BAHAGIAN : 3.0 - KOS ITEM-ITEM KERJA

SUB-BAHAGIAN : 3.10 - BRICKWORK,BLOCKWORK AND MASONRY

Kawasan A - Perlis, Kedah & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - Pahang

Kawasan C - WP.KL.,Selangor Kawasan F - Terengganu N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Brickwork

1 115 mm Thick common brickwork laid and jointed in 1 : 3 M2 - - - 22.00 - - - 22.00

cement mortar with and including brick reinforcement at every fourth course.

2 230 mm Thick ditto M2 - - - 40.00 - 40.00

3 230 mm Thick ditto as a build-up wall to the road side M2 - - - 30.00 - 37.20 30.00 - 37.20

block drain. 42.00 42.00

4 338 mm Thick ditto M2 - - - 44.00 - 44.00

5 230 mm Thick brick retaining wall including 20 mm thick M2 - - - 60.00 - - - 60.00

cement plaster on exposed surfaces.

6 To construct brick sump of 1250 mm x 1250 mm internal No - - - 700.00 - - - 700.00

dimension with 150mm thick reinforced concrete base and 230 mm thick brickwall for a height not exceeding 1 m.

7 Ditto for a height exceeding 1 m but not exceeding 1.50 m. No - - - 1000.00 - - - 1000.00

8 Ditto for a height exceeding 1.5 m but not exceeding 2.00 m. No - - - 1,300.00 - - - 1,300.00

c: brick

KAWASAN A KAWASAN B KAWASAN C KAWASAN D KAWASAN E KAWASAN F KESELURUHAN

(2)

BAHAGIAN : 3.0 - KOS ITEM-ITEM KERJA

SUB-BAHAGIAN : 3.10 - BRICKWORK,BLOCKWORK AND MASONRY

Kawasan A - Perlis, Kedah & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - Pahang

Kawasan C - WP.KL.,Selangor Kawasan F - Terengganu N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Brickwork ( cont'd )

9 Brickwork sump size 1360 mm x 1360 mm plastered with No - - - 1,100.00 - 1,100.00

cement and sand (1:3) plaster mixed with approved plasticiser on all exposed surfaces and including reinforced concrete bedding ( excavation measured separately ) and ready to receive inlet and outlet drains.

10 114 mm Wide horizontal damp proof course M - - - 1.00 - - - 1.00

11 6 mm x 450 mm Long MS tie No - - - 0.50 - - - 0.50

12 Weephole to 230 mm Thick brickwork No - - - 3.00 - 3.40 3.00 - 3.40

3.80

3.80

c: brick

KAWASAN A KAWASAN B KAWASAN C KAWASAN D KAWASAN E KAWASAN F KESELURUHAN

(3)

BAHAGIAN : 3.0 - KOS ITEM-ITEM KERJA

SUB-BAHAGIAN : 3.10 - BRICKWORK,BLOCKWORK AND MASONRY

Kawasan A - Perlis, Kedah & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - Pahang

Kawasan C - WP.KL.,Selangor Kawasan F - Terengganu N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Masonry

1 Supply, transport and lay granite stone ( size 150 mm - 200 mm ) M3 - - - 125.00 - - - 120.00 120.00 - 122.50

for rubble wall including supply and fixing all necessary 125.00

moulding and jointing with cement mortar.

2 225 mm thick rubble pitching to sloping plane M2 45.00 - - - 40.00 40.00 - 42.50

45.00

3 250 mm thick cemented stones pitching at incline surface M2 - - - 38.00 - 38.00

otherwise filling with approved imported material to the required level and slope.

4 Supply and lay 300 mm thick cemented pitching including M2 - - - 36.00 - 36.00

100 mm diameter PVC weephole.

5 Ditto 100 mm diameter claypipe weephole. M2 - - - 60.00 - 60.00

6 Lay 300 mm thick grouted stone pitching with provision M2 - - - 60.00 - - - 60.00

for 100 mm.

7 450 mm thick rubble pitching M2 - - - 50.00 - - - 50.00

8 To supply all labour and material to construct 500 mm stone M2 - - - 60.00 - - - 60.00

pitched river revetment.

c: brick

KAWASAN A KAWASAN B KAWASAN C KAWASAN D KAWASAN E KAWASAN F KESELURUHAN

Referensi

Dokumen terkait

3.0 KOS ITEM‐ITEM KERJA 3.4 CONCRETE WORKS BIL KETERANGAN KERJA UNIT * PURATA KADAR HARGA KERJA 2008 2009 RM RM RM PURATA KADAR HARGA KERJA BAGI TAHUN F Precast Concrete 1

BAHAGIAN 3.14 : MISCELLANEOUS WORKS PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT RM RM RM RM RM RM RM RM KAWASAN TENGAH KAWASAN TENGAH KAWASAN TIMUR KESELURUHAN BIL

BAHAGIAN 3.3 : DEMOLITION & SITE CLEARANCE CLASS E KAWASAN UTARA KAWASAN TENGAH KAWASAN TIMUR KESELURUHAN PURATA KADAR HARGA 2013 RM BIL KETERANGAN KERJA UNIT Demolition and

BAHAGIAN 3.7 : CONCRETE WORK CLASS I KAWASAN UTARA KAWASAN TENGAH KAWASAN TIMUR KESELURUHAN BIL KETERANGAN KERJA UNIT PURATA KADAR HARGA 2013 RM REINFORCEMENT Mild Steel Bars

BAHAGIAN 3.6 : PILING WORK CLASS H KAWASAN UTARA KAWASAN TENGAH KAWASAN TIMUR KESELURUHAN BIL KETERANGAN KERJA UNIT PURATA KADAR HARGA 2013 RM PRECAST REINFORCED CONCRETE

BAHAGIAN 3.15 : ROADS AND PAVINGS CLASS Q KAWASAN UTARA KAWASAN TENGAH KAWASAN TIMUR KESELURUHAN BIL KETERANGAN KERJA UNIT PURATA KADAR HARGA 2013 RM 13 50mm thick asphaltic

BAHAGIAN 3.7 : CONCRETE WORK CLASS I PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT RM RM RM RM RM RM RM RM KESELURUHAN BIL KETERANGAN KERJA UNIT KAWASAN UTARA KAWASAN

KETERANGAN KERJA UNITJULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA RM RM RM RM RM RM RM RM RM RM RM RM RM RM Demolition 1 Demolition of