• Tidak ada hasil yang ditemukan

of FERTILIZER

N/A
N/A
Protected

Academic year: 2024

Membagikan "of FERTILIZER"

Copied!
51
0
0

Teks penuh

(1)

COD AND NITROGEN REMOVAL FROM FERTILIZER WASTEWATER EFFLUENT BY USING AN ENGINEERED WETLAND

by

Mohd Hafiz Bin Mohamad Hazli

Submitted in partial fulfillment of the requirements for the Bachelor of Engineering

(Civil Engineering)

Universiti Teknologi PETRONAS Bandar Seri Iskandar

31750 Tronoh Perak Darul Ridzuan Tronoh Perak Darul Ridzuan

JANUARY 2008

(2)

CERTIFICATION OF APPROVAL

COD AND NITROGEN REMOVAL FROM FERTILIZER WASTEWATER EFFLUENT BY USING AN ENGINEERED WETLAND

Approved by,

by

Mohd Hafiz Bin Mohamad Hazli

A project dissertation submitted to the Civil Engineering Programme Universiti Teknologi PETRONAS in partial fulfillment of the requirement for the

BACHELOR OF ENGINEERING (Hons) (CIVIL ENGINEERING)

u_~

(ASSOC. PROF. DR. NASIMAN SAPARI)

UNIVERSITI TEKNOLOGI PETRONAS TRONOH, PERAK

(3)

CERTIFICATION OF ORIGINALITY

This is to certifY that I am responsible for the work submitted in this project, that the original work is my own except as specified in the reference and acknowledgements, and that the original work contained herein have not been undertaken or done by unspecified sources or persons.

MOHD HAFIZ BIN MOHAMAD HAZLI

(4)

ABSTRACT

This project presents the analysis of the effectiveness of engineered wetland to tmat the effluent from the Wastewater Treatment Plant (WWTP) of Fertilizer Plant. The Chemical Oxygen Demand (COD) level of the fertilizer wastewater effluent is high, ranging from 89 to 200 mg/L with the average of 140 mg/L. This is higher than the specified discharge standard oflOO mg/L.

The objective of using this wetland system is to remove nutrients as well as other contaminants. The constructed wetland was planted with Eichhornia crassipes (floating type of plant). The model was found to be able to remove COD to 45 mg/L after 27 days of treatment (meet the discharge standard A).

The methodology of this project involves the analysis of Chemical Oxygen Demand (COD), ammonia, nitrate, nitrite and phosphorus. The flow rate for the treatment system is set at 8Liday, and the detention time is about 10 days. The result from this project shows that the wetland system with floating plant (Eichhornia crassipes) is able to remove 47% COD, 78% ammonia, 83% nitrate, 80% nitrite and 81% phosphorus after 27 days of treatment.

I

(5)

ACKNOWLEDGEMENT

Alhamdulillah, grateful to Allah s.w.t. for giving me the opportunity to complete this final year project report.

I wish to express my sincere appreciation to my supervisor, Assoc. Prof. Dr. Nasiman Sapari for guidance, encouragement, advices and critics. Without his support, this project would not have be the same as presented here.

To all lab technicians, thank you so much for helping me throughout the project work.

Thank you to Mr. Anuar, Kak Nor, Mr Meor, Mr Johan and Mr Zaini for giving me aid in my project.

My sincere appreciation also extends to all my colleagues for their support. Thank you Shafik, Alif, Shida, and to all my friends around me.

Last but not least, to my beloved family. Thank you so much for your kind support, blessing, courage and always by my side in ups and downs.

(6)

TABLE OF CONTENT

ABSTRACT... 1

TABLE OF CONTENT... 11

LIST OF FIGURES... 1v

LIST OF TABLES... v

CHAPTER 1: INTRODUCTION... I 1.1 Background of Study... . . ... I 1.2 Problem Statement... . . . ... 2

1.2.1 Problem Identification... 2

1.2.2 Significance of Project... 3

1.3 Objectives of the Study... 4

1.4. Scope of the Study... 4

1.4.1 Relevancy of Project... 5

CHAPTER 2:LITERATURE REVIEWffHEORY... 6

2.1 Literature Review... . . 6

2.1.1. Wetland... 6

2.1.2. Natural Wetland... 7

2.1.3. Constructed Wetland... 7

2.1.4. Aquatic Plants For Engineered Wetland... 12

2.1.5. Treatment Process Mechanisms... . . . 13

2.1.6. Summary of Treatment Performance in Constructed Wetland... 15

CHAPTER 3 : METHODOLOGY OR PROJECT WORK... 18

3.1 Set- Up Wetland for Fertilizer Treatment... 18

3.2. Experimental Analysis... 20

3 .2.1. Analysis of the fertilizer wastewater... 20

3.2.2. Observation of Plant Growth... 23

11

(7)

CHAPTER 4: RESULT AND DISCUSSION... 24

4.1 Introduction... 24

4.2 Pollutant Removal... 25

4.2.1 Chemical Oxygen Demand (COD)... 25

4.2.2 Ammonia Nitrogen (NH3-N)... 26

4.2.3 Nitrate Nitrogen (N03 ·-N). .. ... . . ... ... . . . ... . . . ... 27

4.2.4 Total Phosphorus (Poi·)... 27

4.3 Observation of Plant Growth... 28

CHAPTER 5: CONCLUSION AND RECOMMENDATION... 30

5.1. Conclusion... 30

5.2. Recommendations... 30

CHAPTER 6 : REFERENCES... 32

CHAPTER 7 : APPENDIX... 37

111

(8)

LIST OF FIGURES

Figure I Free water surface wetland system 9

Figure 2 Types ofFWS wetland 10

Figure 3 Subsurface flow wetland system 11

Figure 4 Types of SSF wetland 11

Figure 5 Nitrogen transformation in wetland system 15

Figure 6 The location ofthe floating plant 18

Figure 7 Flow chart of the project system 19

Figure 8 The wetland system 19

Figure 9 The equipment used inside the lab for COD test 21

Figure 10 The equipment used inside the lab for ammonia test 21 Figure 11 The equipment used inside the lab for nitrate test 22 Figure 12 The equipment used inside the lab for nitrite test 22 Figure 13 Percentage removal of COD in the control and the wetland system 25 Figure 14 Percentage removal of ammonia in the control and wetland system 26 Figure 15 Percentage removal of nitrate nitrogen in the control and wetland system 27 Figure 16 Percentage removal of phosphorus in the control and wetland system 27 Figure 17 Root length of the wetland plant, plant from section 1 29 Figure 18 The initial weight of the wetland plant in section 1 29 Figure 19 Graph of the COD concentration of influent, wetland and control system 42

in 27 days of experiment

Figure 20 Graph of the ammonia concentration of influent, wetland and control 42 system in 27 days of experiment

Figure 21 Graph of the nitrate concentration of influent, wetland and control 43 system in 27 days of experiment

Figure 22 Graph of the nitrite concentration of influent, wetland and control 43 system in 27 days of experiment

Figure 23 Graph of the total phosphorus concentration of influent, wetland and 44 control system in 27 days of experiment

IV

(9)

1.0 INTRODUCTION

CHAPTER I INTRODUCTION

1.1 Background of Study

This project is based on the topic- organic matter and nutrient removal of fertilizer wastewater by using an engineered wetland. Treatment cost, less maintenance and environmental friendly are some of the main target in choosing the treatment system for the wastewater. Constructed wetland (e.g. by using the floating plants) emerged as one of the potential treatment to remove pollutants from the wastewater. The use of wetlands to treat fertilizer wastewater is a relatively new compared to the conventional treatment systems. This wetland will create an additional natural aquatic system which could be part of the local environment.

The constructed wetland systems may be described as "engineered" if the system involved:

a) design modifications,

b) process additions or modifications, and c) vegetation modifications.

1

(10)
(11)
(12)
(13)
(14)
(15)
(16)
(17)
(18)
(19)
(20)
(21)
(22)
(23)
(24)
(25)
(26)
(27)
(28)
(29)
(30)
(31)
(32)
(33)
(34)
(35)
(36)
(37)
(38)
(39)
(40)
(41)
(42)
(43)
(44)
(45)
(46)
(47)
(48)
(49)
(50)
(51)

Referensi

Dokumen terkait

v LIST OF FIGURES Figure 1 HydroView Max TM 5 Figure 2 Flowchart of the Project 9 Figure 3 Milestones 11 Figure 4 Overview of Control System for Pitch Angle 13 Figure 5

LIST OF FIGURES Figure 1: Microphone Structure 5 Figure 2: Pressure Microphone versus Free-Field Microphone 6 Figure 3: Testing Workbench 11 Figure 4: DAQ Equipment Detail 12

List of Figures Figure 1-1 Schematics of various MSR concepts Figure 1-2 Multiphysics system of liquid-fueled molten salt reactor Figure 2-1 Comparison of flow chart for sensitivity

xii List of Figures Items Figure Caption Page Figure 1.1 Heat transfer system 2 Figure 1.2 Nanoparticles 3 Figure 1.3 Nanofluids mechanism 4 Figure 1.4 Different types of

LIST OF FIGURES Figure 2.1 Simplified process flow diagram of methanol processing in PML Figure 2.2 Relative activities of typical copper/ zinc oxide under poisons free conditions

©Daffodil International University VII LIST OF FIGURES FIGURES PAGE NO Figure 3.1: List of features of the dataset 10 Figure 3.2: Research methodology 11 Figure 4.1: Heatmap

LIST OF FIGURES Figure 1: FreeRTOS directory structure...7 Figure 2: State transitions [17]...8 Figure 3: FreeRTOS scheduling [6]...9 Figure 4: Flow chart of the system

LIST OF FIGURES Figure 2.1 Sinusoidal Current Response in Linear System 10 Figure 2.2 Nyquist Plot with Impedance Vector 11 Figure 3.1 Step by step procedure for sample preparation