STEAM TURBINE ROTOR RUNOUT INSPECTION REPORT

PROJECT NO. : P-03930

CUSTOMER : PT. HAGA JAYA MANDIRI MFR/MODEL : GEC ALSTHOM / 100 MW S/N & EQUIPMENT NO : TBA / UNIT #2

REPORT NO. : FNL-01

INSPECTED BY: FNA DATE: NOVEMBER 02, 2022

STATUS: AS RECEIVED OTHERS/…………. FINAL SURFACES: RADIAL AXIAL UNITS: 1/100 MILLIMETERS 1/10,000 INCHES

NOTE:

1. ALL PHASE ANGLE RECORDED : CCW AS VIEWED FROM C/E 2. ZERO DEGREE POINTS IS: MARK “0” ON C/E

3. ROTOR/SHAFT/PART IS SUPPORTED BY: V-BLOCKS RTS

APPROVED BY: ASP

POS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

0° 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

45° -2 -0.5 0.5 0.5 1 -1 0.5 0 0 1 2 4 2 1 1 2 -1 -1.5 0 -0.5 -3 0

90° -2.5 -0.5 -1.5 0.5 1 -1 0 0.5 0.5 -1 1 6 3 2 1.5 2 -0.5 -2 -0.5 -0.5 -3 0

135° -2.5 -0.5 0 0.5 1 -0.5 1 1 1 -1 1 8 3 0.5 0 1 0 -1.5 -0.5 -0.5 -0.5 1

180° -2 -0.5 0 0.5 1.5 -1 1 0.5 1 0 2 3 5 2 0 1 0.5 -0.5 0.5 0.5 -1 1

225° -0.5 0 -1 0 1.5 1 -1 -0.5 0 -0.5 1 3 3 2 -0.5 1 -1 -1 0.5 0.5 -2 0

270° 0 0 -2 0 1 2 0.5 0 0 -1 0 0 0 2 0 0.5 -0.5 -1.5 -0.5 -0.5 -1 0

315° 0 0 -1 0 0.5 2 -1 0 0 0 0 0 0 0.5 -0.5 0 0 -2 -0.5 -0.5 1 1.5

TIR 2.5 0.5 2.5 0.5 1.5 3 2 1.5 1 2 2 8 5 2 2 2 1 2 1 1 4 1.5

T/E C/E

1 2

3 4 5 6 7 8

10 11

16 13

17 18 19 7

20

21 9

12 14 15

22

(2)

PRODUCTION Form

This material is the exclusive property of PT. Sulzer Indonesia

PRO-01FR-56 Rev.04 Page 2 of 2

STEAM TURBINE ROTOR RUNOUT INSPECTION REPORT

PROJECT NO. : P-03930

CUSTOMER : PT. HAGA JAYA MANDIRI MFR/MODEL : GEC ALSTHOM / 100 MW S/N & EQUIPMENT NO : TBA / UNIT #2

REPORT NO. : FNL-01

INSPECTED BY: FNA. DATE: NOVEMBER 02, 2022

STATUS: AS RECEIVED OTHERS/…………. FINAL SURFACES: RADIAL AXIAL UNITS: 1/100 MILLIMETERS 1/10,000 INCHES

NOTE:

1. ALL PHASE ANGLE RECORDED : CCW AS VIEWED FROM C/E 2. ZERO DEGREE POINTS IS: MARK “0” ON C/E

3. ROTOR/SHAFT/PART IS SUPPORTED BY: V-BLOCKS RTS

APPROVED BY: ASP

POS A B C D E F

0° 0 0 0 0 0 0

45° -0.5 0 0 0 0 0

90° -1 0 1 0 1 0

135° -1 0 1 0 0 0

180° 0.5 0 -1 -1 -1 -2

225° 0.5 -1.5 -1 -1 -1 -2

270° 1 -1.5 0 0 0 -2

315° 0 -2 -1 -1 -2 -1

TIR 2 2 2 1 3 2

T/E C/E

C B

F A

D E

Referensi

Dokumen terkait

Jadi pengertian "Perancangan Sistem Propulsi LNG Carrier Menggunakan Dual Fuel Diesel -Electric Sebagai Pengganti Steam Turbine Ditinjau Dari Aspek Teknis dan

Based on the results and discussion of it can show as follows: Changes in methods of soft contact lens inspection process that was originally performed by manual processes first

Results at the Sterelizer Station Boiling Strelizier is a tool for processing oil palm fruit by utilizing saturated steam power from the ex turbine to boil fresh fruit bunches FFB in

In this study, a quantitative MSA test was performed on the inspection results of a 10 pieces sample of the refinery distillation tower and qualitative MSA test on the results of the

The document outlines the results of statistical analyses performed on two variables and provides detailed information regarding the analysis process and

A Study Analysis of Micro-Hydro Powerplant MHPP Potential from Cooling of Steam Turbine Yayak Triasdian PLN Unit Pelaksana Pembangkitan Timor, PT PLN Persero Unit Induk Wilayah

This paper presents the preliminary design of an Archimedean screw turbine prototype for remote area power supply, with governing equations and a comparison between theoretical and experimental

The document presents a study on an energy harvesting system using a solar ORC system and Archimedes Screw Turbine (AST) combination with different refrigerant working