• Tidak ada hasil yang ditemukan

Analisis Penerapan Metode CPM (Critical Path Method) menggunakan Software Microsoft Project pada Proyek Pembangunan Turap/Talud/Bronjong Ruas Jalan Patung Lembuswana-Sebulu 2

N/A
N/A
Protected

Academic year: 2023

Membagikan "Analisis Penerapan Metode CPM (Critical Path Method) menggunakan Software Microsoft Project pada Proyek Pembangunan Turap/Talud/Bronjong Ruas Jalan Patung Lembuswana-Sebulu 2"

Copied!
40
0
0

Teks penuh

(1)

59

LAMPIRAN

Lampiran 1 Tabel Analisa Harga Satuan Pekerjaan

No. Nama Kegiatan Harga Satuan Total Biaya I Pekerjaan Persiapan

1.1 Mobilisasi Rp 179,252,860.96 Rp 179,252,860.96 1.2 Manajemen dan Keselamatan

Lalu Lintas Rp 53,141,000.00 Rp 53,141,000.00 1.2

Pengujian Oksigen Terlarut

(DO) Rp 100,000.00 Rp 300,000.00 1.3 Pengujian Vibrasi Lingkungan Rp 150,000.00 Rp 450,000.00 1.4 Pengujian Tingkat Getaran

Kendaraan Bermotor Rp 350,000.00 Rp 1,050,000.00 1.5 Pengujian Nox Rp 140,000.00 Rp 420,000.00 1.6

Pengujian Karbon dioksida

(CO2) Rp 140,000.00 Rp 420,000.00 1.7 Pengujian Total Partikulat(TSP)-

Debu Rp 165,000.00 Rp 495,000.00 Keselamatan dan Kesehatan

Kerja Rp 43,230,000.00 Rp 43,230,000.00 1.8

Pengeboran, Termasuk SPT dan

Laporan Rp 680,307.69 Rp 20,409,230.77 1.9 Sondir Termasuk Laporan Rp 495,916.67 Rp 14,877,500.00 Manajemen Mutu Rp 51,000,000.00 Rp 51,000,000.00 II Pekerjaan Drainase

2.1

Galian untuk Selokan Drainase

dan Saluran Air Rp 23,629.23 Rp 8,555,435.31 2.2 Saluran Berbentuk U tipe DS 4 Rp 826,959.00 Rp 148,852,620.00 III Pekerjaan Tanah dan Geosintetik

3.1 Galian Biasa Rp 25,315.77 Rp 7,933,202.84 3.2

Galian Perkerasan Beraspal

Tanpa Cold Milling Machine Rp 131,882.20 Rp 3,018,783.56 3.3 Galian Perkerasan Beton Rp 171,112.52 Rp 36,412,744.26 3.4 Timbunan Biasa dari Sumber

Galian Rp 84,964.48 Rp 8,214,365.93 IV Pekerjaan Perkerasan Berbutir Dan Perkerasan Beton Semen

4.1 Lapis Fondasi Kelas A Rp 564,447.32 Rp 9,527,870.76 V Pekerjaan Struktur

5.1 Beton Struktur, fc '35 Mpa Rp 2,151,746.40 Rp 711,582,534.48

5.2 Beton Struktur, fc '30 Mpa Rp 2,073,852.38 Rp 39,299,502.60

5.3 Beton Struktur, fc '20 Mpa Rp 1,885,993.46 Rp 45,263,843.04

5.4 Beton,fc '15 Mpa Rp 1,635,444.50 Rp 35,979,779.00

5.5 Beton,fc '10 Mpa Rp 1,290,692.86 Rp 17,721,212.97

Lanjutan Lampiran 1 Tabel Analisa Harga Satuan Pekerjaan

(2)

No. Nama Kegiatan Harga Satuan Total Biaya 5.6 Baja Tulangan Polos - BjTP 280 Rp 19,321.50 Rp 56,349,222.60 5.7 Baja Tulangan Strip - BjTS420B Rp 20,251.00 Rp1,039,448,795.77 5.8 Anyaman Kawat yang dilas

(Welded Wire Mesh) Rp 23,298.00 Rp 8,689,222.08 5.9

Fondasi Cerucuk, Penyediaan

dan Pemancangan Rp 79,467.14 Rp 112,843,338.80 5.10 Penyedian Tiang Pancang Baja

Diameter 300mm Tebal 9mm Rp 1,746,429.18 Rp1,501,929,094.80 5.11 Pemancangan Tiang Pancang

Baja Diameter 300 mm Rp 307,843.16 Rp 264,745,117.60 5.12

Bronjong dengan kawat yang

dilapisi Galvanis Rp 938,850.00 Rp 176,034,375.00 5.13 Sandaran (Railing) Rp 188,254.69 Rp 11,833,689.81 5.14 Pipa Drainase PVC Diameter

100mm Rp 86,670.83 Rp 7,254,348.47 VI Pekerjaan Harian dan Lain-lain

6.1 Marka Jalan Temoplastik Rp 199,893.10 Rp 5,756,921.28 6.2 Patok Pengarah Rp 166,789.91 Rp 6,338,016.58 Sumber : Dinas Pekerjaan Umum Provinsi Kalimantan

Timur

(3)

Lampiran 2 Time Schedule Rencana Asli

(4)

1234567891011121314151617181920212223IPekerjaan Persiapan1.1MobilisasiLS1.0056179,252,860.96IDR 3.76%0.47%0.47%0.47%0.47%0.47%0.47%0.47%0.47%1.2Manajemen dan Keselamatan Lalu LintasLS1.0016753,141,000.00IDR 1.12%0.05%0.05%0.05%0.05%0.05%0.05%0.05%0.05%0.05%0.05%0.05%0.05%0.05%0.05%0.05%0.05%0.05%0.05%0.05%0.05%0.05%0.05%0.09%1.3Pengujian Oksigen Terlarut (DO)Buah3.0021300,000.00IDR 0.01%0.00%0.00%0.00%1.4Pengujian Vibrasi Lingkungan Buah3.0021450,000.00IDR 0.01%0.00%0.00%0.00%1.5Pengujian Tingkat Getaran Kendaraan BermotorBuah3.00211,050,000.00IDR 0.02%0.01%0.01%0.01%1.6Pengujian NoxBuah3.0021420,000.00IDR 0.01%0.00%0.00%0.00%1.7Pengujian Karbon dioksida (CO2)Buah3.0021420,000.00IDR 0.01%0.00%0.00%0.00%1.8Pengujian Total Partikulat(TSP)-DebuBuah3.0021495,000.00IDR 0.01%0.00%0.00%0.00%1.9Keselamatan dan Kesehatan KerjaLS1.0015343,230,000.00IDR 0.91%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%1.10Pengeboran, Termasuk SPT dan LaporanM130.001420,409,230.77IDR 0.43%0.21%0.21%1.10Sondir Termasuk LaporanM130.001414,877,500.00IDR 0.31%0.16%0.16%1.12Manajemen MutuLS1.0016751,000,000.00IDR 1.07%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.04%0.09%IIPekerjaan Drainase2.1Galian untuk Selokan Drainase dan Saluran AirM3362.07568,555,435.31IDR 0.18%0.02%0.02%0.02%0.02%0.02%0.02%0.02%0.02%2.2Saluran Berbentuk U tipe DS 4M1180.0035148,852,620.00IDR 3.13%0.63%0.63%0.63%0.63%IIIPekerjaan Tanah dan Geosintetik3.1Galian BiasaM3313.37217,933,202.84IDR 0.17%0.06%0.06%0.06%3.2Galian Perkerasan Beraspal Tanpa Cold Milling MachineM322.89213,018,783.56IDR 0.06%0.02%0.02%0.02%3.3Galian Perkerasan BetonM3212.802136,412,744.26IDR 0.76%0.25%0.25%0.25%3.4Timbunan Biasa dari Sumber GalianM396.68358,214,365.93IDR 0.17%0.03%0.03%0.03%0.03%0.03%0.03%IVPekerjaan Perkerasan Berbutir Dan Perkerasan Beton Semen4.1Lapis Fondasi Kelas AM316.88269,905,545.39IDR 0.21%0.06%0.06%0.06%0.06%VPekerjaan Struktur5.1Beton Struktur, fc '35 MpaM3330.7052725,476,267.25IDR 15.24%2.05%2.05%2.05%2.05%2.05%2.05%2.05%0.83%5.2Beton Struktur, fc '30 MpaM318.954939,299,502.60IDR 0.83%0.12%0.12%0.12%0.12%0.12%0.12%0.12%0.12%0.12%0.12%5.3Beton Struktur, fc '20 MpaM324.007045,263,843.04IDR 0.95%0.10%0.10%0.10%0.10%0.10%0.10%0.10%0.10%0.10%0.10%0.10%0.10%5.4Beton,fc '15 MpaM322.005236,682,288.42IDR 0.77%0.10%0.10%0.10%0.10%0.10%0.10%0.10%0.04%5.5Beton,fc '10 MpaM313.735218,067,221.74IDR 0.38%0.05%0.05%0.05%0.05%0.05%0.05%0.05%0.02%0.02%5.6Baja Tulangan Polos - BjTP 280Kg2916.407056,349,222.60IDR 1.18%0.12%0.12%0.12%0.12%0.12%0.12%0.12%0.12%0.12%0.12%5.7Baja Tulangan Strip - BjTS 420BKg51328.27521,059,744,155.89IDR 22.26%3.00%3.00%3.00%3.00%3.00%3.00%3.00%1.61%5.8Anyaman Kawat yang dilas (Welded Wire Mesh)Kg372.96288,689,222.08IDR 0.18%0.05%0.05%0.05%0.05%5.9Fondasi Cerucuk, Penyediaan dan PemancanganM11420.0016120,255,879.55IDR 2.53%1.11%0.48%0.48%5.10Penyedian Tiang Pancang Baja Diameter 300mm Tebal 9mmM1860.00211,576,186,279.15IDR 33.11%11.04%11.04%11.04%5.11Pemancangan Tiang Pancang Baja Diameter 300 mmM1860.0021277,834,435.25IDR 5.84%1.95%1.95%1.95%5.12Bronjong dengan kawat yang dilapisi GalvanisM3187.5028176,034,375.00IDR 3.70%0.92%0.92%0.92%0.92%5.13Sandaran (Railing)M162.861411,833,689.81IDR 0.25%0.12%0.12%5.14Pipa Drainase PVC Diameter 100mmM183.70108,035,301.29IDR 0.17%0.12%0.12%VIPekerjaan Harian dan Lain-lain6.1Marka Jalan TemoplastikM228.80106,376,671.48IDR 0.13%0.09%0.09%6.2Patok PengarahBuah38.00107,020,323.47IDR 0.15%0.10%0.10%4,761,086,967.63IDR 100.00%523,719,566.44IDR PROGRES0.6%0.6%1.0%1.0%0.6%0.6%1.0%0.9%1.6%11.7%11.7%13.6%5.6%9.2%9.2%9.3%7.3%5.8%4.5%2.4%0.8%0.6%0.6%5,284,806,534.06IDR KUMULATIF0.6%1.2%2.2%3.2%3.8%4.4%5.3%6.3%7.8%19.5%31.2%44.7%50.3%59.5%68.7%78.0%85.3%91.1%95.6%98.0%98.8%99.4%100.0% Jumlah Harga Pekerjaan Pajak Pertambahan NilaiJumlah Total Harga Pekerjaan No.216543Nama Kegiatan WAKTU PELAKSANAAN 157 HARI KALENDERBOBOT %HARGA TOTALDURASIVolumeSatuan

Lampiran 3 Time Schedule Rencana Pembanding

(5)

Lampiran 4 Gambar Rencana Proyek

(6)

Lanjutan Lampiran 4 Gambar Rencana Proyek

(7)

Lanjutan Lampiran 4 Gambar Rencana Proyek

(8)

Lanjutan Lampiran 4 Gambar Rencana Proyek

(9)

Lanjutan Lampiran 4 Gambar Rencana Proyek

(10)

Lanjutan Lampiran 4 Gambar Rencana Proyek

(11)

Lanjutan Lampiran 4 Gambar Rencana Proyek

(12)

Lanjutan Lampiran 4 Gambar Rencana Proyek

(13)

Lampiran 5 Dokumen Bukti AHSP (Analisa Harga Satuan Pekerjaan)

(14)

Lanjutan Lampiran 5 Dokumen Bukti AHSP (Analisa Harga Satuan Pekerjaan)

(15)

Lanjutan Lampiran 5 Dokumen Bukti AHSP (Analisa Harga Satuan Pekerjaan)

(16)

Lanjutan Lampiran 5 Dokumen Bukti AHSP (Analisa Harga Satuan Pekerjaan)

(17)

Lanjutan Lampiran 5 Dokumen Bukti AHSP (Analisa Harga Satuan Pekerjaan)

(18)

Lanjutan Lampiran 5 Dokumen Bukti AHSP (Analisa Harga Satuan Pekerjaan)

(19)

Lanjutan Lampiran 5 Dokumen Bukti AHSP (Analisa Harga Satuan Pekerjaan)

(20)

Lanjutan Lampiran 5 Dokumen Bukti AHSP (Analisa Harga Satuan Pekerjaan)

(21)

Lanjutan Lampiran 5 Dokumen Bukti AHSP (Analisa Harga Satuan Pekerjaan)

(22)

Lanjutan Lampiran 5 Dokumen Bukti AHSP (Analisa Harga Satuan Pekerjaan)

(23)

Lanjutan Lampiran 5 Dokumen Bukti AHSP (Analisa Harga Satuan Pekerjaan)

(24)

Lanjutan Lampiran 5 Dokumen Bukti AHSP (Analisa Harga Satuan Pekerjaan)

(25)

Lanjutan Lampiran 5 Dokumen Bukti AHSP (Analisa Harga Satuan Pekerjaan)

(26)

Lanjutan Lampiran 5 Dokumen Bukti AHSP (Analisa Harga Satuan Pekerjaan)

(27)

Lanjutan Lampiran 5 Dokumen Bukti AHSP (Analisa Harga Satuan Pekerjaan)

(28)

Lanjutan Lampiran 5 Dokumen Bukti AHSP (Analisa Harga Satuan Pekerjaan)

(29)

Lanjutan Lampiran 5 Dokumen Bukti AHSP (Analisa Harga Satuan Pekerjaan)

(30)

Lanjutan Lampiran 5 Dokumen Bukti AHSP (Analisa Harga Satuan Pekerjaan)

(31)

Lanjutan Lampiran 5 Dokumen Bukti AHSP (Analisa Harga Satuan Pekerjaan)

(32)

Lanjutan Lampiran 5 Dokumen Bukti AHSP (Analisa Harga Satuan Pekerjaan)

(33)

Lanjutan Lampiran 5 Dokumen Bukti AHSP (Analisa Harga Satuan Pekerjaan)

(34)

Lanjutan Lampiran 5 Dokumen Bukti AHSP (Analisa Harga Satuan Pekerjaan)

(35)

Lampiran 6 Surat Permohonan Pengambilan Data

(36)
(37)

Lampiran 7 Lembar Konsultasi

(38)

Lanjutan Lampiran 7 Lembar Konsultasi

(39)
(40)

Referensi

Dokumen terkait

Metode yang digunakan untuk mengestimasi biaya konstruksi antara lain analisa harga satuan pekerjaan, namun pada umumnya dalam perhitungan anggaran biaya

Selain itu nilai SL dapat bernilai positif jika semua pekerjaan yang berakhir di titik i atau j selesai lebih awal dari waktu paling lambat dari waktu tang diperbolehkan

Analisa harga satuan pekerjaan merupakan analisa material, upah, tenaga kerja, dan peralatan untuk membuat suatu satuan pekerjaan tertentu yang diatur dalam analisa SNI,

Untuk meningkatkan kualitas perencanaan dan pengendalian dalam sebuah proyek digunakan suatu metode Critical Path Method CPM dengan program bantu software microsoft project, Hal ini

19 Lampiran 5 - Analisa Harga Satuan Pekerjaan Proyek Pembangunan Gedung Kantor Dinas Perhubungan Provinsi Jawa Timur .... 55 Lampiran 10 – Perhitungan Biaya Tambahan Tenaga Kerja