3.0 KOS ITEM‐ITEM KERJA

3.1 SLOPE STABILISATION & GROUND TREATMENTS

BIL KETERANGAN KERJA UNIT

*PURATA KADAR HARGA  KERJA 

2008 2009

(RM) (RM) (RM)

A Slope Stabilisation

1 Stone pitching to slope of outfall; 250mm  thick

M2 48.00 48.00 48.00

2 Supply and install approved mattress  including all necessary works

M2 81.40 79.33 80.00

3 Supply and install toe scour protection M 130.00 ‐ 130.00

4 Supply and lay approved gabion cage all  as per specified; size 1.0m x 1.0m x 2.0m

NO 450.00 ‐ 450.00

5 Supply and lay approved gabion cage all  as per specified; size 6.0m x 2.0m x  0.23m

NO 556.67 ‐ 557.00

6 Supply and lay approved gabion cage all  as per specified; size 2.0m x 1.0m x 0.5m

M2 225.00 ‐ 225.00

7 Supply and lay geotextile ‐ non woven  type

M2 21.32 41.25 31.00

8 Supply and lay graded gravel layer M3 60.33 ‐ 60.00

9 Supply and lay graded gravel layer; 

100mm ‐ 200mm

M3 53.50 ‐ 54.00

10 Supply and lay graded stones for armour  layer

M3 72.09 89.50 81.00

11 Supply and lay graded stones for armour  layer; 600 ‐ 1000kg

M3 94.00 94.00 94.00

* Purata Keseluruhan (rounded up) yang ditetapkan 8

PURATA KADAR HARGA KERJA  BAGI TAHUN

(2)

3.0 KOS ITEM‐ITEM KERJA

3.1 SLOPE STABILISATION & GROUND TREATMENTS

BIL KETERANGAN KERJA UNIT

*PURATA KADAR HARGA  KERJA 

2008 2009

(RM) (RM) (RM)

PURATA KADAR HARGA KERJA  BAGI TAHUN

12 Supply and lay graded stones for  underlayer

M3 68.00 ‐ 68.00

13 Supply and lay graded stones for  underlayer; 60 ‐ 100kg

M3 94.00 94.00 94.00

14 Supply and lay PVC coated wire mesh  gabion including all necessary works

M3 180.00 180.00 180.00

15 Supply and lay retaining structures; rock  filled gabion wall; size 1.0m x 1.0m x  1.0m high

M3 140.00 ‐ 140.00

16 Supply and lay retaining reinforced  earthwall; size 3.05m x 2.91m including  all necessary works

M2 373.77 373.77 374.00

17 Supply and lay rip rap of stone size 100 ‐  200mm

M3 100.00 100.00 100.00

18 Supply and lay rip rap of stone size  250mm

M3 100.00 ‐ 100.00

19 Supply and lay rip rap of stone size 300 ‐  400mm

M3 53.00 ‐ 53.00

* Purata Keseluruhan (rounded up) yang ditetapkan 9

Referensi

Dokumen terkait

[r]

[r]

Tujuan dari penelitian ini adalah untuk menyarankan perbaikan sistem lama yang masih konvensional dalam pemasukan kas, pengeluaran kas, dan pengambilan kas oleh pemilik

37 Tahun 2009 tentang Dosen dan Peraturan Mendiknas RI Nomor 47 Tahun 2009 tentang Sertifikasi Pendidik Untuk Dosen Proses penilaianan akhir portopolio dilakukan oleh asesor,

25 Kantor LH Broto Damaryanto Pengendali Dampak Lingkungan Pertama L Staf Kantor Lingkungan Hidup Kota Administrasi. Pusat

e) Hitung dan gambarkan sudut yang didapat pada titik A dan B, perhitungan sudutnya dimulai dan sudut kompas pembidikan ke titik A dan B. f) Dari sudut yang didapat dan

Klasifikasi Kos Klasifikasi kos dalam pandangan akuntansi manajemen antara lain: • Kos dipandang dari segi basis elemen produk: • Kos dipandang dari segi fungsional dalam perusahaan

Kegiatan usaha manufaktur dimulai dari 1 penggunaan kas atau sumber daya lain untuk membeli bahan baku, investasi pada mesin dan bangunan pabrik, dan menyewa tenaga kerja; 2 kegiatan