1 Mechanical Completion (White Tag) 83 days 25/09/24 16/12/24 25/09/24 NA
2 Mechanical Completion Blending (White
Tag) 52 days 25/09/24 15/11/24 25/09/24 15/11/24 454
77 Mechanical Completion Clinker (White Tag) 25 days 23/10/24 16/11/24 23/10/24 16/11/24 326FS-1 day
128 Mechanical Completion Cement Silo #1
(White Tag) 50 days 22/10/24 10/12/24 22/10/24 NA 381FF+1
day,395FS-1 day,396FS-1 day,397FS-1 day,398FS-1
187 Mechanical Completion Cement Silo #2
(White Tag) 54 days 22/10/24 14/12/24 22/10/24 NA 426FS-1
day,427FS-1 day,428FS-1 day,429FS-1 day,430FS-1
226 Mechanical Completion Tripper & Tube
Conveyor (White Tag) 46 days 1/11/24 16/12/24 1/11/24 NA
227 Finish Utomodeck 44 days 1/11/24 14/12/24 1/11/24 NA 435
228 Finish Rubber Curtain 10 days 6/12/24 15/12/24 NA NA 436
229 Masa kerja Programmer Siemens & ABB 7 days 10/12/24 16/12/24 NA NA
230 641-TB01 14 days 30/11/24 13/12/24 30/11/24 NA 274FF
231 Mechanical Terinstall 1 day 30/11/24 30/11/24 30/11/24 30/11/24 232,233
232 Elins Install & Merger test 12 days 1/12/24 12/12/24 1/12/24 NA 231
233 Dokumen Dossier 13 days 1/12/24 13/12/24 NA NA 231
234 641-MS01 14 days 30/11/24 13/12/24 30/11/24 NA 274FF
235 Mechanical Terinstall 1 day 30/11/24 30/11/24 30/11/24 30/11/24 236,237
236 Elins Install & Merger test 12 days 1/12/24 12/12/24 NA NA 235
237 Dokumen Dossier 13 days 1/12/24 13/12/24 NA NA 235
238 641-BW01 14 days 30/11/24 13/12/24 30/11/24 NA 274FF
14/12
0% 14/12
0% 16/12
30/11
12/12 13/12
30/11
12/12 13/12
S S S S
239 Mechanical Terinstall 1 day 30/11/24 30/11/24 30/11/24 30/11/24 240,241
240 Elins Install & Merger test 12 days 1/12/24 12/12/24 NA NA 239
241 Dokumen Dossier 13 days 1/12/24 13/12/24 NA NA 239
242 641-VS01 14 days 30/11/24 13/12/24 30/11/24 NA 274FF
243 Mechanical Terinstall 1 day 30/11/24 30/11/24 30/11/24 30/11/24 244,245
244 Elins Install & Merger test 12 days 1/12/24 12/12/24 NA NA 243
245 Dokumen Dossier 13 days 1/12/24 13/12/24 NA NA 243
246 641-BC01 14 days 30/11/24 13/12/24 30/11/24 NA 274FF
247 Mechanical Terinstall 1 day 30/11/24 30/11/24 30/11/24 30/11/24 248,249
248 Elins Install & Merger test 12 days 1/12/24 12/12/24 NA NA 247
249 Dokumen Dossier 13 days 1/12/24 13/12/24 NA NA 247
250 641-BW02 14 days 30/11/24 13/12/24 30/11/24 NA 274FF
251 Mechanical Terinstall 1 day 30/11/24 30/11/24 30/11/24 30/11/24 252,253
252 Elins Install & Merger test 12 days 1/12/24 12/12/24 NA NA 251
253 Dokumen Dossier 13 days 1/12/24 13/12/24 NA NA 251
254 641-BF07 14 days 30/11/24 13/12/24 30/11/24 NA 274FF
255 Mechanical Terinstall 1 day 30/11/24 30/11/24 30/11/24 30/11/24 256,257
256 Elins Install & Merger test 12 days 1/12/24 12/12/24 NA NA 255
257 Dokumen Dossier 13 days 1/12/24 13/12/24 NA NA 255
258 641-RF07 14 days 30/11/24 13/12/24 30/11/24 NA 274FF
259 Mechanical Terinstall 1 day 30/11/24 30/11/24 30/11/24 30/11/24 260,261
260 Elins Install & Merger test 12 days 1/12/24 12/12/24 NA NA 259
30/11
12/12 13/12
30/11
12/12 13/12
30/11
12/12 13/12
30/11
12/12 13/12
30/11
12/12 13/12
30/11
12/12
S S S S
261 Dokumen Dossier 13 days 1/12/24 13/12/24 NA NA 259
262 641-FN07 14 days 30/11/24 13/12/24 30/11/24 NA 274FF
263 Mechanical Terinstall 1 day 30/11/24 30/11/24 30/11/24 30/11/24 264,265
264 Elins Install & Merger test 12 days 1/12/24 12/12/24 NA NA 263
265 Dokumen Dossier 13 days 1/12/24 13/12/24 NA NA 263
266 641-TR01 14 days 30/11/24 13/12/24 30/11/24 NA 274FF
267 Mechanical Terinstall 1 day 30/11/24 30/11/24 30/11/24 30/11/24 268,269
268 Elins Install & Merger test 12 days 1/12/24 12/12/24 NA NA 267
269 Dokumen Dossier 13 days 1/12/24 13/12/24 NA NA 267
270 641-EH01 14 days 30/11/24 13/12/24 30/11/24 NA
271 Mechanical Terinstall 1 day 30/11/24 30/11/24 30/11/24 30/11/24 272,273
272 Elins Install & Merger test 12 days 1/12/24 12/12/24 NA NA 271
273 Dokumen Dossier 13 days 1/12/24 13/12/24 NA NA 271
274 Sinkronisasi dengan Panel Siemens 4 days 10/12/24 13/12/24 NA NA 230FF,234FF,238FF,242FF,246FF,250FF,254FF,258FF,262FF,266FF438,439,440,441,442,443,444,445,446,447,450
275 Mechanical Completion Shiploader (White
Tag) 41 days 1/11/24 11/12/24 1/11/24 NA 450
276 Mechanical Terinstall 1 day 1/11/24 1/11/24 1/11/24 1/11/24
277 641-CG01 1 day 1/11/24 1/11/24 1/11/24 1/11/24
278 641-SC01 1 day 1/11/24 1/11/24 1/11/24 1/11/24
279 641-SC02 1 day 1/11/24 1/11/24 1/11/24 1/11/24
280 641-BF08 1 day 1/11/24 1/11/24 1/11/24 1/11/24
281 641-FN08 1 day 1/11/24 1/11/24 1/11/24 1/11/24
13/12
30/11
12/12 13/12
30/11
12/12 13/12
30/11
12/12 13/12
0% 13/12
S S S S
282 641-RF08 1 day 1/11/24 1/11/24 1/11/24 1/11/24
283 641-BF09 1 day 1/11/24 1/11/24 1/11/24 1/11/24
284 641-FN09 1 day 1/11/24 1/11/24 1/11/24 1/11/24
285 641-LA02 1 day 1/11/24 1/11/24 1/11/24 1/11/24
286 Elins Install & Merger test 7 days 5/12/24 11/12/24 5/12/24 NA
287 Dokumen Dossier 7 days 5/12/24 11/12/24 5/12/24 NA
288 Individual Test (Blue Tag) 65 days 15/10/24 18/12/24 15/10/24 NA
289 Individual test (Blue Tag) Blending 61 days 15/10/24 14/12/24 15/10/24 NA 453
290 D31-AY09 1 day 15/10/24 15/10/24 15/10/24 15/10/24
291 D31-AY10 1 day 15/10/24 15/10/24 15/10/24 15/10/24
292 D31-CX09 1 day 15/10/24 15/10/24 15/10/24 15/10/24
293 D31-CX10 1 day 15/10/24 15/10/24 15/10/24 15/10/24
294 431-PF02 1 day 19/10/24 19/10/24 19/10/24 19/10/24
295 431-PG04 1 day 19/10/24 19/10/24 19/10/24 19/10/24
296 391-DB11 1 day 22/10/24 22/10/24 22/10/24 22/10/24
297 391-FN05 1 day 22/10/24 22/10/24 22/10/24 22/10/24
298 391-RF04 1 day 22/10/24 22/10/24 22/10/24 22/10/24
299 411-BL05 1 day 24/10/24 24/10/24 24/10/24 24/10/24
300 411-BL06 1 day 24/10/24 24/10/24 24/10/24 24/10/24
301 411-BL07 1 day 24/10/24 24/10/24 24/10/24 24/10/24
302 431-FA04 1 day 24/10/24 24/10/24 24/10/24 24/10/24
303 391-FA07 1 day 9/11/24 9/11/24 9/11/24 9/11/24
0% 11/12
0% 11/12
S S S S
304 391-FA08 1 day 9/11/24 9/11/24 9/11/24 9/11/24
305 431-FA05 1 day 9/11/24 9/11/24 9/11/24 9/11/24
306 391-GT01 1 day 12/11/24 12/11/24 12/11/24 12/11/24
307 391-BF04 1 day 16/11/24 16/11/24 16/11/24 16/11/24
308 431-BF03 1 day 16/11/24 16/11/24 16/11/24 16/11/24
309 431-BF04 1 day 15/11/24 15/11/24 15/11/24 15/11/24
310 431-FN03 1 day 15/11/24 15/11/24 15/11/24 15/11/24
311 431-FN04 1 day 15/11/24 15/11/24 15/11/24 15/11/24
312 431-RF03 1 day 15/11/24 15/11/24 15/11/24 15/11/24
313 431-RF04 1 day 15/11/24 15/11/24 15/11/24 15/11/24
314 411-VU22 1 day 18/11/24 18/11/24 18/11/24 18/11/24
315 431-PG03 1 day 21/11/24 21/11/24 21/11/24 21/11/24
316 431-SM01 1 day 15/11/24 15/11/24 15/11/24 15/11/24
317 411-FA23 1 day 5/12/24 5/12/24 5/12/24 5/12/24
318 411-PG08 1 day 30/11/24 30/11/24 30/11/24 30/11/24
319 411-PG09 1 day 30/11/24 30/11/24 30/11/24 30/11/24
320 411-PG10 1 day 30/11/24 30/11/24 30/11/24 30/11/24
321 411-PG11 1 day 30/11/24 30/11/24 30/11/24 30/11/24
322 411-PG12 1 day 30/11/24 30/11/24 30/11/24 30/11/24
323 411-PG13 1 day 30/11/24 30/11/24 30/11/24 30/11/24
324 411-PG14 1 day 30/11/24 30/11/24 30/11/24 30/11/24
325 391-EH01 1 day 14/12/24 14/12/24 NA NA
100% 5/12 30/11
30/11 30/11 30/11 30/11 30/11 30/11
0% 14/12
S S S S
326 Individual Test Clinker 32 days 7/11/24 8/12/24 7/11/24 8/12/24 77FS-1 day 457FS-1 day,458FS-1 day
327 511-DF09 1 day 7/11/24 7/11/24 7/11/24 7/11/24
328 511-DF10 1 day 7/11/24 7/11/24 7/11/24 7/11/24
329 511-DF11 1 day 7/11/24 7/11/24 7/11/24 7/11/24
330 511-DF12 1 day 7/11/24 7/11/24 7/11/24 7/11/24
331 511-DF13 1 day 7/11/24 7/11/24 7/11/24 7/11/24
332 511-DF14 1 day 7/11/24 7/11/24 7/11/24 7/11/24
333 511-DF15 1 day 7/11/24 7/11/24 7/11/24 7/11/24
334 511-DF16 1 day 7/11/24 7/11/24 7/11/24 7/11/24
335 511-PN04 1 day 7/11/24 7/11/24 7/11/24 7/11/24
336 511-PN05 1 day 7/11/24 7/11/24 7/11/24 7/11/24
337 491-AC03 1 day 10/11/24 10/11/24 10/11/24 10/11/24
338 491-AC04 1 day 10/11/24 10/11/24 10/11/24 10/11/24
339 491-MW01 1 day 11/11/24 11/11/24 11/11/24 11/11/24
340 491-FV03 1 day 16/11/24 16/11/24 16/11/24 16/11/24
341 491-FV04 1 day 16/11/24 16/11/24 16/11/24 16/11/24
342 491-SC03 1 day 16/11/24 16/11/24 16/11/24 16/11/24
343 511-PN06 1 day 17/11/24 17/11/24 17/11/24 17/11/24
344 511-SX05 1 day 17/11/24 17/11/24 17/11/24 17/11/24
345 511-FN06 1 day 18/11/24 18/11/24 18/11/24 18/11/24
346 511-FN08 1 day 18/11/24 18/11/24 18/11/24 18/11/24
347 491-SX03 1 day 18/11/24 18/11/24 18/11/24 18/11/24
S S S S
348 511-SX03 1 day 18/11/24 18/11/24 18/11/24 18/11/24
349 511-SX04 1 day 18/11/24 18/11/24 18/11/24 18/11/24
350 491-SX02 1 day 19/11/24 19/11/24 19/11/24 19/11/24
351 491-FN03 1 day 19/11/24 19/11/24 19/11/24 19/11/24
352 511-RF01 1 day 20/11/24 20/11/24 20/11/24 20/11/24
353 511-RF03 1 day 20/11/24 20/11/24 20/11/24 20/11/24
354 511-RF02 1 day 21/11/24 21/11/24 21/11/24 21/11/24
355 491-BF03 1 day 8/12/24 8/12/24 8/12/24 8/12/24
356 491-BF04 1 day 5/12/24 5/12/24 5/12/24 5/12/24
357 491-EH02 1 day 5/12/24 5/12/24 5/12/24 5/12/24
358 491-FN04 1 day 5/12/24 5/12/24 5/12/24 5/12/24
359 511-BF06 1 day 5/12/24 5/12/24 5/12/24 5/12/24
360 511-BF07 1 day 5/12/24 5/12/24 5/12/24 5/12/24
361 511-BF08 1 day 5/12/24 5/12/24 5/12/24 5/12/24
362 511-FN07 1 day 23/11/24 23/11/24 23/11/24 23/11/24
363 511-PN03 Extended 1 day 5/12/24 5/12/24 5/12/24 5/12/24
364 Cement Silo 8 days 8/12/24 15/12/24 NA NA
365 Individual test (Blue Tag) Cement Silo #1 4 days 8/12/24 11/12/24 NA NA 460,462,461,465,466
366 591-BF06 2 days 8/12/24 9/12/24 NA NA
367 591-RF03 2 days 8/12/24 9/12/24 NA NA
368 591-FN06 2 days 8/12/24 9/12/24 NA NA 369
100% 8/12 100% 5/12
100% 5/12 100% 5/12 100% 5/12 100% 5/12 100% 5/12
100% 5/12
0% 9/12
0% 9/12
0% 9/12
S S S S
369 591-GT04 2 days 10/12/24 11/12/24 NA NA 368
370 591-FA07.1 2 days 8/12/24 9/12/24 NA NA
371 591-FA07.2 2 days 8/12/24 9/12/24 NA NA 372,373
372 591-SM02 2 days 10/12/24 11/12/24 NA NA 371
373 591-BE02 2 days 10/12/24 11/12/24 NA NA 371
374 591-BF07 2 days 8/12/24 9/12/24 NA NA
375 591-RF04 2 days 8/12/24 9/12/24 NA NA
376 591-FN07 2 days 8/12/24 9/12/24 NA NA
377 591-BF08 2 days 8/12/24 9/12/24 NA NA
378 591-RF05 2 days 8/12/24 9/12/24 NA NA
379 591-FN08 2 days 8/12/24 9/12/24 NA NA 380,382,383,384
380 591-GT05 2 days 10/12/24 11/12/24 NA NA 379
381 591-EH02 (Electric Hoist) 2 days 10/12/24 11/12/24 NA NA 128FF+1 day
382 61F-BL01 2 days 10/12/24 11/12/24 NA NA 379
383 61F-BL02 2 days 10/12/24 11/12/24 NA NA 379
384 61F-BL03 2 days 10/12/24 11/12/24 NA NA 379
385 641-PG01.1 2 days 8/12/24 9/12/24 NA NA
386 641-PG01.2 2 days 8/12/24 9/12/24 NA NA
387 641-PG02.1 2 days 8/12/24 9/12/24 NA NA
388 641-PG02.2 2 days 8/12/24 9/12/24 NA NA
389 641-FA01 2 days 8/12/24 9/12/24 NA NA
390 641-BF01 2 days 8/12/24 9/12/24 NA NA
0% 11/12
0% 9/12
0% 9/12
0% 11/12
0% 11/12
0% 9/12
0% 9/12
0% 9/12
0% 9/12
0% 9/12
0% 9/12
0% 11/12
0% 11/12
0% 11/12
0% 11/12
0% 11/12
0% 9/12
0% 9/12
0% 9/12
0% 9/12
0% 9/12
0% 9/12
S S S S
391 641-FN01 2 days 8/12/24 9/12/24 NA NA
392 641-RF01 2 days 8/12/24 9/12/24 NA NA
393 61F-PG01.1 2 days 8/12/24 9/12/24 NA NA
394 61F-PG01.2 2 days 8/12/24 9/12/24 NA NA
395 62F-VS01 2 days 10/12/24 11/12/24 NA NA 128FS-1 day
396 62F-FA01 2 days 10/12/24 11/12/24 NA NA 128FS-1 day
397 62F-BF01 2 days 10/12/24 11/12/24 NA NA 128FS-1 day
398 62F-FN01 2 days 10/12/24 11/12/24 NA NA 128FS-1 day
399 62F-RF01 2 days 10/12/24 11/12/24 NA NA 128FS-1 day
400 62F-LA01 2 days 10/12/24 11/12/24 NA NA 128FS-1 day
401 62F-WB01 2 days 10/12/24 11/12/24 NA NA 128FS-1 day
402 D33-CX04 2 days 10/12/24 11/12/24 NA NA 128FS-1 day
403 D33-CX05 2 days 10/12/24 11/12/24 NA NA 128FS-1 day
404 D33-AY04 2 days 10/12/24 11/12/24 NA NA 128FS-1 day
405 D33-AY05 2 days 10/12/24 11/12/24 NA NA 128FS-1 day
406 Individual test (Blue Tag) Cement Silo #2 8 days 8/12/24 15/12/24 NA NA 464
407 591-BF09 2 days 8/12/24 9/12/24 NA NA
408 591-RF06 2 days 8/12/24 9/12/24 NA NA
409 591-FN09 2 days 8/12/24 9/12/24 NA NA
410 591-FA08.1 2 days 8/12/24 9/12/24 NA NA
411 591-FA08.2 2 days 8/12/24 9/12/24 NA NA 412,413,414,415
0% 9/12
0% 9/12
0% 9/12
0% 9/12
0% 11/12
0% 11/12
0% 11/12
0% 11/12
0% 11/12
0% 11/12
0% 11/12
0% 11/12
0% 11/12
0% 11/12
0% 11/12
0% 9/12
0% 9/12
0% 9/12
0% 9/12
0% 9/12
S S S S
412 591-EH03 2 days 10/12/24 11/12/24 NA NA 411
413 61G-BL01 2 days 10/12/24 11/12/24 NA NA 411
414 61G-BL02 2 days 10/12/24 11/12/24 NA NA 411
415 61G-BL03 2 days 10/12/24 11/12/24 NA NA 411
416 641-PG03.1 2 days 8/12/24 9/12/24 NA NA
417 641-PG03.2 2 days 8/12/24 9/12/24 NA NA
418 641-PG04.1 2 days 8/12/24 9/12/24 NA NA
419 641-PG04.2 2 days 8/12/24 9/12/24 NA NA
420 641-FA02 2 days 8/12/24 9/12/24 NA NA
421 641-BF02 2 days 8/12/24 9/12/24 NA NA
422 641-FN02 2 days 8/12/24 9/12/24 NA NA
423 641-RF02 2 days 8/12/24 9/12/24 NA NA
424 61G-PG01.1 2 days 8/12/24 9/12/24 NA NA
425 61G-PG01.2 2 days 8/12/24 9/12/24 NA NA
426 62G-VS01 2 days 14/12/24 15/12/24 NA NA 187FS-1 day
427 62G-FA01 2 days 14/12/24 15/12/24 NA NA 187FS-1 day
428 62G-BF01 2 days 14/12/24 15/12/24 NA NA 187FS-1 day
429 62G-FN01 2 days 14/12/24 15/12/24 NA NA 187FS-1 day
430 62G-RF01 2 days 14/12/24 15/12/24 NA NA 187FS-1 day
431 62G-LA01 2 days 14/12/24 15/12/24 NA NA 187FS-1 day
432 62G-WB01 2 days 14/12/24 15/12/24 NA NA 187FS-1 day
0% 11/12
0% 11/12
0% 11/12
0% 11/12
0% 9/12
0% 9/12
0% 9/12
0% 9/12
0% 9/12
0% 9/12
0% 9/12
0% 9/12
0% 9/12
0% 9/12
0% 15/12
0% 15/12
0% 15/12
0% 15/12
0% 15/12
0% 15/12
0% 15/12
S S S S
433 Individual test (Blue Tag) Tripper & Tube
Conveyor 5 days 14/12/24 18/12/24 NA NA 468SS
434 Test Uji Kebocoran 2 days 15/12/24 16/12/24 NA NA
435 Pengujian kebocoran atap tripper
building 1 day 15/12/24 15/12/24 NA NA 227 437,448
436 Pengujian kebocoran rubber curtain 1 day 16/12/24 16/12/24 NA NA 228
437 Pengujian kebocoran shiding di gallery
7 1 day 16/12/24 16/12/24 NA NA 435
438 641-TB01 5 days 14/12/24 18/12/24 NA NA 274
439 641-MS01 5 days 14/12/24 18/12/24 NA NA 274
440 641-BW01 5 days 14/12/24 18/12/24 NA NA 274
441 641-VS01 5 days 14/12/24 18/12/24 NA NA 274
442 641-BC01 5 days 14/12/24 18/12/24 NA NA 274
443 641-BW02 5 days 14/12/24 18/12/24 NA NA 274
444 641-BF07 5 days 14/12/24 18/12/24 NA NA 274
445 641-RF07 5 days 14/12/24 18/12/24 NA NA 274
446 641-FN07 5 days 14/12/24 18/12/24 NA NA 274
447 641-TR01 5 days 14/12/24 18/12/24 NA NA 274
448 641-EH01 2 days 16/12/24 17/12/24 NA NA 435
449 Individual test (Blue Tag) Shiploader 2 days 14/12/24 15/12/24 NA NA 471
450 62G-WB01 2 days 14/12/24 15/12/24 NA NA 275,274
451 Group Test (Red Tag) 19 days 3/12/24 21/12/24 3/12/24 NA
0% 15/12
0% 16/12 0% 16/12
0% 18/12
0% 18/12
0% 18/12
0% 18/12
0% 18/12
0% 18/12
0% 18/12
0% 18/12
0% 18/12
0% 18/12
0% 17/12
0% 15/12
S S S S
453 Group Test Blending 391 6 days 3/12/24 8/12/24 3/12/24 8/12/24 289
454 Group Test Blending 411, 431FA04,
411FA23, 431PF02 2 days 3/12/24 4/12/24 3/12/24 4/12/24 2
455 Group Test Blending 431 0 days 3/12/24 3/12/24 3/12/24 3/12/24
456 Clinker 7 days 3/12/24 9/12/24 3/12/24 9/12/24 476FS-1 day
457 Group Test Clinker 491 2 days 3/12/24 9/12/24 3/12/24 9/12/24 326FS-1 day
458 Group Test Clinker 511 2 days 3/12/24 9/12/24 3/12/24 9/12/24 326FS-1 day
459 Cement Silo 1 2 days 12/12/24 13/12/24 NA NA 478
460 Group Test Cement Silo 591 (Silo 1) 2 days 12/12/24 13/12/24 NA NA 365
461 Group 61-F & 641 2 days 12/12/24 13/12/24 NA NA 365
462 Group 62-F & 641 2 days 12/12/24 13/12/24 NA NA 365
463 Cement Silo 2 6 days 12/12/24 17/12/24 NA NA
464 Group Test Cement Silo 591 (Silo 2) 2 days 16/12/24 17/12/24 NA NA 406
465 Group 61-G & 641 3 days 12/12/24 14/12/24 NA NA 365
466 Group 62-G & 641 3 days 12/12/24 14/12/24 NA NA 365
467 Tube Conveyor 8 days 14/12/24 21/12/24 NA NA 486
468 Group Test Cement Transport 5 days 14/12/24 18/12/24 NA NA 433SS 469
469 Pasang Siding Tube Conveyor 3 days 19/12/24 21/12/24 NA NA 468
470 Shiploader 2 days 16/12/24 17/12/24 NA NA 488
471 Group Test Cement Loading 2 days 16/12/24 17/12/24 NA NA 449
472 Commissioning 17 days 8/12/24 24/12/24 8/12/24 NA
473 Blending 2 days 8/12/24 9/12/24 8/12/24 NA
100% 8/12
100% 4/12
100% 9/12
100% 9/12
0% 13/12
0% 13/12
0% 13/12
0% 17/12
0% 14/12
0% 14/12
0% 18/12
0% 21/12
0% 17/12
S S S S
474 Pengisian Blending Silo phase 1 2 days 8/12/24 9/12/24 8/12/24 NA 452FS-1 day
475 Clinker 2 days 9/12/24 10/12/24 NA NA
476 Pengisian Clinker Silo phase 1 2 days 9/12/24 10/12/24 NA NA 456FS-1 day
477 Cement silo 1 10 days 14/12/24 23/12/24 NA NA
478 Pengisian semen silo 1 dari Cement Mill 2 days 14/12/24 15/12/24 NA NA 459 479
479 Pengendapan silo 1 1 day 16/12/24 16/12/24 NA NA 478 483,480
480 Pengisian silo 1 sampai penuh 2 days 17/12/24 18/12/24 NA NA 479 484,486
481 pengeluaran silo 1 ke kapal 2 days 22/12/24 23/12/24 NA NA 486FF
482 Cement silo 2 5 days 17/12/24 21/12/24 NA NA
483 Transfer sement dari silo 1 ke silo 2 (Bulk
Truck) 3 days 17/12/24 19/12/24 NA NA 479
484 Pengisian silo 2 sampai penuh 3 days 19/12/24 21/12/24 NA NA 480 486
485 Cement Transport to Shiploader 3 days 22/12/24 24/12/24 NA NA 488SS
486 Commissioning pengeluaran silo 1 ke
kapal 2 days 22/12/24 23/12/24 NA NA 480,484,467487,481FF
487 Commissioning pengeluaran silo 2 ke
kapal 1 day 24/12/24 24/12/24 NA NA 486
488 Cement Loading to Export 3 days 22/12/24 24/12/24 NA NA 470,485SS
0% 9/12
0% 10/12
0% 15/12
0% 16/12
0% 18/12
0% 23/12
0% 19/12
0% 21/12
0% 23/12
0% 24/12
0% 24/12
S S S S