I NVITATION TO B ID

To come up with a Water Resource Plan for the design and construction of two units drinking water system at KSU Bulanao Campus;. ii) Conduct underground water survey for the most feasible location of the underground source for the two-unit drinking water system;. iii). Prepare detailed cost estimates for the construction of a two-unit drinking water system; vi).

I NSTRUCTIONS TO B IDDERS

Bidder's SLCC statement similar to the contract to be offered, in accordance with ITB Clause 5.4. Any other document related to the financial component of the offer as stated in the BDS. a). Unless otherwise specified in the BDS, payment of the contract price shall be made in Philippine Pesos.

B ID D ATA S HEET

The name of the contract is construction of two (2) units of drinking water system - Bulanao Campus. The Government of the Philippines (GoP) through General Budget Act (GAA) Capital Outlay CY 2017 duly approved by the Board of Regents through Board Resolution No. The name of the project is Design and Construction of Two-Unit Drinking Water System at KSU Bulanao Campus.

5.4(b) For this purpose, similar contracts shall refer to contracts which have the same main categories of work as the design and construction of water systems or the design and construction or installation of water facilities. Note: All key personnel must have General and Relevant Experience applicable and defined in their line of specializations. Amount of not less than Php e ABC), if the bid security is in cash, cashier's/manager's check, bank draft/guarantee or irrevocable letter of credit;.

NOTE: The parent envelope must be wrapped in a black plastic bag when dropped off at the KSU Bid Box located in front of the BAC Office, 2/F Admin Bldg., Main Campus.

G ENERAL C ONDITIONS OF C ONTRACT

All materials and equipment on site are considered the property of the client. The contractor will follow all the instructions of the client's representative, which are in accordance with the applicable legislation where the location is located. The performance bond remains valid until the client issues a certificate of final acceptance.

All drawings prepared by the contractor for the performance of the temporary works are subject to prior approval by the contracting authority's representative before being used. The approval of the contracting authority's representative does not diminish the responsibility of the contractor for the design of the temporary work. The Contractor shall obtain third party approval for the design of the Agency Work, if required by the Contracting Authority.

Each completed form must be verified and signed by the contracting entity's representative within two days of completion of the work. The approval of the work program by the contracting entity's representative does not change the contractor's obligations. Such request for payment must be verified and certified by the procuring entity's representative/project engineer.

The Contractor shall submit monthly statements of the estimated value of the work performed less the cumulative amount previously certified to the Procuring Entity's Representative.

S PECIAL C ONDITIONS OF C ONTRACT

To provide signed and sealed structural analysis, structural details, drawings, plans and specifications relating to the construction of two units drinking water system;. v). Integrate solar panel system or windmill as a form of alternative electrification for the operation of this proposed two-unit drinking water system; And. VII). To build two units of drinking water system at Bulanao Campus that will provide an uninterrupted supply of water, sufficient water pressure, a water quality free of unpleasant taste, turbidity, odor or chemical attack and water that is bacteriologically safe to drink and easily accessible to Kalinga State University end users.

NOTE: Names of key personnel and their appointment to be completed by the winner before signing the contract. 7.4(c) The performance bond covers the period from the signing of the contract to the final acceptance of the project by the government, subject to the warranty period as prescribed in Sec. For this reason, the performance bond cover must include a one (1) year defect liability period and will only be released when the client issues a final acceptance certificate.

The amount to be withheld for late submission of an updated Work Program is at least equal to one-tenth of one percent (0.001) of the actual cost of contract for each day of delay. The date on which "as built" drawings are required is upon approval of the variation orders.

S PECIFICATIONS

The architectural drawings and details to be approved shall be the general reference in the structural, electrical and sanitary design of the construction of the two unit potable water system. The design development drawings for the proposed two-unit water system at KSU Bulanao Campus shall be included in the bidder's technical proposal. All communications about this project should be addressed to the President of Kalinga State University.

Master's or Ph.D in Civil/Structural Engineering or recognized as a Civil Engineer by PICE or Civil Engineers Association of the Philippines. This must refer to the natural plane or the identified final floor lines of adjacent existing buildings. The proposed building must also be designed using a wind importance factor of 1.15, particularly in the design of the roof system and building supports.

Soil drilling and survey (at least three drilling sites) should be performed to estimate the bearing capacity of the soil that will be used in the design of the building's foundation. Reference: Revised Implementing Rules and Regulations of the National Building Code of the Philippines (PD 1096).

D RAWINGS

B ILL OF Q UANTITIES

Our firm, including any subcontractor or supplier for any part of the Contract, is a national of the following eligible countries: [insert information];. We also certify/confirm that the undersigned is the duly authorized representative of the bidder and has been given full power and authority to do, execute and perform any and all acts necessary to participate, submit the bid and to sign and execute the following contract. for [Project Name] of [Procuring Entity Name]. k). Bidder's Name] authorizes the Head of the Procuring Entity or his regularly authorized representatives to verify all submitted documents.

Upon expiration of the bid's validity period or any extension thereof pursuant to your request;. Duly certified statements of all potential joint venture partners in accordance with Section 23.1(b) of the IRR. Made an estimate of the facilities available and necessary for the contract to be awarded, if any; and.

Note: Any missing document in the above checklist is grounds for outright rejection of the offer. Note: Any missing document in the above checklist is grounds for outright rejection of the offer.

B IDDING F ORMS

G ENERAL

  • Scope of Bid
  • Source of Funds
  • Corrupt, Fraudulent, Collusive, Coercive, and Obstructive Practices
  • Conflict of Interest
  • Eligible Bidders
  • Bidder’s Responsibilities
  • Origin of Goods and Services
  • Subcontracts

Unless otherwise specified in the BDS, the Bidder may subcontract portions of the Works to the extent approved by the Procuring Entity and stated in the BDS. In the event that any subcontractor is found by the Procuring Entity to be ineligible, the subcontracting of such portion of the Works shall not be permitted.

C ONTENTS OF B IDDING D OCUMENTS

  • Pre-Bid Conference
  • Clarification and Amendment of Bidding Documents

The Bidder may designate a subcontractor to whom it will subcontract part of the work at any stage of the bidding process or during the execution of the contract. Any supplemental/offer bulletin issued by the BAC shall also be posted in the PhilGEPS and on the website of the concerned procuring entity, if available, and in any conspicuous place on the premises of the concerned procuring entity.

P REPARATION OF B IDS

  • Language of Bids
  • Documents Comprising the Bid: Eligibility and Technical Components
  • Documents Comprising the Bid: Financial Component
  • Alternative Bids
  • Bid Prices
  • Bid Currencies
  • Bid Validity
  • Bid Security
  • Format and Signing of Bids
  • Sealing and Marking of Bids

Unless otherwise stated in the BDS, the financial part of the offer must contain the following: The Bidder must fill in prices and rates for all parts of the Works described in the Bill of Quantities.

S UBMISSION AND O PENING OF B IDS

  • Deadline for Submission of Bids
  • Late Bids
  • Modification and Withdrawal of Bids
  • Opening and Preliminary Examination of Bids

No bid may be withdrawn in the interval between the deadline for submission of bids and the expiry of the bid validity period specified by the Bidder on the Financial Bid Form. The notice must be issued within seven (7) calendar days from the date of the bid opening.

E VALUATION AND C OMPARISON OF B IDS

  • Process to be Confidential
  • Clarification of Bids
  • Detailed Evaluation and Comparison of Bids
  • Post Qualification
  • Reservation Clause

The Procuring Entity must prepare the minutes of the proceedings of the bid opening which shall include at least: (a) names of Bidders, their bid price (per lot, if applicable, and/or including rebate, if any), bid security, findings of preliminary investigation, and whether there is a withdrawal or amendment; and (b) attendance sheet. When applicable, the BAK will conduct a post-qualification of the Bidder with the next Lowest Calculated Bid.

A WARD OF C ONTRACT

  • Contract Award
  • Signing of the Contract
  • Performance Security
  • Notice to Proceed
  • Protest Mechanism

If the funding source for the project has been withheld or reduced through no fault of the contracting entity. The Completion Date is the date of completion of the Works as certified by the Contracting Entity's representative in accordance with GCC Clause 49. The Contractor shall submit to the Employer for consent the name and details of the person authorized to receive instructions on behalf of the Contractor.

The performance security provided in favor of the client shall be forfeited if the contractor is found to be in breach of any of its obligations under the contract. The performance security may be released by the client and returned to the contractor after the issuance of the certificate of final acceptance under the following conditions: From the start date until the certificate of final acceptance is issued, the following risks are for the contracting entity:. one).

The Procuring Entity will terminate this contract for non-payment when any of the following conditions attend its implementation:. In the event of the Contractor's insolvency, any Contractor's Equipment that the Procuring Entity instructs in the notice must be used until the completion of the Works;. All decisions recommended by the CTRC shall be subject to the approval of the HoPE.

In the absence of the CPES assessment form, the contracting authority's existing performance monitoring system will be applied. The contracting authority's representative may require the contractor to provide an estimate of the expected effect of the future event or condition on the contract price and completion date. The first installment payment may be made by the contracting authority to the contractor, provided that at least twenty percent (20%) of the work has been completed, as certified by the contracting authority's representative.