• Tidak ada hasil yang ditemukan

MATERIAL REQUIREMENT PLANNING (MRP)

N/A
N/A
Teuku M

Academic year: 2023

Membagikan "MATERIAL REQUIREMENT PLANNING (MRP)"

Copied!
15
0
0

Teks penuh

(1)

MATERIAL

REQUIREMENT PLANNING (MRP )

Sabtu, 9 Desember 2023

(2)

Material Requirement Planning

⊡ Metode Lot For Lot (LFL)

⊡ Metode Economic Order Quantity (EOQ)

⊡ Metode Period Order Quantity (POQ)

⊡ Metode Least Unit Cost (LUC)

⊡ Metode Least Total Cost (LTC)

⊡ Metode Part Period Balancing (PPB)

(3)

DATA YANG DIGUNAKAN (LAMPIRAN)

⊡ Data Hasil Peramalan

⊡ Data Struktur Produk

Bill Of Material (BOM)

Item Master Record

(4)

STRUKTUR PRODUK

(5)

BILL OF MATRIAL (BOM)

Level Kode Item Nama Komponen Jumlah Harga/unit Total

0 A1 Tamiya 1 Rp 30.000 Rp 30.000

1

B1 Body 1 Rp 5.900 Rp 5.900

B2 Chassis Rangka 1 Rp 5.750 Rp 5.750

B3 Ban 4 Rp 500 Rp 2.000

B4 Pengunci 1 Rp 400 Rp 400

2

C1 Penutup Gear Depan 1 Rp 1.400 Rp 1.400

C2 Penutup Gear Belakang 1 Rp 1.500 Rp 1.500

C3 Pengikat Baterai 1 Rp 850 Rp 850

C4 Ash 2 Rp1.500 Rp3.000

3

D1 Dinamo 1 Rp 5.000 Rp 5.000

D2 Gear Depan 1 Rp 600 Rp 600

D3 Gear Belakang 1 Rp 700 Rp 700

D4 Gardan 1 Rp 900 Rp 900

D5 Plat tembaga Depan 1 Rp 1.600 Rp 1.600

D6 Switch On-Off 1 Rp 400 Rp 400

(6)

ITEM MASTER RECORD

No Kode

Item Keterangan Lot Sizing Ongkos Pesan (Rp/Pesan)

Ongkso Simpan (Rp/Pesan)

Lead time (Bulan)

Harga Satuan

1 A1 Tamiya LFL 130.000 65 1 Rp 30.000

2 B1 Body LTC, LUC, EOQ,

POQ, PPB 130.000 65 1 Rp 5.900

3 B2 Chassis Rangka LFL 130.000 65 1 Rp 5.750

4 B3 Ban LFL 130.000 65 1 Rp 500

5 B4 Pengunci LTC, LUC, EOQ,

POQ, PPB 130.000 65 1 Rp 400

6 C1 Penutup Gear

Depan LFL 130.000 65 1 Rp 1.400

7 C2 Penutup Gear

Belakang LFL 130.000 65 1 Rp 1.500

8 C3 Penutup Baterai LTC, LUC, EOQ,

POQ, PPB 130.000 65 1 Rp 850

9 C4 Ash LTC, LUC, EOQ,

POQ, PPB 130.000 65 1 Rp1.500

10 D1 Dinamo LTC, LUC, EOQ,

POQ, PPB 130.000 65 1 Rp 5.000

(7)

LOT FOR LOT (LFL)

0 1 2 3 4 5 6 7 8 9 10 11 12

GR 548 812 826 841 855 870 886 901 917 933 950 967

SR 548

POH 0 0 0 0 0 0 0 0 0 0 0 0 0

PoRec 548 812 826 841 855 870 886 901 917 933 950 967

PoRel 812 826 841 855 870 886 901 917 933 950 967

(8)

ECONOMIC ORDER QUANTITY (EOQ)

0 1 2 3 4 5 6 7 8 9 10 11 12

GR 812 826 841 855 870 886 901 917 933 950 967

SR 6421

POH 5609 4783 3942 3087 2217 1331 430 5934 5001 4051 3084

PoRec 6421 6421

PoRel 6421

(9)

PERIOD ORDER QUANTITY (POQ)

0 1 2 3 4 5 6 7 8 9 10 11 12

GR 812 826 841 855 870 886 901 917 933 950 967

SR 5991

POH 5179 4353 3512 2657 1787 901 0 2850 1917 967 0

PoRec 5991 3767

PoRel 3767

EOQ = = = 6420,59 ≈ 6421 unit

N = = = 1,6 POQ = = 6,8 ≈ 7

(10)

LEAST UNIT COST (LUC)

Periode Jumlah Order

Ongkos

Pesan Ongkos Simpan Ongkos

Total

Ongkos Per Unit

1 812 130.000 0 130.000 160,10

1 - 2 1638 130.000 826 × 65 = 53690 183.690 112,14

1 - 3 2479 130.000 (826×65)+(841×130)= 163020 293.020 118,20

3 841 130.000 0 130.000 154,58

3 - 4 1696 130.000 855 × 65 = 55575 185.575 109,42

3 - 5 2566 130.000 (855×65)+(870×130)= 168675 298.675 116,40

5 870 130.000 0 130.000 149,43

5 - 6 1756 130.000 886 × 65 = 57590 187.590 106,83

5 - 7 2657 130.000 (886×65)+(901×130)= 174720 304.720 114,69

7 901 130.000 0 130.000 144,28

7 - 8 1818 130.000 917 × 65 = 59605 189.605 104,29

7 - 9 2751 130.000 (917×65)+(933×130)= 180895 310.895 113,01

9 933 130.000 0 130.000 139,34

9 - 10 1883 130.000 950 × 65 61750 191.750 101,83

9 - 11 2850 130.000 (950×65)+(967×130)= 187460 317.460 111,39

11 967 130.000 0 130.000 134,44

(11)

LEAST UNIT COST (LUC)

0 1 2 3 4 5 6 7 8 9 10 11 12

GR 812 826 841 855 870 886 901 917 933 950 967

SR 1638

POH 826 0 855 0 886 0 917 0 950 0 0

PoRec 1638 1696 1756 1818 1883 967

PoRel 1696 1756 1818 1883 967

(12)

LEAST TOTAL COST (LTC)

Periode Jumlah Order

Periode

Simpan Ongkos Periode Simpan Kumulatif Ongkos

1 812 0 0 0

2 826 1 826 × 65 × 1 = 53.690 53.690

3 841 0 0 0

4 855 1 855 × 65 × 1 = 55.575 55.575

5 870 0 0 0

6 886 1 886 × 65 × 1 = 57.590 57.590

7 901 0 0 0

8 917 1 917 × 65 × 1 = 59.605 59.605

9 933 0 0 0

10 950 1 950 × 65 × 1 = 61.750 61.750

11 967 0 0 0

(13)

LEAST TOTAL COST (LTC)

0 1 2 3 4 5 6 7 8 9 10 11 12

GR 812 826 841 855 870 886 901 917 933 950 967

SR 1638

POH 826 0 855 0 886 0 917 0 950 0 0

PoRec 1638 1696 1756 1818 1883 967

PoRel 1696 1756 1818 1883 967

(14)

PART PERIOD BALANCING (PPB)

Periode Jumlah Order

Periode

Simpan Bagian Periode Simpan Kumulatif Bagian

1 812 0 0 0

2 826 1 826 826

3 841 0 0 0

4 855 1 855 855

5 870 0 0 0

6 886 1 886 886

7 901 0 0 0

8 917 1 917 917

9 933 0 0 0

10 950 1 950 950

EPP = = = 2000 unit/periode

(15)

PART PERIOD BALANCING (PPB)

0 1 2 3 4 5 6 7 8 9 10 11 12

GR 812 826 841 855 870 886 901 917 933 950 967

SR 1638

POH 826 0 855 0 886 0 917 0 950 0 0

PoRec 1638 1696 1756 1818 1883 967

PoRel 1696 1756 1818 1883 967

Referensi

Dokumen terkait

Tujuan penelitian ini adalah melakukan analisis metode Material Requirement Planning (MRP) yang diawali dengan menganalisis jadwal produksi induk,

Material Requirement Planning (Rencana Kebutuhan Bahan) pada Pennyellow Furniture adalah sebagai berikut: bahan baku berupa rotan sintetis, pipa alumunium, dan aksesoris

Perhitungan pada metode LUC mirip dengan Silver Meal, bedanya adalah Silver Meal dalam pemilihan lot size yang optimal dengan melihat biaya paling minimum dari setiap

Berdasarkan perhitungan teknik Lot Sizing bahan baku Nalco Water Treatment dengan menggunakan metode Economic Order Quantity (EOQ), Least Unit Cost (LUC), dan metode

Kaibon Indah untuk memproduksi tea set adalah dengan menerapkan metode Material Requirement Planning dengan pendekatan lot for lot apabila perusahaan ingin menekan

Mulai dari metode analisis persediaan yang digunakan dalam penelitian ini adalah peramalan, Lot-For-Lot LFL, Economy Order Quantity EOQ, serta menggunakan rumus peramalan Exponential

Dari hasil perbandingan ketiga metode lot sizing diatas dapat disimpulkan bahwa metode yang paling baik dipergunakan adalah metode Period Order Quantity POQ karena perhitungan metode

Kapasitas Gudang Hasil Perhitungan Teknik Lot Sizing Dengan mengunakan 5 lima metode teknik Lot Sizing yaitu metode Fixed Order Quantity FOQ, Economic Order Quantity EOQ, Periodic