HMSI H&S

Job safety environment analysis

PROJECT:

MELAK MINING PROJECT

LOCATION OF WORK:

ALL PIT

Disusun Oleh:

Raihan Aditya Firjatullah Diperiksa Oleh:

Akhmad Zaki Yamani Disetujui Oleh:

Rachmat Hidayatullah

DATE: 10/09/2019 PAGE NO 1 OF 4 JOB DESCRIPTION:

PENGEBORAN DI AREA FREEFACE / DRILLING IN THE FREEFACE AREA

JSA NO.

HMSI/JSEA/10/II/2019

New

Revised

SEQUENCE OF BASIC JOB STEPS POTENTIAL HAZARDS RECOMMENDED ACTION OR PROCEDURE WHO Break the job down into steps. Each of

the steps should accomplish some major task and be logical.

Identify the hazards associated with each step. Examine each to find possibilities that could lead to an accident.

Using the first two columns as a guide, decide what actions are necessary to eliminate or minimise the hazards that could lead to an accident, injury or occupational illness.

1. Persiapan Kerja / Work

Preparation 1.1. Mesin Hidup / Engine

start 1.1.1. Sumber energy sudah posisi ON / enery source

is on position Operator

1.1.2. Tekan tombol bypass sebelum menghidupkan mesin / press the bypass button before turning on the engine

Operator

1.1.3. Operator kompeten simper F aktif. / competent

operator simper F active Pengawas / Supervisior

1.1.4. Operator fit dan bugar untuk melakukan pekerjaan ( mengisi jumlah jam tidur) / operator fit for doing work (fill in the number of hopurs of sleep)

Pengawas / Supervisior

2. Travel 2.1. Interaksi dengan unit lain /

interaction with other units 2.1.1. Komunikasi dua arah melalui radio dan copy

darat./ two way communication and in person Operator

2019-02 Page 1 of 4

(2)

HMSI H&S

PROJECT: JOB DESCRIPTION: PAGE 2 OF 4

SEQUENCE OF BASIC JOB STEPS POTENTIAL HAZARDS RECOMMENDED ACTION OR PROCEDURE WHO Break the job down into steps. Each of

the steps should accomplish some major task and be logical.

Identify the hazards associated with each step. Examine each to find possibilities that could lead to an accident.

Using the first two columns as a guide, decide what actions are necessary to eliminate or minimise the hazards that could lead to an accident, injury or occupational illness.

2.1.2. Melalui jalan yang sudah ditentukan dan kondisi area rata / through the path has been determined and the condition of the area is flat

Operator

2.1.3. Jaga jarak aman 30 meter dari unit lain yang sedan beroperasi / keep a safe distance of 30m from other units in operation

Operator 3. Memposisikan Unit

Drilling Diarea Freeface / Position The Drilling Unit In The Freeface Area

3.1. Leveling 3.1.1. Posisikan boot jack menyentuh tanah pada kondisi level waterpass / Position the boot

jack to touch the ground under the waterpass Operator, Supervisior 3.1.2. Menaikan menara secara perlahan-lahan dan

kunci pin Menara / raise the mast slowly and

lock the mast pin Operator, Supervisior

4. Melakukan Drilling Di Area Freeface / Do Drilling In The Free Face Area

4.1. Material rusak / broken material

4.1.1. Pada saat pengeboran awal kedalaman 1-2m lakukan colaring / during initial drilling 1-2m

depth does colaring. Operator, Supervisior

4.1.2. Gunakan preesure rendah pada saat proses colaring / use the low pressure during the

process colaring Operator

4.1.3. Operator selalu mengidentifikasi celah atau retakan ditanggul freeface / the operator always identifies gaps or cracks in the

freeface embankment. Operator, Supervisior

4.1.4. Pengawas selalu standby untuk memonitoring kondisi tanggul freeface / the supervisior is always standby to monitoring the freeface dike condition.

Pengawas / Supervisior

2019-02 Page 2 of 4

(3)

HMSI H&S

4.2. Freeface Longsor /

freeface landslide 4.2.1. Tanggul sudah tersedia dengan tinggi 1,2m /

embankments are available at 1,2m high Operator 4.2.2. Operator selalu mengidentifikasi celah atau

retakan ditanggul freeface / the operator always identifies gaps or cracks in the freeface embankment.

Operator

4.2.3. Pengawas standby selalu monitoring kondisi tanggul freeface / the supervisior is always standby to monitoring the freeface dike condition.

Pengawas / Supervisior

PROJECT: JOB DESCRIPTION: PAGE 3 OF 4

SEQUENCE OF BASIC JOB STEPS POTENTIAL HAZARDS RECOMMENDED ACTION OR PROCEDURE WHO Break the job down into steps. Each of

the steps should accomplish some major task and be logical.

Identify the hazards associated with each step. Examine each to find possibilities that could lead to an accident.

Using the first two columns as a guide, decide what actions are necessary to eliminate or minimise the hazards that could lead to an accident, injury or occupational illness.

5. Selsai Mengebor Lubang /

After Drilling A Hole 5.1. Menaikan pipa dari lubang (Rod Bengkok) / raise the pipe from the hole (Rod Crooked)

5.1.1. RHU terpasang dan berfungsi dengan baik /

RHU is installed and functioning properly. Operator

5.1.2. Pipa kedua sudah tersimpan di loader atau karosel / the second pipe is stored in loader or

karosel. Operator

5.1.3. Pipa utama sudah terinstal dengan topsub / the main pipe has been installed with topsub

Operator 5.1.4. Tarik ke atas kepala rotary sampai posisi

crown / Pull up rotary head to crown position Operator 5.1.5. Semua jack sudah terangkat./ all jack has

been lifted

Operator 6. Pindah Titik Bor / Move

Drill Point 6.1. Interaksi dengan unit lain /

Interaction with other units 6.1.1. Komunikasi dua arah melalui radio dan di pandu oleh spotter / two-way communication via radio and spotter guides.

Operator

6.1.2. Melipat mast jika di perlukan (kondisi permukaan tanah tidak rata) / fold the mast if needed (uneven ground condition)

Operator

2019-02 Page 3 of 4

(4)

HMSI H&S

6.1.3. Jalan yang akan di lalui aman dan stabil / the

road to be passed is safe and stable. Operator 6.1.4. Penerangan yang cukup apabila bekerja di

malam hari / adequate lighting, if working at night.

Pengawas / Supervisior

7. Jika Terjadi Keadaan

Darurat 7.1. Insident / ketidaksesuaian 7.1.1. Jika terjadi keadaan darurat atau insiden segera Menghubungi Chanel 05 melalui radio, dan nomor 085753930333 TCI

Semua Pekerja

2019-02 Page 4 of 4

Referensi

Dokumen terkait

EBOOK Occupational Health & Safety Practitioner, JOB SAFETY ANALYSIS  28. EBOOK

Potensi bahaya pada kegiatan penambangan dan perawatan alat gali muat berdasarkan metode Job Safety Analysis memiliki tingkat risiko yang berbeda-beda yaitu pada

Field research involving core drilling methods applied in the area of Sungai Batu Archaeological Complex with the main purpose of obtaining primary data related

Fire Watcher in Place Gas Tested Safety Harness Other Protective Equipment Job Leader/Supv. In Place Job Safety Analysis in Place Pre Job

This project is basically to test whether graphene material enhancement can give a significant improvement to the conventional oil based drilling fluid it terms of its rheological

Original Article Comparison of Implant Stability Using Resonance Frequency Analysis: Osteotome versus Conventional Drilling Rokhsareh Sadeghi1, Amir Reza Rokn2, Asghar Miremadi3

In order to speed up the progress of exploration and development, the main influence factors of ROP are studied in Yuanba area and the matching drilling technologies and tools are

This document provides an overview of Job Safety Analysis (JSA), a systematic method for identifying hazards in the workplace, evaluating risks, and determining appropriate control