise the establishment of the ASEAN Community comprising

Nilai LAI rata-rata varietas Atlantik yang lebih besar mengindikasikan varietas ini memiliki luas daun yang lebih besar, sehingga memungkinkan varietas tersebut akan lebih

pengembangan pariwisata 12  jp 3.5 Memahami jenjang karir  dalam organisasi industri  pariwisata 4.5 Mengelompokkan jenjang  karir dalam organisasi  kepariwisataan  6  jp

[r]

[r]